Electricity Supply (General) Regulation 2014
65HModification relating to offers to connect
Start here
Get a plain-English read of 65H
Turn the raw legal text into a practical explanation grounded in Electricity Supply (General) Regulation 2014.
65H Modification relating to offers to connect
65H Modification relating to offers to connect
The National Electricity Rules, rule 5.3.6 is taken to include the following paragraph—
(b6) If a customer has notified a network service provider that the customer intends to produce green hydrogen, the offer to connect made under paragraph (a) must include—
(1) if the network service provider has determined that the connection of the customer’s load will not require augmentations or alterations to affected networks, other than augmentations or alterations involving connection assets or augmentations or alterations that the customer will pay for (excluded augmentations)—a statement to that effect, or
(2) if the network service provider proposes to impose power transfer limitations or load control arrangements to enable the network service provider to manage network constraints—
(i) a statement to that effect, including an explanation as to why the power transfer limitations or load control arrangements are necessary, and
(ii) a description of the power transfer limitations or load control arrangements, or
(3) if neither subparagraph (1) or (2) applies—a statement that, and an explanation as to why, the network service provider—
(i) has determined, or was unable to determine whether, the connection of the customer’s load will require augmentations or alterations to affected networks, other than excluded augmentations, and
(ii) if the load will require augmentations or alterations to affected networks other than excluded augmentations—the provider is unable to impose power transfer limitations or load control arrangements to enable the network service provider to manage network constraints.
cl 65H: Ins 2023 (93), Sch 1.