This Regulation sets detailed technical and procedural rules for preparing, labelling, numbering, lodging and registering community land development plans, contracts and management statements in NSW. It prescribes what maps, survey data, unit entitlements, forms and certificates must show and how amendments, subdivisions, conversions, amalgamations, easements and access ways are recorded.
It principally affects developers, surveyors, community/precinct/neighbourhood associations, the Registrar‑General and listed utilities. Those parties bear the compliance costs of surveys, statutory forms and certificates; decisions about approvals rest with associations, developers, planning authorities and the Registrar‑General.
This Regulation prescribes the form, content, procedural steps and certain administrative discretions that govern the preparation, lodgment and registration of scheme plans, management statements, development contracts and related instruments under the Community Land Development Act 2021 (the Act). It sets mandatory drafting and lodgment rules for plan sheets, schedules of unit entitlement, replacement and additional sheets, statutory easement diagrams, access way plans, boundary adjustment and acquisition plans, development contracts and management statements. The Regulation also designates particular public authorities for the Act and prescribes timing rules for valuation days and for evidence of expiry of the initial developer period.
Mechanically, the Regulation:
fixes labelling, numbering and content requirements for location plans, detail plans and association property plans in a scheme plan, including that association property be numbered Lot 1 and other lots be consecutively numbered beginning at Lot 2 (ss 5-7);
prescribes the three-column format and required entries for schedules of unit entitlement and that the schedule include an approved-form warning and total (s 8);
requires additional and replacement sheets to include specific notes, deposited plan numbers and sheet numbering conventions, including alphabetic suffixes for replacement sheets (ss 9-11);
constrains what must appear on subdivision, consolidation, boundary adjustment, acquisition and amalgamation applications, including specific survey information, numbering, certificates and accompanying reports (ss 12-16, 29);
requires development contracts and management statements lodged for registration to comply with the lodgment rules for paper or electronic form (Schedules 2 or 6 of the lodgment rules) and to contain prescribed matters and signatures (ss 19-21, 25);
Current sections
Direct links to the current provisions in Community Land Development Regulation 2021.
This Regulation commences on 1 December 2021 and is required to be published on the NSW legislation website.
3
Definitions
3 Definitions
3 Definitions
In this Regulation—
access way plan means a plan for an open access way or private access way included in the management statement for a scheme under the Act, section 41(3).
detailed survey information, for a plan, has the same meaning as in the Act, section 25.
The Act and the Interpretation Act 1987 also contain definitions and other provisions that affect the interpretation and application of this Regulation.
(2) This Regulation prevails to the extent of an inconsistency between this Regulation and the provisions referred to in subsection (1).
Part 2
Scheme plans
Part 2 Scheme plans
Part 2 Scheme plans
5
Location plans—the Act, Schedule 1, cl 1(2)(b)
5 Location plans—the Act, Schedule 1, cl 1(2)(b)
5 Location plans—the Act, Schedule 1, cl 1(2)(b)
A location plan included in a scheme plan must—
(a) be clearly labelled “LOCATION PLAN” in the plan drawing area, and
(b) contain a schedule on which to record subsequent subdivisions, consolidations, severances and other changes to lots in the scheme.
6
Detail plans—the Act, Schedule 1, cl 1(2)(b)
6 Detail plans—the Act, Schedule 1, cl 1(2)(b)
6 Detail plans—the Act, Schedule 1, cl 1(2)(b)
(1) Each sheet of a detail plan included in a scheme plan must be clearly labelled “DETAIL PLAN” in the plan drawing area.
(2) The detail plan must set out the detailed survey information for all of the lots in the scheme, including the association property.
(3) The association property must be numbered “Lot 1” and, if it comprises more than 1 part, each part must be identified as part of Lot 1.
(4) All other lots on the detail plan must be numbered consecutively, beginning with “Lot 2”.
7
Association property plans—the Act, Schedule 1, cl 1(2)(b)
7 Association property plans—the Act, Schedule 1, cl 1(2)(b)
7 Association property plans—the Act, Schedule 1, cl 1(2)(b)
(1) An association property plan included in a scheme plan must be clearly labelled with one of the following, as the case requires, in the plan drawing area—
COMMUNITY PROPERTY PLAN
PRECINCT PROPERTY PLAN
NEIGHBOURHOOD PROPERTY PLAN
(2) The association property plan must be a diagram showing all association property in the scheme.
(3) The association property plan must include the boundaries and complete dimensions, including area and part areas, of the whole of the association property but without the detailed survey information.
(4) The association property must be numbered “Lot 1” and, if it comprises more than 1 part, each part must be identified as part of Lot 1.
(5) Unless the Registrar-General otherwise agrees, the association property plan must comprise 1 sheet only.
8
Schedules of unit entitlement—the Act, s 115(2)(c)
8 Schedules of unit entitlement—the Act, s 115(2)(c)
8 Schedules of unit entitlement—the Act, s 115(2)(c)
(1) A schedule of unit entitlement accompanying a scheme plan must contain 3 columns as follows—
(a) the first column, headed “LOT”, must list the lots in the scheme in numerical order,
(b) the second column, headed “UNIT ENTITLEMENT”, must contain—
(i) for the association property—the words “COMMUNITY PROPERTY”, “PRECINCT PROPERTY” or “NEIGHBOURHOOD PROPERTY”, as the case requires, and
(ii) for a lot that is to be dedicated as a public reserve or drainage reserve—the words “PUBLIC RESERVE” or “DRAINAGE RESERVE”, as the case requires, and
(iii) for each other lot—the value of the unit entitlement,
(c) the third column, headed “SUBDIVISION”, must record details of subsequent subdivisions, consolidations, severances and other changes to lots as they occur.
(2) At the end of the schedule of unit entitlement—
(a) the first column must contain the word “TOTAL”, and
(b) the second column must contain the total value of all the unit entitlements of the individual lots referred to in subsection (1)(b)(iii).
(3) A warning statement that the schedule of unit entitlement may be altered or replaced must be—
(a) in the approved form, and
(b) set out in the panels provided on the administration sheet required to accompany the scheme plan.
Part 3
Additional sheets and replacement sheets and schedules
Part 3 Additional sheets and replacement sheets and schedules
Part 3 Additional sheets and replacement sheets and schedules
9
Additional sheet of a detail plan—the Act, Schedule 1, cl 1(2)(b)
9 Additional sheet of a detail plan—the Act, Schedule 1, cl 1(2)(b)
9 Additional sheet of a detail plan—the Act, Schedule 1, cl 1(2)(b)
(1) An additional sheet of a detail plan must comply with the requirements in section 6, to the extent that the requirements are relevant to an additional sheet.
(2) An additional sheet must also—
(a) contain a note in the note column, in the approved form, indicating the sheet is an additional sheet, and
(b) include the deposited plan number of the scheme, and
(c) be numbered with the next sheet number after the last number used for the scheme plan.
10
Replacement sheet for an association property plan—the Act, Schedule 1, cl 1(2)(b)
10 Replacement sheet for an association property plan—the Act, Schedule 1, cl 1(2)(b)
10 Replacement sheet for an association property plan—the Act, Schedule 1, cl 1(2)(b)
(1) A replacement sheet for an association property plan must comply with the requirements in section 7, to the extent that the requirements are relevant to a replacement sheet.
(2) A replacement sheet must also—
(a) contain a note in the note column, in the approved form, indicating that the sheet is a replacement sheet, and
(b) include the deposited plan number of the scheme, and
(c) be numbered with the same sheet number as the sheet it is to replace, together with an alphabetic suffix to indicate the number of times the sheet has been replaced.
11
Replacement schedule of unit entitlement—the Act, s 115(2)(c)
11 Replacement schedule of unit entitlement—the Act, s 115(2)(c)
11 Replacement schedule of unit entitlement—the Act, s 115(2)(c)
(1) A replacement schedule of unit entitlement must comply with the requirements in section 8, to the extent that the requirements are relevant to a replacement schedule.
(2) The administration sheet containing the replacement schedule must contain a note, in the approved form, indicating that the schedule is a replacement schedule.
Part 4
Plans and instruments
Part 4 Plans and instruments
Part 4 Plans and instruments
12
Subdivision by scheme plan of subdivision—the Act, Schedule 1, cl 1(2)(b)
12 Subdivision by scheme plan of subdivision—the Act, Schedule 1, cl 1(2)(b)
12 Subdivision by scheme plan of subdivision—the Act, Schedule 1, cl 1(2)(b)
(1) A scheme plan of subdivision must show only the lots subject to the subdivision.
(2) The boundaries of new lots that follow the boundaries of existing lots may be compiled from the relevant scheme plan.
(3) The additional sheet of the detail plan required to be included with the scheme plan of subdivision must also include the detailed survey information for the altered association property.
(4) The new lots on the additional sheet of the detail plan must be numbered consecutively, beginning with the next available lot number for the scheme.
(5) The replacement schedule of unit entitlement required to be included with the scheme plan of subdivision must also include the following—
(a) in the “LOT” column—a list of the lots being created,
(b) in the “UNIT ENTITLEMENT” column—
(i) for each lot being subdivided—a reference to the new lots being created, and
(ii) for each lot being created—its unit entitlement,
(c) in the “SUBDIVISION” column—opposite each lot being subdivided, a reference to the sheet of the scheme plan of subdivision that created the new lots.
13
Dedication of land by scheme plan of subdivision—the Act, Schedule 1, cl 1(2)(b)
13 Dedication of land by scheme plan of subdivision—the Act, Schedule 1, cl 1(2)(b)
13 Dedication of land by scheme plan of subdivision—the Act, Schedule 1, cl 1(2)(b)
A scheme plan of subdivision may dedicate association property as a public road, a public reserve or a drainage reserve.
Note—
The Act, section 15 applies to a scheme plan of subdivision that dedicates association property as a public road, a public reserve or a drainage reserve.
14
Consolidation by scheme plan of consolidation—the Act, Schedule 1, cl 1(2)(b)
14 Consolidation by scheme plan of consolidation—the Act, Schedule 1, cl 1(2)(b)
14 Consolidation by scheme plan of consolidation—the Act, Schedule 1, cl 1(2)(b)
(1) An additional sheet of the detail plan required to be included with a scheme plan of consolidation—
(a) may be compiled from information in the relevant scheme plan, and
(b) must show only the lots subject to the consolidation.
(2) The new lots on the additional sheet of the detail plan must be numbered consecutively, beginning with the next available lot number for the scheme.
