Design and Building Practitioners Act 2020
4CCrown building project—staged provision of designs
Start here
Get a plain-English read of 4C
Turn the raw legal text into a practical explanation grounded in Design and Building Practitioners Act 2020.
4C Crown building project—staged provision of designs
4C Crown building project—staged provision of designs
(1) This clause applies to a Crown building project if Crown building work under the project is carried out after 31 July 2021 and before 1 July 2023.
(2) A building practitioner is taken to comply with a provision of the regulations made under the Act, section 107(2)(e) requiring a building practitioner to provide specified regulated designs and compliance declarations to the Secretary before commencing building work if, before commencing Crown building work under a Crown building project to which this clause applies—
(a) the building practitioner provides regulated designs and compliance declarations relating to a portion of the Crown building project (building work increment) to the Secretary, and
(b) the regulated designs and compliance declarations otherwise comply with the requirements of the provision, and
(c) the only Crown building work carried out relates to the building work increment.
(3) The clause ceases to have effect on 1 July 2023.