17G Costs and damages (Model Law Art 17G)
(1) The party requesting an interim measure is liable for any costs and
damages caused by the measure to any party if the arbitral tribunal
later determines that, in the circumstances, the measure should not
have been granted.
(2) The arbitral tribunal may award such costs and damages at any
point during the proceedings.
Note for section 17G
This section is substantially the same as Art 17G of the Model Law but the
reference to applications for preliminary orders is omitted as a consequence of
this Act not including equivalents to Arts 17B and 17C of the Model Law.