62H Changes to liability for shortfall penalty as result of amended assessment
62H Changes to liability for shortfall penalty as result of amended assessment
(1) A shortfall penalty payable due to the amendment of an assessment is taken to be payable on the later of the following dates—
(a) the date 7 days after the date the Scheme Regulator gives the scheme participant notice of the amended assessment,
(b) the date on which a shortfall penalty would have been payable under the original assessment.
(2) The Scheme Regulator may extend the period for payment of a shortfall penalty that becomes payable as a result of the amendment of an assessment.
(3) A scheme participant whose liability for a shortfall penalty is reduced as a result of an amended assessment is entitled to a refund of an excess shortfall penalty paid under the previous assessment.
(4) If an assessment has been amended, the Scheme Regulator may, within 12 months after the day on which a shortfall penalty became payable under the amended assessment, further amend the assessment if satisfied the further amendment is necessary to make a just reduction in the scheme participant’s liability under the assessment.
cl 62H: Ins 2022 (607), Sch 1[57].