Electricity Supply (General) Regulation 2026
9Time limit for de-energisation
Start here
Get a plain-English read of 9
Turn the raw legal text into a practical explanation grounded in Electricity Supply (General) Regulation 2026.
9 Time limit for de-energisation
9 Time limit for de-energisation
(1) A distributor must de-energise a small customer’s premises within—
(a) 2 days after being notified by the customer’s retailer of the customer’s request for de-energisation, or
(b) the longer period requested by the customer and notified to the distributor by the retailer.
(2) A distributor must de-energise a small customer’s premises within 2 days, not including a protected period, after being notified by a retailer that the retailer requires de-energisation of the premises on a ground permitted under the retail rules.