(3) The replacement schedule of unit entitlement required to be included with a scheme plan of consolidation must also include the following—
(a) in the “LOT” column—a list of the newly consolidated lots,
(b) in the “UNIT ENTITLEMENT” column—
(i) against the superseded lots—a reference to the relevant consolidated lot, and
(ii) for each consolidated lot—its unit entitlement,
(c) in the “SUBDIVISION” column—a reference to the sheet of the scheme plan that shows the consolidated lot.
15
Boundary adjustment plans—the Act, s 18(2)(d) and Schedule 1, cl 1(2)(b)
15 Boundary adjustment plans—the Act, s 18(2)(d) and Schedule 1, cl 1(2)(b)
15 Boundary adjustment plans—the Act, s 18(2)(d) and Schedule 1, cl 1(2)(b)
(1) A boundary adjustment plan must—
(a) illustrate the results of a survey identifying the altered boundaries of the community property or precinct property and of the affected development lots, and
(b) include the original lot numbers of the affected development lots.
(2) Other boundaries shown on the boundary adjustment plan that have not been altered may be compiled from the relevant community plan or precinct plan.
(3) An additional sheet of the detail plan required to be included in a boundary adjustment plan must also include detailed survey information for the altered boundaries of the affected development lots.
(4) The administration sheet required to accompany the boundary adjustment plan must include a certificate—
(a) in the approved form, and
(b) given under seal of the community association or precinct association, and
(c) to the effect that the association approved the altered boundaries by an ordinary resolution of the association.
(5) A comprehensive report provided by a surveyor stating the reasons for the boundary adjustment, and containing other information required by the Registrar-General, must be lodged with the boundary adjustment plan.
(6) If an adjustment is made by the boundary adjustment plan that causes the position of an open access way or a private access way to move—
(a) an amendment must be made to the access way plan, and
(b) an amendment to the management statement must be registered under the Act, section 108.
16
Acquisition plans—the Act, s 115 and Schedule 1, cl 1(2)(b)
16 Acquisition plans—the Act, s 115 and Schedule 1, cl 1(2)(b)
16 Acquisition plans—the Act, s 115 and Schedule 1, cl 1(2)(b)
(1) An acquisition plan must show only the lots to be acquired and must not show residue lots.
(2) If part of a lot is to be acquired, the residue that is not being acquired and will remain in the scheme must be shown as a whole lot in—
(a) if the part to be acquired is association property—the replacement sheet for the association property plan required to be lodged with the acquisition plan, or
(b) if the part to be acquired is a development lot or neighbourhood lot—the additional sheet of the detail plan required to be lodged with the acquisition plan.
(3) The acquisition plan, and the replacement sheet for the association property plan or additional sheet of the detail plan required to be lodged with the plan, must illustrate the results of a survey identifying the altered boundaries of the affected lots.
(4) Other boundaries shown on the acquisition plan, or on the replacement or additional sheet, that have not been altered may be compiled from the relevant scheme plan.
(5) A replacement sheet for an association property plan required to be lodged with an acquisition plan must also be accompanied by an additional sheet of the detail plan showing the updated survey information for the altered boundaries.
(6) The new lots on the additional sheet of a detail plan must be numbered consecutively, beginning with the next available lot number for the scheme.
(7) The acquisition plan must be lodged for registration at the same time as the transfers of the land being acquired under the plan, unless the Registrar-General agrees otherwise in writing.
Part 5
Instruments of severance and conversion
Part 5 Instruments of severance and conversion
Part 5 Instruments of severance and conversion
17
Severance of development lots—the Act, s 115(2)(c)
17 Severance of development lots—the Act, s 115(2)(c)
17 Severance of development lots—the Act, s 115(2)(c)
The replacement schedule of unit entitlement required to accompany an instrument under the Act, section 19 must include, in the “UNIT ENTITLEMENT” column, the words “SEVERED LOT” for each lot severed by the instrument.
18
Conversion of development lots or neighbourhood lots to association property—the Act, s 115
18 Conversion of development lots or neighbourhood lots to association property—the Act, s 115
18 Conversion of development lots or neighbourhood lots to association property—the Act, s 115
(1) An instrument of conversion must be accompanied by an additional sheet of the detail plan for the relevant scheme plan showing the updated detailed survey information for the altered boundaries.
(2) The additional sheet of the detail plan may be compiled from information in the relevant scheme plan, unless the information conflicts or the Registrar-General requires otherwise.
(3) The replacement schedule of unit entitlements required to accompany an instrument of conversion must include, against the converted lots in the “UNIT ENTITLEMENT” column, the words “CONVERTED TO LOT 1”.
(4) In this section—
instrument of conversion means an instrument referred to in the Act, section 24.
Part 6
Development contracts
Part 6 Development contracts
Part 6 Development contracts
19
Registration of development contracts—the Act, s 115(2)(a)
19 Registration of development contracts—the Act, s 115(2)(a)
19 Registration of development contracts—the Act, s 115(2)(a)
(1) A proposed development contract that is lodged for registration must comply with the following provisions of the lodgment rules—
(a) if lodged in paper form—Schedule 2,
(b) if lodged in electronic form—Schedule 6.
(2) For the purposes of this section, a proposed development contract—
(a) is taken to be an instrument or other document to which Schedule 2 or 6 of the lodgment rules applies, and
(b) includes an instrument setting out amendments to sheets of a proposed development contract.
20
Matters to be included in development contracts—the Act, ss 46(4)(e) and 115(2)(a)
20 Matters to be included in development contracts—the Act, ss 46(4)(e) and 115(2)(a)
20 Matters to be included in development contracts—the Act, ss 46(4)(e) and 115(2)(a)
(1) A development contract must include each of the following matters—
(a) a description of the buildings, services, facilities or infrastructure proposed to be built, installed or provided on association property,
(b) details of easements proposed to be created benefiting or burdening association property,
(c) details of restrictions on the use of land, or positive covenants, proposed to be created benefiting or burdening association property,
(d) if land is proposed to be added to the scheme—whether the land is to be added as a development lot or neighbourhood lot or association property.
(2) Authorised proposals and warranted development should be listed and dealt with separately in the development contract.
(3) The concept plan required to be included in the development contract must relate to the authorised proposals and warranted development.
21
Execution of a dealing, plan or other instrument—the Act, s 56(5)
21 Execution of a dealing, plan or other instrument—the Act, s 56(5)
21 Execution of a dealing, plan or other instrument—the Act, s 56(5)
(1) A dealing, plan or other instrument executed by a relevant developer on behalf of an association under the Act, section 56(4)(b) must be executed in the approved form.
(2) The relevant developer must also provide the Registrar-General with a statutory declaration that—
(a) sets out the circumstances in which the decision about the development concern to which the dealing, plan or other instrument relates was made, including the particulars of the meeting at which the decision was made, and
(b) verifies that the requirements of the Act, section 57(1) and (4) were complied with in making the decision.
(3) If the relevant developer is a corporation, the statutory declaration must be provided by a director or officer of the relevant developer.
22
Notices relating to development concerns—the Act, s 115(2)(a)
22 Notices relating to development concerns—the Act, s 115(2)(a)
22 Notices relating to development concerns—the Act, s 115(2)(a)
Each of the following must, to the extent it deals with a motion relating to a development concern, identify the motion as relating to a development concern and refer to the Act, section 57—
(a) a notice served on the secretary of an association requiring inclusion of the motion in the agenda of the next general meeting of the association,
(b) a qualified request made under the Community Land Management Act 2021, section 17 requesting the convening of a general meeting to consider the motion,
(c) a request made under the Community Land Management Act 2021, section 43 requesting the convening of a meeting of the association committee to consider the motion.
23
Conclusion of development contract for a community scheme—the Act, s 58(2)(b)
23 Conclusion of development contract for a community scheme—the Act, s 58(2)(b)
23 Conclusion of development contract for a community scheme—the Act, s 58(2)(b)
(1) A development contract for a community scheme may specify a date for the conclusion of the contract that is between 10 and 20 years after the registration of the contract if—
(a) the developer applies to the Registrar-General for the longer period, and
(b) the Registrar-General is satisfied the development cannot be completed in 10 years.
(2) The application—
(a) must contain an explanation of why the development cannot be completed in 10 years, which may include the following information—
(i) the number of lots and subsidiary schemes proposed to be created before the conclusion of the development contract,
(ii) the proposed number of stages for the development of the land in the community scheme and the timing of those stages,
(iii) the details of planning approvals granted for the development of the land in the community scheme, and
(b) must be made before, or at the time of, lodgment of the proposed development contract for registration.
24
Planning authority approval—the Act, s 115(2)(a)
24 Planning authority approval—the Act, s 115(2)(a)
24 Planning authority approval—the Act, s 115(2)(a)
(1) The certificates referred to in the Act, sections 47(4) and 50(5)(b) must be in the approved form.
(2) The approval of the planning authority referred to in the Act, section 53(2)(b) must be evidenced by the certificate referred to in the Act, section 50(5)(b).
Part 7
Management statements
Part 7 Management statements
Part 7 Management statements
25
Registration of management statements—the Act, s 115(2)(b)
25 Registration of management statements—the Act, s 115(2)(b)
25 Registration of management statements—the Act, s 115(2)(b)
(1) A proposed management statement that is lodged for registration must comply with the following provisions of the lodgment rules—
(a) if lodged in paper form—Schedule 2,
(b) if lodged in electronic form—Schedule 6.
(2) For the purposes of this section, the proposed management statement—
(a) is taken to be an instrument or other document to which Schedule 2 or 6 of the lodgment rules applies, and
(b) includes an instrument setting out amendments to a proposed management statement.
(3) The proposed management statement must be signed by or on behalf of the developer.
26
Statutory easement diagram—the Act, s 115(2)(b)
26 Statutory easement diagram—the Act, s 115(2)(b)
26 Statutory easement diagram—the Act, s 115(2)(b)
(1) This section applies to a prescribed diagram which creates a statutory easement when registered as part of the management statement for a scheme (statutory easement diagram).
(2) A statutory easement diagram must—
(a) illustrate the position of—
(i) all existing service lines for which a statutory easement is proposed to be created, and
(ii) all proposed service lines intended to be provided within the scheme and over which a statutory easement is proposed to be created, and
(b) show sufficient information to locate the approximate position of each service line within each lot through which the service line passes, and
(c) indicate the nature of each service and how it is, or is proposed to be, provided, and
(d) on the first page, contain the deposited plan number and a description of the relevant scheme.
