sec.21Restoration of publicly controlled place
Start here
Get a plain-English read of sec.21
Turn the raw legal text into a practical explanation grounded in Electricity Regulation 2006.
sec.21 Restoration of publicly controlled place
An electricity entity that has opened or broken up a publicly controlled place must— with all convenient speed, finish the work; and on finishing the work, take away from the place all plant, materials and equipment not built into the work; and restore, as far as practicable, the place where the work was carried out and leave it tidy. The way action under subsection (1) is to be carried out by or for the electricity entity is as agreed between the electricity entity and the public entity controlling the place and in accordance with reasonable conditions and requirements stated by the public entity. (sec.21-ssec.1) An electricity entity that has opened or broken up a publicly controlled place must— with all convenient speed, finish the work; and on finishing the work, take away from the place all plant, materials and equipment not built into the work; and restore, as far as practicable, the place where the work was carried out and leave it tidy. (sec.21-ssec.2) The way action under subsection (1) is to be carried out by or for the electricity entity is as agreed between the electricity entity and the public entity controlling the place and in accordance with reasonable conditions and requirements stated by the public entity.
- (a) with all convenient speed, finish the work; and
- (b) on finishing the work, take away from the place all plant, materials and equipment not built into the work; and
- (c) restore, as far as practicable, the place where the work was carried out and leave it tidy.