#### 4B Crown building work—commenced
4B Crown building work—commenced
> > (1) This clause applies to Crown building work if—
> >
> > > (a) it is carried out before 1 August 2021, and
> >
> > > (b) the Crown building project to which it relates has not been completed by that day.
>
> > (2) The following requirements of the Act do not apply to the Crown building work, or a design in relation to the Crown building work, to which this clause applies—
> >
> > > (a) provisions requiring regulated designs to be prepared for the Crown building work, including requirements for compliance declarations,
> >
> > > (b) provisions requiring a person to be registered to carry out the Crown building work,
> >
> > > (c) provisions requiring a building compliance declaration to be prepared for the Crown building work.
>
> > (3) The building practitioner for the Crown building work must provide copies of all designs relied on to carry out the Crown building work—
> >
> > > (a) to the Secretary in the approved way, and
> >
> > > (b) before the completion of the Crown building project to which the Crown building work relates.
> >
> > Maximum penalty—1,500 penalty units for a body corporate or 500 penalty units for an individual.