(3) Each sheet of the statutory easement diagram must be numbered as a sheet of the management statement.
(4) In this section—
lot, prescribed diagram, service and service line have the same meanings as in the Act, section 32.
27
Access way plans—the Act, s 41(3)(c)
27 Access way plans—the Act, s 41(3)(c)
27 Access way plans—the Act, s 41(3)(c)
(1) An access way plan must—
(a) illustrate the position of each access way within the association property, and
(b) show and define the extent of each open access way and each private access way and indicate how the change of status between an open access way and private access way will be indicated, and
(c) if an access way has been named, show the name within the access way with the words “known as” before the name, and
(d) include a note indicating the access ways are still association property and are not public roads, and
(e) on the first page, contain the deposited plan number of the relevant scheme.
(2) Each sheet of an access way plan must be numbered as a sheet of the management statement for the relevant scheme.
(3) All survey information required under the Surveying and Spatial Information Act 2002 to define an access way must be shown on the detail plan included in the scheme plan.
(4) In this section—
access way means a private access way or an open access way.
28
Amendments to management statements—the Act, s 115(2)(b)
28 Amendments to management statements—the Act, s 115(2)(b)
28 Amendments to management statements—the Act, s 115(2)(b)
(1) An amendment to a management statement must be lodged with the Registrar-General in the form of a consolidated version of the management statement that incorporates the amendment.
(2) The Registrar-General may permit an amendment to a management statement to be lodged separately and not in the form of a consolidated version if—
(a) the amendment relates only to an access way plan or a statutory easement diagram, or
(b) otherwise—
(i) the Registrar-General is satisfied it would be too onerous for a consolidated version to be lodged, and
(ii) there are no more than 5 separate changes recorded on the relevant folio of the Register for the association property.
Part 8
Amalgamation of schemes
Part 8 Amalgamation of schemes
Part 8 Amalgamation of schemes
29
Application for amalgamation—the Act, s 62(1)(e) and 64
29 Application for amalgamation—the Act, s 62(1)(e) and 64
29 Application for amalgamation—the Act, s 62(1)(e) and 64
(1) The additional sheet of the detail plan for the community plan required to accompany an application for amalgamation—
(a) must show the updated survey information for the association property that is to be amalgamated, and
(b) may be compiled from information in the relevant precinct plan or neighbourhood plan.
(2) The new lots on the additional sheet of the detail plan must be numbered consecutively, beginning with the next available lot number for the community scheme.
(3) The replacement schedule of unit entitlement required to accompany an application for a standard amalgamation must be accompanied by a certificate (an association certificate) in the approved form.
(4) The association certificate must—
(a) be under the seal of the association, and
(b) contain a statement to the effect that the unit entitlement of the new community development lots have been apportioned in accordance with the Act, Schedule 3, clause 13(2).
(5) The consent of the planning authority required under the Act, section 61(1)(d) must be in the approved form.
(6) In this section—
standard amalgamation means an amalgamation to which the Act, Schedule 3, clause 13(4) does not apply.
Part 9
Miscellaneous
Part 9 Miscellaneous
Part 9 Miscellaneous
30
Evidence of expiration of initial period—the Act, s 115
30 Evidence of expiration of initial period—the Act, s 115
30 Evidence of expiration of initial period—the Act, s 115
(1) This section applies to a plan or dealing if—
(a) the plan or dealing must not be registered unless the initial period has expired, and
(b) the plan or dealing is not in accordance with a development contract that is in force, and
(c) the Tribunal has not—
(i) for a scheme plan of subdivision that adds land to a scheme parcel as a development lot or neighbourhood lot—authorised the addition of the land, or
(ii) for a dealing or other plan—authorised the dealing or other plan.
(2) A certificate in the approved form certifying that the initial period has expired must—
(a) for a plan—be included on the administration sheet required to be lodged with the plan for registration, and
(b) for a dealing—accompany the dealing when the dealing is lodged for registration.
31
Valuation day—the Act, Schedule 3, cll 3–6 and 13
31 Valuation day—the Act, Schedule 3, cll 3–6 and 13
31 Valuation day—the Act, Schedule 3, cll 3–6 and 13
The valuation day for a schedule of unit entitlement is prescribed as—
(a) for the purposes of a schedule of unit entitlement referred to in the Act, Schedule 3, clause 3—a day within 2 months before an application is made for a subdivision certificate required by the Act, Schedule 1, clause 1 (4)(c), and
(b) for the purposes of a schedule of unit entitlement referred to in the Act, Schedule 3, clause 4—a day within 2 months before an application is made for a subdivision certificate required by the Act, Schedule 1, clause 1 (4)(c), and
(c) for the purposes of a schedule of unit entitlement referred to in the Act, Schedule 3, clause 5—
(i) the valuation day for the original scheme plan, or
(ii) if there has been a subsequent subdivision affecting the association property—the most recent valuation day, and
(d) for the purposes of a schedule of unit entitlement referred to in the Act, Schedule 3, clause 6—
(i) a day within 2 months before an application is made for a subdivision certificate required by the Act, Schedule 1, clause 1 (4)(c), or
(ii) if a subdivision certificate is not required, 2 months before the date of the transfer of the relevant land, and
(e) for the purposes of a schedule of unit entitlement referred to in the Act, Schedule 3, clause 13(4)—a day within 2 months before an application is made for the consent of the planning authority required by the Act, section 61(1)(d).
32
Prescribed public authorities
32 Prescribed public authorities
32 Prescribed public authorities
Each of the following is prescribed as a public authority for the purposes of the Act, Dictionary, definition of public authority—
This Regulation is the Community Land Development Regulation 2021.
2 Commencement
2 Commencement
2 Commencement
This Regulation commences on 1 December 2021 and is required to be published on the NSW legislation website.
3 Definitions
3 Definitions
3 Definitions
In this Regulation—
access way plan means a plan for an open access way or private access way included in the management statement for a scheme under the Act, section 41(3).
detailed survey information, for a plan, has the same meaning as in the Act, section 25.
statutory easement diagram—see section 26(1).
survey has the same meaning as in the Surveying and Spatial Information Act 2002.
the Act means the Community Land Development Act 2021.
Note—
The Act and the Interpretation Act 1987 also contain definitions and other provisions that affect the interpretation and application of this Regulation.
4 Application
4 Application
4 Application
(1) This Regulation applies in addition to—
(a) the Conveyancing (General) Regulation 2018, Part 3 and Schedule 1, or the equivalent provisions of a regulation that replaces that regulation, and
(b) the regulations made under the Real Property Act 1900 and the lodgment rules.
(2) This Regulation prevails to the extent of an inconsistency between this Regulation and the provisions referred to in subsection (1).
Part 2 Scheme plans
Part 2 Scheme plans
Part 2 Scheme plans
5 Location plans—the Act, Schedule 1, cl 1(2)(b)
5 Location plans—the Act, Schedule 1, cl 1(2)(b)
5 Location plans—the Act, Schedule 1, cl 1(2)(b)
prescribes content and labelling for statutory easement diagrams and access way plans, including required notes that access ways remain association property and are not public roads (ss 26-27);
sets procedures for amendments to management statements, allowing consolidated lodgment except in limited situations where the Registrar-General may permit separate amendments (s 28);
prescribes the valuation day timing for a range of unit entitlement scenarios under Schedule 3 to the Act (s 31);
prescribes a defined list of public authorities for the Act’s Dictionary of public authority (s 32); and
commenced on 1 December 2021 and must be published on the NSW legislation website (s 2).
The Regulation expressly applies in addition to, and prevails to the extent of inconsistency over, certain provisions of the Conveyancing (General) Regulation 2018 and regulations under the Real Property Act 1900 and lodgment rules (s 4). That placement makes these drafting and procedural requirements definitive within the Act’s procedural field, subject to the Registrar-General’s limited discretions expressly given in particular provisions.
This description is sourced directly from the Regulation. The Regulation references other instruments and rules (for example lodgment rules, the Act’s Schedules and the Surveying and Spatial Information Act 2002) and delegates some practice-level discretion to the Registrar-General; the mechanics described above therefore operate in conjunction with those external instruments and the Registrar-General’s approvals or requirements where the Regulation so provides (see s 3, s 4, ss 10(2)(a), 15(5), 21(2), 23(1)(b) and 28(2)).
Main concepts
The Regulation organises a set of technical, form and administrative requirements around several core concepts inherited from the Act. Those concepts determine what must be shown on plans, what auxiliary instruments must accompany a lodgment, who must sign and certify, and where limited discretion exists.
Key statutory concepts in the Regulation are:
Scheme plan sheet types and labelling. A scheme plan comprises a location plan, detail plan(s) and an association property plan. Each sheet type has mandated labelling, content and numbering conventions: location plans must be clearly labelled “LOCATION PLAN” and include a schedule for subsequent lot changes (s 5); detail plans must be labelled “DETAIL PLAN”, include detailed survey information for all lots including association property, and require Lot 1 to be association property (s 6); association property plans must be labelled according to the association property type (COMMUNITY PROPERTY PLAN, PRECINCT PROPERTY PLAN or NEIGHBOURHOOD PROPERTY PLAN), show boundaries and complete dimensions without detailed survey information and generally be single-sheet unless the Registrar-General agrees otherwise (s 7).
Unit entitlement schedule. The schedule accompanying a scheme plan must use a three-column format (LOT, UNIT ENTITLEMENT, SUBDIVISION), include specific text entries for association property and reserved lots, capture unit entitlement totals and include an approved-form warning on the administration sheet (s 8).
Additional and replacement sheets. Additional detail plan sheets must follow the detail plan rules where relevant, show a note that they are additional sheets, include the deposited plan number and be sequentially numbered (s 9). Replacement association property sheets must comply with association plan requirements and be labelled as replacement sheets, include the deposited plan number, and reuse the replaced sheet number with an alphabetic suffix indicating replacement iterations (s 10). Replacement schedules of unit entitlement must comply with schedule rules and be accompanied by an approved-form note that they are replacement schedules (s 11).
Instruments for subdivision, consolidation, acquisition, boundary adjustment and amalgamation. These instruments have specified survey, numbering and certification requirements: subdivision plans must show only lots subject to subdivision and include updated detailed survey information on additional sheets (s 12); acquisition plans must show only acquired lots, show residue as whole lots on accompanying replacement or additional sheets and be lodged with transfers unless agreed otherwise (s 16); boundary adjustments require an association certificate under seal confirming approval by ordinary resolution and a comprehensive surveyor’s report lodged with the plan (s 15). Amalgamation applications require updated survey detail and an association certificate apportioning unit entitlements as required under the Act (s 29).
