Energy Co-ordination and Planning Act 1995
8IApproval of HRL recovery plan
Start here
Get a plain-English read of 8I
Turn the raw legal text into a practical explanation grounded in Energy Co-ordination and Planning Act 1995.
8I Approval of HRL recovery plan
(1) On receipt of an HRL recovery plan, the Assessor is to provide the Co-ordinator with a copy of the plan.
(2) The Co-ordinator must review the HRL recovery plan.
(3) In reviewing an HRL recovery plan, the Co-ordinator may require information from any person or body that the Co-ordinator considers relevant.
(4) If the Co-ordinator is not satisfied that the HRL recovery plan adequately addresses the matters referred to in section 8H , the Co-ordinator is to liaise with Hydro to rectify any deficiencies in the HRL recovery plan.
(5) Once any deficiencies in the HRL recovery plan have been rectified to the Co-ordinator’s satisfaction, the amended HRL recovery plan is to be submitted to the Assessor.
(6) If an amended HRL recovery plan is submitted to the Assessor, the Assessor is to provide the Co-ordinator with a copy of the amended HRL recovery plan for review.
(7) If the Co-ordinator is satisfied that the HRL recovery plan, whether as amended or not, adequately addresses the matters referred to in section 8H , the Co-ordinator is to –
(a) approve the HRL recovery plan; and
(b) advise Hydro, the Assessor and the Minister of that approval.