sec.120F Record keeping
This section applies if a person conducting a business or undertaking is responsible for ensuring— a risk assessment is conducted under section 120C (3) (a) ; or a statement is prepared under section 120C (3) (c) . Subject to subsection (3) , the person must keep— a copy of the risk assessment until at least 28 days after the work or entry to which it relates is completed or made; and a copy of the statement until the work or entry to which it relates is completed or made. Maximum penalty—60 penalty units. If a serious electrical incident or dangerous electrical event occurs in connection with any work or entry to which the risk assessment or statement relates, the person must keep the risk assessment or statement for at least 2 years after the incident occurs. Maximum penalty—60 penalty units. s 120F ins 2024 SL No. 241 s 42 (sec.120F-ssec.1) This section applies if a person conducting a business or undertaking is responsible for ensuring— a risk assessment is conducted under section 120C (3) (a) ; or a statement is prepared under section 120C (3) (c) . (sec.120F-ssec.2) Subject to subsection (3) , the person must keep— a copy of the risk assessment until at least 28 days after the work or entry to which it relates is completed or made; and a copy of the statement until the work or entry to which it relates is completed or made. Maximum penalty—60 penalty units. (sec.120F-ssec.3) If a serious electrical incident or dangerous electrical event occurs in connection with any work or entry to which the risk assessment or statement relates, the person must keep the risk assessment or statement for at least 2 years after the incident occurs. Maximum penalty—60 penalty units.
- (a) a risk assessment is conducted under section 120C (3) (a) ; or
- (b) a statement is prepared under section 120C (3) (c) .
- (a) a copy of the risk assessment until at least 28 days after the work or entry to which it relates is completed or made; and
- (b) a copy of the statement until the work or entry to which it relates is completed or made.