Development contracts and management statements. Both must comply with lodgment rules for paper or electronic form (s 19, s 25). The content of development contracts is prescribed to include description of proposed buildings, services and easements, restrictions, covenants and whether added land will be development, neighbourhood or association property; authorised proposals and warranted development must be separately listed and the concept plan must relate to authorised/warranted items (s 20). A development contract for a community scheme may specify a conclusion date between 10 and 20 years after registration if the Registrar-General is satisfied on an application supported by specific information (s 23).
Execution and proof. The Regulation requires certain instruments executed by a relevant developer on behalf of an association to be in the approved form and accompanied by a statutory declaration setting out the decision circumstances and verifying compliance with the Act’s decision requirements (s 21). If the relevant developer is a corporation, a director or officer must provide the statutory declaration (s 21(3)).
Diagrammatic requirements for statutory easements and access ways. Statutory easement diagrams must show existing and proposed service lines, approximate locations, service nature and how provided, and include the deposited plan number and scheme description (s 26). Access way plans must illustrate access ways, show the extent of open and private access ways and explain how status changes will be indicated, show names when provided, include a note that access ways remain association property and be numbered as sheets of the management statement; survey information to define access ways must be on the detail plan (s 27).
Registrar-General discretion and approvals. Several provisions expressly allow the Registrar-General to agree to departures or require additional materials, for example allowing multiple sheets for association property only with Registrar-General agreement (s 7(5)), permitting separate lodging of an amendment to a management statement in limited circumstances and otherwise where consolidated lodging would be onerous and no more than five separate changes affect the folio (s 28(2)), and agreeing to different treatment of additional/replacement compilations (ss 9(1), 10(1), 16(2)-(4)). Those discretions are formalised procedural gates for departures from the primary drafting rules.
Prescribed public authorities. The Regulation lists named utilities and infrastructure owners to be treated as public authorities for the Act, including several entities identified by ACN and the owner of a transacted distribution system under a separate Act (s 32).
These concepts are technical and practice-oriented. They reallocate compliance costs to persons preparing plans, developers and surveyors through mandatory survey, certification and form requirements; they allocate decision-making power to associations for certain boundary adjustments and to the Registrar-General for limited procedural departures. The Regulation thus embeds specific incentives for accurate survey work, formal association decision-making and early engagement with the Registrar-General and planning authority where approvals or non-standard treatment may be required.
Who it affects
The Regulation affects a defined set of actors that prepare, lodge, certify, approve or rely on schemes under the Act. The principal affected parties are developers, surveyors, associations (community, precinct and neighbourhood associations), the Registrar-General and prescribed public authorities. Secondary affected parties include planning authorities, purchasers of lots, utility providers and transferees in acquisition plans.
Developers and relevant developers
Developers must prepare management statements and development contracts in the formats required by the lodgment rules and include prescribed content for development contracts (ss 19, 20, 25). The proposed management statement must be signed by or on behalf of the developer (s 25(3)). Where a relevant developer executes an instrument on behalf of an association under s 56(4)(b) of the Act, that dealing, plan or instrument must be executed in the approved form and the developer must provide a statutory declaration verifying compliance with the Act’s decision-making requirements; for corporate developers, a director or officer must make the declaration (s 21).
Developers seeking a community scheme development contract longer than 10 years must apply to the Registrar-General and supply explanatory information about timing, stages and planning approvals; that application must be made before or at lodgment (s 23).
Surveyors and drafters of plans
Surveyors produce the detailed survey information required on detail plans and additional sheets, the survey-based compilation allowances, and statutory easement diagrams and access way plans as required. Several provisions require updated detailed survey information to accompany subdivisions, acquisitions, boundary adjustments, conversions and amalgamations (ss 6(2), 9(1), 12(3), 15(3), 16(3), 18(1), 29(1)). Section 15 requires a comprehensive report by a surveyor explaining the boundary adjustment and containing other information required by the Registrar-General to be lodged with the boundary adjustment plan.
The Surveying and Spatial Information Act 2002 definitions apply (s 3).
Associations (community, precinct and neighbourhood)
Associations must approve boundary adjustments by ordinary resolution and provide an association seal certificate on the administration sheet for boundary adjustment plans (s 15(4)). Amalgamation applications for standard amalgamation require an association certificate under seal that the unit entitlements have been apportioned in accordance with the Act (s 29(3)-(4)). Association property must be identified and numbered as Lot 1 on detail and association property plans (ss 6(3), 7(4)).
For instruments executed on behalf of an association by a relevant developer, the statutory declaration must set out the circumstances and verify compliance with the Act’s decision rules (s 21(2)).
Registrar-General
The Registrar-General has defined procedural discretion: to agree to association plan sheets comprising more than one sheet (s 7(5)), to require consolidated or allow separate amendments to management statements (s 28(2)), to accept compilation of additional sheets from scheme plans unless it conflicts or Registrar-General requires otherwise (s 9(1), 10(1), 18(2)), and to agree to lodging timing exceptions for acquisition transfers (s 16(7)). The Registrar-General also receives statutory easement diagrams and may have further requirements for surveyor reports under s 15(5).
Planning authorities and the Tribunal
Planning authority approvals are required in some contexts; certificates referred to in the Act must be in approved form and the planning authority approval in s 53(2)(b) must be evidenced by the certificate in s 50(5)(b) (s 24). Section 29(5) requires the planning authority consent for amalgamation be in approved form. The Regulation also contemplates Tribunal authorisations where the Act requires Tribunal action for particular plans or dealings (s 30).
Public authorities, utilities and service owners
The Regulation expressly prescribes particular entities as public authorities for the Act’s dictionary, naming the Australian Postal Corporation, several water and energy providers, Foxtel Management Pty Limited (ACN included), and the owner of a transacted distribution system under another Act (s 32). Those designations may affect notification or consent pathways where the Act uses “public authority.”
Owners and transferees
Purchasers of lots and transferees will be affected indirectly through the content of schedules of unit entitlement, the timing rules for valuation days tied to subdivision certificates or transfers (s 31), and requirements that acquisition plans be lodged with the transfers unless otherwise agreed (s 16(7)). The Regulation also requires warning statements on schedules of unit entitlement of potential alteration to the schedule (s 8(3)).
Who pays and who decides
The immediate compliance costs fall on developers, surveyors and associations required to prepare, certify and lodge the prescribed materials. The Registrar-General makes limited discretionary decisions concerning permitted departures from single-sheet association plans, separate amendment lodgments and lodgment timing of transfers. Planning authorities and the Tribunal make substantive approvals where the Act requires them; the Regulation prescribes approved-form certificates to evidence those approvals (s 24, s 29(5), s 30).
The Regulation structures incentives towards comprehensive survey documentation, formalised association approvals for boundary and amalgamation changes and early engagement with the Registrar-General and planning authorities where the standard form or timing requirements might not be met. The named public authorities are given predictable status under the Act where the term “public authority” is engaged.
Key duties and rights
The Regulation imposes precise duties on plan drafters, developers, associations and surveyors, while conferring limited administrative rights and discretions to the Registrar-General and setting evidentiary requirements that affect parties’ rights to register dealings.
Key duties
Duties on plan content, labelling and numbering
Location, detail and association property plan sheets must carry prescribed labels and content: location plans must be labelled “LOCATION PLAN” and contain a schedule to record future lot changes (s 5); each detail plan sheet must be labelled “DETAIL PLAN”, include detailed survey information for all lots including association property, and number association property as Lot 1 and other lots consecutively beginning with Lot 2 (s 6); association property plans must be labelled as COMMUNITY PROPERTY PLAN, PRECINCT PROPERTY PLAN or NEIGHBOURHOOD PROPERTY PLAN, include boundaries and complete dimensions and be single-sheet unless Registrar-General agrees otherwise (s 7).
Duties on schedules of unit entitlement
A schedule of unit entitlement must present three columns (LOT, UNIT ENTITLEMENT, SUBDIVISION) and include the specified text for association property and reserve lots, list unit entitlements for other lots, and include a total value and an approved-form warning statement on the administration sheet (s 8).
Duties for additional and replacement sheets
Additional sheets must comply with relevant detail plan requirements and include an approved-form note indicating their status, the deposited plan number and sequential sheet numbering (s 9). Replacement association property sheets must comply with relevant association plan requirements, include a replacement note, the deposited plan number and reuse the same sheet number plus an alphabetic suffix showing replacement iterations (s 10). Replacement schedules must comply with the schedule rules and include a replacement note on the administration sheet (s 11).
Duties for particular instruments
Scheme plans of subdivision must show only those lots subject to the subdivision and include updated detailed survey information for any altered association property on the additional sheet, and must renumber new lots consecutively starting at the next available lot number (s 12). Acquisition plans must show only acquired lots, show residues on accompanying sheets, include survey results for affected lots, and generally be lodged concurrently with transfers unless the Registrar-General agrees otherwise (s 16). Boundary adjustment plans must illustrate altered boundaries, include original lot numbers, include detailed survey information for altered boundaries on additional sheets, include an association certificate under seal confirming ordinary resolution approval, and be lodged with a comprehensive surveyor report explaining the adjustment (s 15).
Duties for development contracts and management statements
Proposed development contracts and management statements lodged for registration must comply with the lodgment rules for either paper (Schedule 2) or electronic form (Schedule 6) (ss 19, 25). Management statements must be signed by or on behalf of the developer (s 25(3)). Development contracts must include specified matters such as descriptions of buildings, services, easements, restrictions and whether added land will be development or neighbourhood or association property (s 20).
Duties on execution and verification
A dealing, plan or instrument executed by a relevant developer on behalf of an association must be in the approved form and be accompanied by a statutory declaration that sets out decision circumstances and verifies compliance with the Act’s sections 57(1) and (4); for corporate relevant developers, the declaration must be by a director or officer (s 21).
Duties on diagrams and access ways
Statutory easement diagrams must show existing and proposed service lines, approximate positions within lots, the nature and provision means of each service and have the deposited plan number and scheme description on the first page (s 26). Access way plans must illustrate access ways within association property, define open and private access ways and how status changes will be indicated, show names where used, include a note that access ways are association property and not public roads, be numbered as sheets of the management statement and rely on detail plan survey information for defining access way extents (s 27).
