65D Revocation of approval
65D Revocation of approval
The Minister must revoke an order made under clause 65C in relation to an approved customer if satisfied—
(a) the approved customer has ceased to be an eligible customer, or
(b) the approved customer has ceased to produce green hydrogen, or
(c) that, within 2 years of the Minister making the order, the approved customer is not a party to a connection agreement or connection contract with a network service provider in relation to a connection point specified in that order, or
(d) the approved customer has not complied with a proposal in the application under clause 65C(2) or the statement in clause 65C(2)(b)(i) is not true, or
(e) the approved customer has not complied with a requirement under clause 65A or 65C(5).
cl 65D: Ins 2023 (93), Sch 1.