123 Revocation of approval
123 Revocation of approval
(1) The Minister may revoke the approval of an approved facility if satisfied—
(a) the facility is no longer used to produce green hydrogen, or
(b) production of green hydrogen at the facility has not commenced before 1 January 2030, or
(c) the prescribed person who uses the facility—
(i) failed, within 2 years of the approval of the facility, to become a party to a connection agreement or connection contract with a network service provider in relation to a connection point specified in the Minister’s order, or
(ii) has not complied with a notice under section 118, or
(iii) made a statement under section 122(2)(b) that, when the statement was made, was false, or
(iv) has not complied with section 122(6),
(d) an eligible person who uses the facility has ceased to be an eligible person.
(2) In this section—
prescribed person, for a facility, means the person who—
(a) uses the facility to produce green hydrogen, or
(b) was the eligible person who applied for approval of the facility.