Duties for valuation day timings and evidence requirements
The valuation day for schedules of unit entitlement is prescribed in relation to subdivision certificates, transfers and planning authority consent applications for the particular subclauses of Schedule 3 to the Act (s 31). Plans or dealings that cannot be registered until the initial period has expired require an approved-form certificate certifying expiration to be included on the administration sheet or accompanying the dealing when lodged (s 30).
Administrative rights and discretions
Registrar-General discretions
The Registrar-General may agree that an association property plan comprises more than one sheet (s 7(5)). The Registrar-General may permit an amendment to a management statement to be lodged separately and not as a consolidated version if the amendment relates only to an access way plan or statutory easement diagram, or otherwise if consolidated lodging would be too onerous and there are no more than five separate changes on the folio (s 28(2)). The Registrar-General may also require or agree to different compilation approaches for additional or replacement sheets in some cases (see ss 9(1), 10(1), 16(2)-(5)).
Rights of associations
Associations have the right to approve boundary adjustments by ordinary resolution, and must supply a seal certificate to that effect; they also must certify apportionments of unit entitlements for certain amalgamations (s 15(4), s 29(3)-(4)).
Rights of public authorities
The Regulation designates named entities as “public authorities” for the Act’s purposes so they acquire whatever notification or involvement rights are attached to that status under the Act (s 32).
Evidentiary and procedural effects
Failure to comply with required forms, labels, certificates, survey information, statutory declarations or lodgment rule requirements will affect whether a plan or instrument is treated as properly lodged for registration. For example, acquisition plans must generally be lodged with transfers unless the Registrar-General agrees otherwise (s 16(7)); the absence of an approved-form certificate evidencing the expiry of an initial period will prevent registration of plans or dealings that require that condition be met (s 30).
Rights tied to form approvals
Planning authority approvals and the Tribunal’s authorisations are to be evidenced in approved forms where required by the Act and this Regulation (s 24, s 29(5), s 30). The Regulation therefore converts approval and certification processes into discrete documentation tasks whose absence can block registration.
In short, the Regulation translates duties under the Act into granular form, survey and certification steps and assigns limited administrative discretion. This concentrates compliance risk with developers, surveyors and associations and gives the Registrar-General the narrow power to permit or require departures in specified circumstances.
Penalties and enforcement
The Regulation itself focuses on procedural, form and content requirements rather than introducing new penalty provisions. It does not prescribe specific fines, criminal offences or civil penalty regimes within its text. Enforcement of compliance with procedures in the Regulation therefore operates through the statutory registration regime and the Registrar-General’s administrative powers under the Act and associated lodgment rules rather than through standalone penalty clauses in this Regulation.
Mechanisms that yield enforcement effects
Registrar-General’s control over registration
The Regulation builds registration preconditions that the Registrar-General can enforce by refusing to accept or register plans, dealings and instruments that do not comply with prescribed content and form rules. Examples include requirements for approved-form certificates (s 30), statutory declarations (s 21), compliance with lodgment rules (ss 19, 25), and specific survey information and supporting documents for boundary adjustment, acquisition and subdivision plans (ss 12, 15, 16). The Registrar-General’s discretionary agreements (for example on consolidated amendments, multiple association property sheets and timing of lodgment of acquisition transfers) are framed as permissive approvals; absence of such approvals will operate as negative enforcement because the standard lodgment pathway will be unavailable without them (ss 7(5), 28(2), 16(7)).
Interaction with the Act’s registration and compliance machinery
The Act contains the statutory framework giving the Registrar-General power to accept, register, endorse or refuse instruments and to impose requirements for registration. The Regulation specifies documents and forms whose absence or non-compliance can prevent registration, and registration is itself the trigger for legal effect in many contexts under the Act. For example, if a replacement schedule of unit entitlement is required by a subdivision or consolidation but is not provided in the approved form, the subdivision may not be registrable under the Act’s scheme.
Administrative certainties that affect enforcement risk
The Regulation prescribes approved-form certificates and statutory declarations for evidentiary purposes, shifting enforcement toward administrative verification instead of ex post sanctions. A failure to produce an approved-form certificate evidencing the expiration of the initial developer period (s 30) will prevent registration until that certificate is produced, functioning as an enforcement mechanism.
Absence of express penalties
The Regulation does not itself create monetary penalties or specify that particular breaches attract specified fines. Enforcement therefore relies on refusal or inability to register instruments, and on the Act’s general enforcement, compliance and remedies framework which is outside the text of this Regulation. Where the Regulation requires an association seal certificate or statutory declaration, potential consequences for false declarations or misuse of seals would depend on extant general legal rules and any offence provisions in the Act or other statutes governing false statutory declarations, misuse of corporate seals or fraudulent misrepresentation.
Implications for practice
Because enforcement is procedural, the practical penalty for non-compliance is frequently delay, rejection of lodgment, or the need to re-lodge corrected instruments accompanied by the mandatory documents and certificates. Those outcomes translate into direct costs (fees and professional time) and opportunity costs (delay in development, transfer or financing). The Registrar-General’s role as gatekeeper means that parties should engage with the lodgment rules, ensure approved-form certificates and statutory declarations are prepared in advance and confirm whether Registrar-General consent is required in non-standard situations such as multi-sheet association property plans or exceptions to concurrent registration of transfers with acquisition plans.
In summary, the Regulation enforces compliance through registration prerequisites and administrative gatekeeping rather than by creating standalone penalties in its text; the legal and practical consequences of non-compliance are manifested through refused or delayed registration and the wider enforcement framework of the Act and general statutory offences for false declarations where applicable.
How it interacts with other laws
The Regulation is explicitly drafted to operate alongside and to prevail to the extent of inconsistency over specified existing instruments. It also references and imports definitions and procedural instruments from other legislation and administrative rules. The Regulation’s interaction points are concrete and affect how practitioners must coordinate lodgments, surveys and approvals.
Express primacy and application
Section 4(1) provides that the Regulation applies in addition to the Conveyancing (General) Regulation 2018, Part 3 and Schedule 1, or their replacement provisions, and to the regulations made under the Real Property Act 1900 and the lodgment rules. Section 4(2) states that this Regulation prevails to the extent of any inconsistency between this Regulation and those provisions. Practically, do not assume that Conveancing or Real Property rules displace these drafting and lodgment requirements; this Regulation has primacy on the specific matters it regulates.
Incorporation of other statutory definitions and requirements
Section 3 specifies that “survey” has the same meaning as in the Surveying and Spatial Information Act 2002 and that “detailed survey information” also has the same meaning as in the Act, s 25. The Regulation thereby ties survey content and compliance to surveying standards and obligations established in that separate Act.
Lodgment rules and the Real Property Act
The Regulation requires that proposed development contracts and management statements lodged for registration must comply with certain provisions of the lodgment rules: Schedule 2 for paper form lodgment and Schedule 6 for electronic lodgment (ss 19 and 25). The lodgment rules likely specify specific forms, lodgment processes and electronic requirements that the Registrar-General implements under the Real Property Act or other registration statutes. The Regulation therefore delegates modality and technical lodgment mechanics to those lodgment rules and the Real Property Act framework.
Planning approvals
Several provisions require planning authority approvals and certificates in approved form (s 24, s 29(5)). The Act’s interaction with local planning approvals and state planning authorities remains in force; the Regulation requires the approved-form certificates as the formal evidence of those approvals. The Regulation therefore interfaces with planning law and administrative practice: practitioners must secure planning authority approvals in ways that can be evidenced in the approved forms mandated for registration.
Tribunal and Act procedures
Section 30 contemplates Tribunal authorisations under the Act as gating conditions for registration. If the Act requires Tribunal authorisation for certain additions or dealings, the Regulation prescribes that an approved-form certificate that the initial period has expired must accompany plans or dealings where the Tribunal has not authorised the dealing. This links the Regulation to Tribunal procedures under the Act and means practitioners should factor Tribunal timelines into registration planning.
Acts dealing with electricity network assets and other Acts
Section 32 prescribes as public authorities named utilities and the owner of a transacted distribution system under the Electricity Network Assets (Authorised Transactions) Act 2015. That reference ties providers of electricity network services and owners of transacted assets under a separate regime into the Act’s procedural pathways where public authority status matters.
Survey and spatial information law
The Regulation’s reliance on survey definitions and the requirement that surveys meet Surveying and Spatial Information Act 2002 standards (s 3 and s 27(3)) means practitioners must ensure surveyors deliver plans compliant with that Act’s accuracy and certification obligations.
Other instruments and approval forms
Throughout the Regulation, “approved form” appears repeatedly for certificates, notes and statutory declarations (see ss 8(3), 9(2)(a), 10(2)(a), 11(2), 15(4), 21(1)-(2), 24(1), 29(5), 30(2)). Those approved forms are not reproduced in the Regulation; they are administratively prescribed and likely located in lodgment rule materials, Registrar-General practice notes or other instruments. Parties must therefore obtain the correct approved forms from the Registrar-General or the lodgment rules.
Practical effect
In practice, the Regulation coordinates with the Act and with other statutes and administrative instruments to create a multi-layered compliance regime. The Regulation sets the content and sequencing rules; the lodgment rules determine the technical filing method; the Surveying and Spatial Information Act defines survey standards; planning authorities and Tribunal processes can impose substantive preconditions; and the Registrar-General enforces compliance at registration. Parties must therefore map tasks across these instruments to secure registration: survey compliance, drafting to the labelling and numbering rules, obtaining association seals and ordinary resolutions, securing planning authority approval in the certified form, preparing statutory declarations, and adhering to lodgment processes.
In short, the Regulation is a technical overlay on several existing legal and administrative frameworks that together govern registration, evidentiary standards and approvals for community land development instruments.
Amendment history
The Regulation itself records its formal name and commencement date. Section 1 states the Regulation is the Community Land Development Regulation 2021. Section 2 fixes commencement on 1 December 2021 and requires publication on the NSW legislation website. The text provided contains no expressions of prior amendments or insertions to this Regulation after that commencement date. Therefore, within the Regulation’s text supplied here, the amendment history is limited to its initial naming and commencement provisions only.
What the text explicitly records
The Regulation’s name is fixed in s 1 as the Community Land Development Regulation 2021. The operative commencement is s 2, which states the Regulation commences on 1 December 2021 and is required to be published on the NSW legislation website. The Regulation contains a note in s 3 pointing practitioners to the Act and the Interpretation Act 1987 as containing definitions and other provisions that affect interpretation and application, which is a descriptive cross-reference rather than an amendment history.
