13 Interpretation of Part
[Regulation 13 Inserted by S.R. 2021, No. 132, Applied:01 Jan 2022]
(1) In this Part –
applicant, in relation to an application, means the person who made the application;
application means an application for a permit for a development or use that requires a relevant entity to make a connection to relevant electricity infrastructure;
assessment stage means the stage of works that includes –
(a) the assessment or determination of the scope of the works; and
(b) the issue of a letter of response;
connection letter of offer means a letter, issued by a relevant entity to an applicant, that confirms the details of the design stage of the works to which the applicant’s application relates;
connection stage means the stage of works that includes –
(a) the construction of relevant electricity infrastructure, to a point of supply that has been agreed between the relevant entity and the applicant; and
(b) the inspection and approval of relevant electricity infrastructure, including infrastructure for connections, that has been constructed as part of the works; and
(c) notification that the works are completed being given to the applicant, or the retailer, by the relevant entity;
design stage means the stage of works that includes –
(a) the design of the works; and
(b) the checking of the design of the works; and
(c) the approval of the design of the works; and
(d) the issue of a connection letter of offer;
means works that –