No textual amendments or schedules of amendment appear in the provided text
The provided text does not include any notation, marginal note or amendment schedule indicating later modifications, repeals or transitional provisions. It does not reproduce a history table, amending instrument list, or dates of subsequent amending regulations. Accordingly, based solely on the supplied text, the Regulation should be treated as enacted and commenced on 1 December 2021, with no later amendments recorded within the document.
Implication for practitioners
Because the Regulation cross-references other instruments (lodgment rules, the Conveyancing (General) Regulation 2018, Real Property Act regulations, and the Surveying and Spatial Information Act 2002) and requires use of “approved forms”, practitioners should confirm current versions of those instruments and forms at the time of lodgment. The Regulation’s own absence of recorded amendments in the supplied text does not preclude the possibility of subsequent amending regulations outside the text; accordingly, check the NSW legislation website or the Registrar-General’s guidance for any amendments, practice directions or updated approved forms since commencement.
Transitional and saving provisions
The Regulation does not, in the supplied text, contain transitional or savings provisions addressing how instruments lodged before commencement are treated. Where transitional rules are required, they may be located in the Act, an amending instrument or Registrar-General notices; they are not present here.
Record-keeping for compliance
Because approved-form certificates and lodgment rules are administered outside the Regulation, practitioners should maintain a record of the exact versions of lodgment rules and approved forms used to prepare and lodge instruments, and any Registrar-General consents or certificates obtained, as part of compliance documentation.
In brief, the supplied Regulation text records only its own enactment name and the 1 December 2021 commencement date; no subsequent amendment history is set out in the material provided.
Litigation history
The Regulation text supplied contains no references to court or tribunal decisions, no annotated case citations and no judicial interpretation. The Regulation itself does not reproduce cases. Therefore, within the provided source there is no litigation history to report.
Absent direct litigation records, the Regulation’s contents point to potential dispute vectors that are likely to generate litigation or Tribunal applications under the Act and associated instruments. The Regulation itself identifies several procedural gates and discretionary decision points that may be the focus of future disputes, and those procedural requirements can give rise to litigation about registration refusal, the validity of certificates, association approvals and the Registrar-General’s exercise of discretion. The Regulation’s text highlights the following concrete areas that could generate disputes, and the mechanisms through which they might be litigated or subject to Tribunal review:
Registrar-General discretion on consolidated lodgment and sheet formats (s 7(5), s 28(2))
The Registrar-General may permit departures from single-sheet association property plans and consolidated management statement lodgments. Disputes may arise if the Registrar-General refuses such an application, or if the Registrar-General’s requirements are contested as being unreasonable, arbitrary, or inconsistent with the Act. Applicants may therefore seek administrative review or judicial review challenging exercise of discretion, or pursue interlocutory relief to enable registration pending decision.
Evidentiary certificates and statutory declarations (ss 21, 30)
The Regulation requires approved-form certificates verifying the expiration of the initial developer period (s 30) and statutory declarations verifying compliance with the Act’s decision rules (s 21). Disputes could arise over whether such certificates accurately reflect the underlying facts, whether association decisions were properly made, or whether statutory declarations are truthful. These disputes may be litigated in contexts where registration is refused or where third parties challenge the validity of registered instruments relying on such certificates.
Boundary adjustments and association approvals (s 15)
Boundary adjustment plans require an association certificate under seal confirming ordinary resolution approval, and a comprehensive surveyor report. Litigation or Tribunal disputes may emerge from challenges to the validity of the association’s ordinary resolution, disputes about whether proper notice or decision-making procedures were followed under the Act, or technical challenges to the surveyor report’s sufficiency.
Valuation day and apportionment of unit entitlements (s 31, s 29(3)-(4))
The Regulation prescribes the valuation day timing for unit entitlements and requires association certificates confirming apportionment for amalgamations. Disputes about the correct valuation day, the method of apportionment, or whether the association certificate correctly reflects compliance with the Act’s Schedule 3 rules could be raised in the Tribunal or courts when unit entitlement positions affect financial rights or levies.
Interaction with planning authority approvals and Tribunal authorisations (s 24, s 30)
Because the Regulation requires planning authority approvals to be evidenced in approved form, and contemplates Tribunal authorisations as preconditions to registration, disputes could arise concerning the sufficiency of planning authority approvals, the content of approval certificates, or the Tribunal’s determination to grant or withhold authorisation required by the Act.
Registration refusals and defective lodgments (secs 12, 16, 19, 25)
Failure to comply with lodgment rules or the prescribed content could lead the Registrar-General to refuse registration. Such refusals can be the subject of merits review or judicial review depending on the statutory avenues provided in the Act and other administrative law channels.
Practical note
The Regulation does not create new private rights or causes of action in itself beyond those in the Act, but it creates procedural preconditions and documentation requirements that can form the factual basis for litigation or Tribunal applications where registration, ownership, levies or access rights are contested. Parties seeking to avoid litigation should ensure careful adherence to the Regulation’s certification, survey and lodgment requirements and secure association approvals and Registrar-General consents where required.
Because there is no litigation history recorded in the Regulation itself, practitioners should search Tribunal and court databases, and consult Registrar-General guidance and case law interpreting the Act, for any post-enactment disputes that may develop around these procedural requirements.
Gotchas
The Regulation is technical and prescriptive. Small drafting, numbering, certification or timing mistakes can block registration or create downstream ripples. The following practical pitfalls arise directly from the Regulation’s text and should guide red-flag checks before lodgment.
Labelling and numbering are strict
Location, detail and association property plans require specific labels (“LOCATION PLAN”, “DETAIL PLAN”, “COMMUNITY PROPERTY PLAN”, “PRECINCT PROPERTY PLAN”, “NEIGHBOURHOOD PROPERTY PLAN”) in the plan drawing area (ss 5-7). Association property must be numbered Lot 1 and all other lots must be numbered consecutively beginning at Lot 2 on detail plans (s 6(3)-(4)) and the association property plan (s 7(4)). If the numbering sequence deviates, or association property is not Lot 1, a plan may be non-compliant.
Schedule of unit entitlement format and content
The schedule must have three columns with specific headings and content rules, including expressing association property using the words COMMUNITY PROPERTY, PRECINCT PROPERTY or NEIGHBOURHOOD PROPERTY and indicating public reserve or drainage reserve in particular ways (s 8(1)(b)). The total of individual unit entitlements must appear in the second column under “TOTAL” and an approved-form warning statement must be on the administration sheet (s 8(2)-(3)). These formatting requirements are administrative but mandatory.
Replacement sheet and sheet-numbering conventions
Replacement association property sheets must use the same sheet number as the sheet they replace, with an alphabetic suffix to indicate the number of times it has been replaced (s 10(2)(c)). Failing to use the proper suffixing convention could create indexing errors and registration issues.
Additional sheets must include the deposited plan number
Both additional detail sheets and replacement association property sheets must include the deposited plan number of the scheme (ss 9(2)(b), 10(2)(b)). Omitting the deposited plan number is a likely cause for rejection.
Association approvals must be by ordinary resolution and under seal
Boundary adjustment plans require a certificate under seal of the community or precinct association stating that the association approved the altered boundaries by ordinary resolution, and that certificate must be on the administration sheet (s 15(4)). If the association approval was not properly passed or no seal exists, registration will be impeded.
Surveyor reports and compilation of plan data
Boundary adjustments require a comprehensive surveyor report stating reasons for the adjustment and other Registrar-General-required information to be lodged with the plan (s 15(5)). The Regulation also allows compilation of unaltered boundaries from the relevant plan, but where conflicts exist the Registrar-General can require fresh survey information (ss 12(2), 14(1)(a), 18(2)). Assume the Registrar-General may insist on fresh surveys where records are stale or conflicting.
Statutory easement and access way diagrams require particular content
Statutory easement diagrams must show existing and proposed service lines, approximate positions through lots, the nature of each service and how it is provided, and contain the deposited plan number and scheme description on the first page (s 26). Access way plans must indicate that access ways remain association property and are not public roads, show how status changes between open and private access ways will be indicated and rely on detail plan survey data to define access way extents (s 27). Failure to include the required note that access ways are not public roads is explicitly required; omission can lead to rejection.
Lodgment rules and approved forms are external dependencies
The Regulation repeatedly requires compliance with Schedule 2 or Schedule 6 of the lodgment rules and use of approved forms (ss 19, 25, 8(3), 11(2), 24(1), 29(5), 30(2)). Those forms and lodgment tech requirements are not contained in the Regulation. Practitioners who prepare documents without the current approved forms or without conforming to the lodgment rules risk technical rejection even if substantive content is correct.
Timing traps for valuation days and initial period certificates
Valuation days are tied to specific events and windows (s 31). For example, some valuation days must be within two months before an application for a subdivision certificate; others are linked to the date of transfer where no subdivision certificate is required. Mis-timing valuation evidence can change unit entitlement calculations and lead to objections. Similarly, plans or dealings that require the initial developer period to have expired must be accompanied by an approved-form certificate (s 30), and the Tribunal’s lack of authorisation can change registration eligibility.
Acquisition plans and concurrent transfers
Acquisition plans must generally be lodged for registration at the same time as transfers of the land being acquired, unless the Registrar-General agrees otherwise in writing (s 16(7)). If transfers are lodged at different times, an acquisition plan could be delayed or rejected unless prior Registrar-General agreement is obtained.
A developer executing a dealing, plan or instrument for an association must provide a statutory declaration that sets out the meeting details and verifies compliance with the Act’s decision requirements (s 21(2)). If the statutory declaration lacks particulars of the meeting or does not verify compliance with the specific Act sections mentioned, the Registrar-General could withhold registration.
Amalgamation apportionment certificate
For standard amalgamations, the replacement schedule of unit entitlement must be accompanied by an association certificate under seal certifying the apportionment of unit entitlement in accordance with Act, Schedule 3, cl 13(2) (s 29(3)-(4)). Ensuring the apportionment is calculated and documented to match the Act’s Schedule 3 requirement is essential.
Prescribed public authorities list may be narrower than assumed
The Regulation prescribes a specific list of public authorities (s 32). Practitioners should not assume other utility providers automatically carry public authority status for the Act; where a provider is not listed, its role and notification obligations might differ.
Consolidated vs separate amendments to management statements
The default is consolidated lodging of amendments to management statements (s 28(1)). The Registrar-General may permit separate lodgment only in certain limited circumstances (s 28(2)). Expect resistance to piecemeal amendments unless an access way or statutory easement diagram is the only change or the Registrar-General is satisfied aggregated lodgment is onerous and other conditions are met.
Approved forms, ACNs and exact names matter
The Regulation lists entities by exact corporate name and ACN in s 32 (for example, Foxtel Management Pty Limited (ACN 068 671 938)). Using an incorrect corporate name or omitting an ACN when referencing a prescribed public authority in certificates may raise administrative issues.
In practice, the main “gotchas” are administrative: exact labelling, numbering, use of approved forms, association approval formalities and survey evidence. Checklist and cross-referencing are necessary steps to avoid delays.
How to comply
This section provides a concrete compliance checklist and sequencing notes tied to the Regulation’s provisions. It assumes the practitioner will also consult the lodgment rules (Schedules 2 and 6), the Act and any Registrar-General guidance or approved forms.
Pre-lodgment preparation and survey work
Engage a surveyor early. The Regulation requires detailed survey information on detail plans and additional sheets for subdivisions, acquisitions, boundary adjustments and conversions (ss 6(2), 9(1), 12(3), 15(3), 16(3), 18(1)). Ensure surveyors understand the Surveying and Spatial Information Act 2002 standards because “survey” is defined by that Act (s 3). For boundary adjustments, request a comprehensive surveyor report addressing reasons for adjustment and any Registrar-General-requested information and ensure it will be lodged with the plan (s 15(5)).
Sheet labelling, numbering and content checklist
Location plan: label “LOCATION PLAN” in the drawing area and include a schedule on which subsequent lot changes will be recorded (s 5).
Detail plan sheets: label “DETAIL PLAN” on each sheet, include detailed survey information for all lots including association property, number association property as Lot 1 and number other lots consecutively starting at Lot 2 (s 6). If adding additional sheets, follow the additional sheet rules (s 9).
Association property plan: use the required label (COMMUNITY, PRECINCT or NEIGHBOURHOOD PROPERTY PLAN), include boundaries and complete dimensions including area and part areas but omit detailed survey information, number association property Lot 1 and, unless approved otherwise by the Registrar-General, limit the association property plan to one sheet (s 7).
Schedules of unit entitlement
Prepare a three-column schedule headed LOT, UNIT ENTITLEMENT and SUBDIVISION. For association property include the words COMMUNITY PROPERTY, PRECINCT PROPERTY or NEIGHBOURHOOD PROPERTY as applicable. For lots to be dedicated as public or drainage reserves use the words PUBLIC RESERVE or DRAINAGE RESERVE. Populate the “UNIT ENTITLEMENT” column with values for other lots, place “TOTAL” in the LOT column and the total unit entitlement in the UNIT ENTITLEMENT column. Add the approved-form warning statement on the administration sheet (s 8).
Additional and replacement sheets
Additional sheets must include an approved-form note indicating they are additional sheets, the deposited plan number and be sequentially numbered after the last sheet used for the scheme plan (s 9). Replacement association property sheets must contain an approved-form replacement note, deposited plan number, and the same sheet number as the sheet being replaced plus alphabetic suffixes to indicate iterations (s 10). Replacement schedules must include the replacement note on the administration sheet (s 11).
Plans for subdivision, consolidation, acquisition and boundary adjustments
Subdivision: ensure the scheme plan of subdivision shows only the lots being subdivided, that new lot boundaries following existing lot boundaries can be compiled from the scheme plan where appropriate, and include detailed survey info for altered association property on the additional sheet; renumber new lots starting from the next available lot number and include the required replacement schedule of unit entitlement entries and references (s 12).
Consolidation: additional sheets may be compiled from relevant scheme plan information and must show only the lots being consolidated; new lots must be consecutively numbered and replacement schedule must include the required references and entitlements (s 14).
Acquisition: show only the lots to be acquired on the acquisition plan, depict residues on accompanying replacement or additional sheets as whole lots depending on the lot type, include survey results for altered boundaries, and lodge the acquisition plan concurrently with transfers unless Registrar-General agrees otherwise in writing (s 16).
Boundary adjustment: include a plan illustrating altered boundaries, show original lot numbers, include detailed survey info on the additional sheet, include an association certificate under seal confirming ordinary resolution approval, and lodge a comprehensive surveyor report with the plan (s 15).
Development contracts and management statements
For lodgment, ensure proposed development contracts and proposed management statements comply with the lodgment rules for paper (Schedule 2) or electronic form (Schedule 6) (ss 19, 25).
Development contracts must include a description of proposed buildings, services and infrastructure on association property, details of proposed easements and covenants affecting association property, and specify whether any land to be added is to be development, neighbourhood or association property (s 20). List authorised proposals and warranted development separately and ensure the included concept plan relates to authorised proposals and warranted development (s 20(2)-(3)).
Proposed management statements must be signed by or on behalf of the developer (s 25(3)).
Execution formalities and statutory declarations
When a relevant developer executes a dealing, plan or instrument on behalf of an association, execute in the approved form and prepare a statutory declaration that sets out the meeting particulars and verifies compliance with the Act’s decision provisions (s 21(1)-(2)). If the relevant developer is a corporation, the statutory declaration must be by a director or officer (s 21(3)).
Certificates, approved forms and lodgment rules
Identify the approved forms required and obtain them from the Registrar-General or the lodgment rules guidance. The Regulation requires approved-form certificates for items such as the warning statement on schedules (s 8(3)), the association and boundary adjustment certificates (ss 15(4), 29(3)-(4)), and the planning authority certificates (s 24). Ensure the certificates match the Registrar-General’s current approved forms.
Amendments to management statements
Amendments must generally be lodged as a consolidated version that incorporates the amendment (s 28(1)). If the amendment relates only to an access way plan or statutory easement diagram, lodge separately. Otherwise, if consolidated lodging would be too onerous and there are no more than five separate changes recorded on the folio, apply to the Registrar-General to permit separate lodging (s 28(2)). Make this application well before lodgment to avoid processing delays.
Access way and statutory easement diagrams
Prepare statutory easement diagrams showing existing and proposed service lines, approximate positions within lots, and the nature and provision method of each service; include the deposited plan number and scheme description on the first page (s 26).
Prepare access way plans that show the position of each access way, define the extent of each open and private access way, indicate how status changes will be identified, show names where given with “known as” prefix, include a note that access ways remain association property and are not public roads and be numbered as a sheet of the management statement; ensure all survey information to define access ways is shown on the detail plan (s 27).
Valuation days and unit entitlement evidence
For unit entitlement calculations, follow s 31. Determine whether your valuation day must be a day within 2 months before an application for a subdivision certificate, the valuation day for the original scheme plan, or a day set in relation to a transfer where a subdivision certificate is not required (s 31). Obtain and preserve valuation evidence dated within the prescribed windows.
Amalgamation and apportionment
For amalgamation applications, ensure the additional sheet shows updated survey information and new lots are consecutively numbered from the next available lot number; prepare a replacement schedule of unit entitlement accompanied by an association certificate under seal stating the unit entitlement apportionment complies with the Act, Schedule 3, cl 13(2) (s 29).
Prescribed public authorities and notifications
Consult s 32 to identify which entities are prescribed public authorities for the Act. Where the Act requires consultation or notices to public authorities, be aware that only the listed entities have that status under the Regulation.
Concurrent lodgment and Registrar-General consents
Where the Regulation requires concurrent lodgment, such as acquisition plans with transfers (s 16(7)), organise transfers and plan lodgment to occur simultaneously unless you have obtained a written Registrar-General agreement in advance.
Practical sequencing and project plan
Early stage: instruct surveyor, confirm survey standards and scope, and map lots and association property as Lot 1 in preliminary drawings.
Mid stage: prepare detail plan(s), association property plan, schedule of unit entitlement and any statutory easement or access way diagrams; obtain developer signature on management statement drafts and prepare development contract content.
Association approvals: secure ordinary resolution approval and association seal certificates for boundary adjustments or amalgamations where required (ss 15(4), 29(3)-(4)).
Pre-lodgment checks: ensure all labelling, numbering, deposited plan numbers, approved-form notes, replacement sheet suffixes and schedule formatting are correct; confirm valuation day evidence is within prescribed windows (s 31) and that approved forms are the current versions.
Lodgment: lodge development contracts and management statements in paper or electronic form per lodgment rules (ss 19, 25), include any statutory declarations required for developer-executed dealings (s 21), and lodge acquisition plans with transfers unless Registrar-General consent permits otherwise (s 16(7)).
Post-lodgment: follow up Registrar-General queries, be prepared to supply additional surveys or revised forms, and maintain records of Registrar-General consents and approved-form certificates used.
Record keeping and documentation
Retain copies of all approved-form certificates, statutory declarations, association resolutions and seals, surveyor reports, valuation evidence and versions of schedules and plans that were lodged. These documents will be essential to respond to Registrar-General queries, to defend registration challenges and to demonstrate compliance with the Regulation.
In short, compliance requires early coordination between developers, surveyors, associations and conveyancers to deliver properly labelled, numbered and certified plans and schedules in the approved form and in the lodgment mode required by the lodgment rules.
(a) be clearly labelled “LOCATION PLAN” in the plan drawing area, and
(b) contain a schedule on which to record subsequent subdivisions, consolidations, severances and other changes to lots in the scheme.
6 Detail plans—the Act, Schedule 1, cl 1(2)(b)
6 Detail plans—the Act, Schedule 1, cl 1(2)(b)
6 Detail plans—the Act, Schedule 1, cl 1(2)(b)
(1) Each sheet of a detail plan included in a scheme plan must be clearly labelled “DETAIL PLAN” in the plan drawing area.
(2) The detail plan must set out the detailed survey information for all of the lots in the scheme, including the association property.
(3) The association property must be numbered “Lot 1” and, if it comprises more than 1 part, each part must be identified as part of Lot 1.
(4) All other lots on the detail plan must be numbered consecutively, beginning with “Lot 2”.
7 Association property plans—the Act, Schedule 1, cl 1(2)(b)
7 Association property plans—the Act, Schedule 1, cl 1(2)(b)
7 Association property plans—the Act, Schedule 1, cl 1(2)(b)
(1) An association property plan included in a scheme plan must be clearly labelled with one of the following, as the case requires, in the plan drawing area—
COMMUNITY PROPERTY PLAN
PRECINCT PROPERTY PLAN
NEIGHBOURHOOD PROPERTY PLAN
(2) The association property plan must be a diagram showing all association property in the scheme.
(3) The association property plan must include the boundaries and complete dimensions, including area and part areas, of the whole of the association property but without the detailed survey information.
(4) The association property must be numbered “Lot 1” and, if it comprises more than 1 part, each part must be identified as part of Lot 1.
(5) Unless the Registrar-General otherwise agrees, the association property plan must comprise 1 sheet only.
8 Schedules of unit entitlement—the Act, s 115(2)(c)
8 Schedules of unit entitlement—the Act, s 115(2)(c)
8 Schedules of unit entitlement—the Act, s 115(2)(c)
(1) A schedule of unit entitlement accompanying a scheme plan must contain 3 columns as follows—
(a) the first column, headed “LOT”, must list the lots in the scheme in numerical order,
(b) the second column, headed “UNIT ENTITLEMENT”, must contain—
(i) for the association property—the words “COMMUNITY PROPERTY”, “PRECINCT PROPERTY” or “NEIGHBOURHOOD PROPERTY”, as the case requires, and
(ii) for a lot that is to be dedicated as a public reserve or drainage reserve—the words “PUBLIC RESERVE” or “DRAINAGE RESERVE”, as the case requires, and
(iii) for each other lot—the value of the unit entitlement,
(c) the third column, headed “SUBDIVISION”, must record details of subsequent subdivisions, consolidations, severances and other changes to lots as they occur.
(2) At the end of the schedule of unit entitlement—
(a) the first column must contain the word “TOTAL”, and
(b) the second column must contain the total value of all the unit entitlements of the individual lots referred to in subsection (1)(b)(iii).
(3) A warning statement that the schedule of unit entitlement may be altered or replaced must be—
(a) in the approved form, and
(b) set out in the panels provided on the administration sheet required to accompany the scheme plan.
Part 3 Additional sheets and replacement sheets and schedules
Part 3 Additional sheets and replacement sheets and schedules
Part 3 Additional sheets and replacement sheets and schedules
9 Additional sheet of a detail plan—the Act, Schedule 1, cl 1(2)(b)
9 Additional sheet of a detail plan—the Act, Schedule 1, cl 1(2)(b)
9 Additional sheet of a detail plan—the Act, Schedule 1, cl 1(2)(b)
(1) An additional sheet of a detail plan must comply with the requirements in section 6, to the extent that the requirements are relevant to an additional sheet.
(2) An additional sheet must also—
(a) contain a note in the note column, in the approved form, indicating the sheet is an additional sheet, and
(b) include the deposited plan number of the scheme, and
(c) be numbered with the next sheet number after the last number used for the scheme plan.
10 Replacement sheet for an association property plan—the Act, Schedule 1, cl 1(2)(b)
10 Replacement sheet for an association property plan—the Act, Schedule 1, cl 1(2)(b)
10 Replacement sheet for an association property plan—the Act, Schedule 1, cl 1(2)(b)
(1) A replacement sheet for an association property plan must comply with the requirements in section 7, to the extent that the requirements are relevant to a replacement sheet.
(2) A replacement sheet must also—
(a) contain a note in the note column, in the approved form, indicating that the sheet is a replacement sheet, and
(b) include the deposited plan number of the scheme, and
(c) be numbered with the same sheet number as the sheet it is to replace, together with an alphabetic suffix to indicate the number of times the sheet has been replaced.
11 Replacement schedule of unit entitlement—the Act, s 115(2)(c)
11 Replacement schedule of unit entitlement—the Act, s 115(2)(c)
11 Replacement schedule of unit entitlement—the Act, s 115(2)(c)
(1) A replacement schedule of unit entitlement must comply with the requirements in section 8, to the extent that the requirements are relevant to a replacement schedule.
(2) The administration sheet containing the replacement schedule must contain a note, in the approved form, indicating that the schedule is a replacement schedule.
Part 4 Plans and instruments
Part 4 Plans and instruments
Part 4 Plans and instruments
12 Subdivision by scheme plan of subdivision—the Act, Schedule 1, cl 1(2)(b)
12 Subdivision by scheme plan of subdivision—the Act, Schedule 1, cl 1(2)(b)
12 Subdivision by scheme plan of subdivision—the Act, Schedule 1, cl 1(2)(b)
(1) A scheme plan of subdivision must show only the lots subject to the subdivision.
(2) The boundaries of new lots that follow the boundaries of existing lots may be compiled from the relevant scheme plan.
(3) The additional sheet of the detail plan required to be included with the scheme plan of subdivision must also include the detailed survey information for the altered association property.
(4) The new lots on the additional sheet of the detail plan must be numbered consecutively, beginning with the next available lot number for the scheme.
(5) The replacement schedule of unit entitlement required to be included with the scheme plan of subdivision must also include the following—
(a) in the “LOT” column—a list of the lots being created,
(b) in the “UNIT ENTITLEMENT” column—
(i) for each lot being subdivided—a reference to the new lots being created, and
(ii) for each lot being created—its unit entitlement,
(c) in the “SUBDIVISION” column—opposite each lot being subdivided, a reference to the sheet of the scheme plan of subdivision that created the new lots.
13 Dedication of land by scheme plan of subdivision—the Act, Schedule 1, cl 1(2)(b)
13 Dedication of land by scheme plan of subdivision—the Act, Schedule 1, cl 1(2)(b)
13 Dedication of land by scheme plan of subdivision—the Act, Schedule 1, cl 1(2)(b)
A scheme plan of subdivision may dedicate association property as a public road, a public reserve or a drainage reserve.
Note—
The Act, section 15 applies to a scheme plan of subdivision that dedicates association property as a public road, a public reserve or a drainage reserve.
14 Consolidation by scheme plan of consolidation—the Act, Schedule 1, cl 1(2)(b)
14 Consolidation by scheme plan of consolidation—the Act, Schedule 1, cl 1(2)(b)
14 Consolidation by scheme plan of consolidation—the Act, Schedule 1, cl 1(2)(b)
(1) An additional sheet of the detail plan required to be included with a scheme plan of consolidation—
(a) may be compiled from information in the relevant scheme plan, and
(b) must show only the lots subject to the consolidation.
(2) The new lots on the additional sheet of the detail plan must be numbered consecutively, beginning with the next available lot number for the scheme.
(3) The replacement schedule of unit entitlement required to be included with a scheme plan of consolidation must also include the following—
(a) in the “LOT” column—a list of the newly consolidated lots,
(b) in the “UNIT ENTITLEMENT” column—
(i) against the superseded lots—a reference to the relevant consolidated lot, and
(ii) for each consolidated lot—its unit entitlement,
(c) in the “SUBDIVISION” column—a reference to the sheet of the scheme plan that shows the consolidated lot.
15 Boundary adjustment plans—the Act, s 18(2)(d) and Schedule 1, cl 1(2)(b)
15 Boundary adjustment plans—the Act, s 18(2)(d) and Schedule 1, cl 1(2)(b)
15 Boundary adjustment plans—the Act, s 18(2)(d) and Schedule 1, cl 1(2)(b)
(1) A boundary adjustment plan must—
(a) illustrate the results of a survey identifying the altered boundaries of the community property or precinct property and of the affected development lots, and
(b) include the original lot numbers of the affected development lots.
(2) Other boundaries shown on the boundary adjustment plan that have not been altered may be compiled from the relevant community plan or precinct plan.
(3) An additional sheet of the detail plan required to be included in a boundary adjustment plan must also include detailed survey information for the altered boundaries of the affected development lots.
(4) The administration sheet required to accompany the boundary adjustment plan must include a certificate—
(a) in the approved form, and
(b) given under seal of the community association or precinct association, and
(c) to the effect that the association approved the altered boundaries by an ordinary resolution of the association.
(5) A comprehensive report provided by a surveyor stating the reasons for the boundary adjustment, and containing other information required by the Registrar-General, must be lodged with the boundary adjustment plan.
(6) If an adjustment is made by the boundary adjustment plan that causes the position of an open access way or a private access way to move—
(a) an amendment must be made to the access way plan, and
(b) an amendment to the management statement must be registered under the Act, section 108.
16 Acquisition plans—the Act, s 115 and Schedule 1, cl 1(2)(b)
16 Acquisition plans—the Act, s 115 and Schedule 1, cl 1(2)(b)
16 Acquisition plans—the Act, s 115 and Schedule 1, cl 1(2)(b)
(1) An acquisition plan must show only the lots to be acquired and must not show residue lots.
(2) If part of a lot is to be acquired, the residue that is not being acquired and will remain in the scheme must be shown as a whole lot in—
(a) if the part to be acquired is association property—the replacement sheet for the association property plan required to be lodged with the acquisition plan, or
(b) if the part to be acquired is a development lot or neighbourhood lot—the additional sheet of the detail plan required to be lodged with the acquisition plan.
(3) The acquisition plan, and the replacement sheet for the association property plan or additional sheet of the detail plan required to be lodged with the plan, must illustrate the results of a survey identifying the altered boundaries of the affected lots.
(4) Other boundaries shown on the acquisition plan, or on the replacement or additional sheet, that have not been altered may be compiled from the relevant scheme plan.
(5) A replacement sheet for an association property plan required to be lodged with an acquisition plan must also be accompanied by an additional sheet of the detail plan showing the updated survey information for the altered boundaries.
(6) The new lots on the additional sheet of a detail plan must be numbered consecutively, beginning with the next available lot number for the scheme.
(7) The acquisition plan must be lodged for registration at the same time as the transfers of the land being acquired under the plan, unless the Registrar-General agrees otherwise in writing.
Part 5 Instruments of severance and conversion
Part 5 Instruments of severance and conversion
Part 5 Instruments of severance and conversion
17 Severance of development lots—the Act, s 115(2)(c)
17 Severance of development lots—the Act, s 115(2)(c)
17 Severance of development lots—the Act, s 115(2)(c)
The replacement schedule of unit entitlement required to accompany an instrument under the Act, section 19 must include, in the “UNIT ENTITLEMENT” column, the words “SEVERED LOT” for each lot severed by the instrument.
18 Conversion of development lots or neighbourhood lots to association property—the Act, s 115
18 Conversion of development lots or neighbourhood lots to association property—the Act, s 115
18 Conversion of development lots or neighbourhood lots to association property—the Act, s 115
(1) An instrument of conversion must be accompanied by an additional sheet of the detail plan for the relevant scheme plan showing the updated detailed survey information for the altered boundaries.
(2) The additional sheet of the detail plan may be c