This Local Environmental Plan sets the legal land‑use rules for the Cobar area: maps and zones, what uses are permitted, prohibited or need development consent, subdivision and lot‑size rules, exemptions/complying development pathways, heritage and environmental overlays, and local technical rules (aquaculture, airport airspace and noise, flood planning). It affects landowners, developers, the Council and state/Commonwealth agencies because it determines where and how housing, industry, agriculture, tourism and conservation may proceed, changing approval costs, obligations and discretionary decision‑making.
This instrument is a local environmental plan for Cobar. It (a) establishes the zoning framework and land use controls that apply to land identified on the Land Zoning Map; (b) sets the development consent regime for most forms of development on that land, including exemptions and complying development pathways; (c) imposes development standards (notably minimum lot sizes and zone-specific controls) and detailed local provisions about environmental, heritage and infrastructure matters; and (d) brings a suite of maps and schedules into force as part of the planning control framework.
Mechanically, the Plan operates by: defining the consent authority (the Council, cl 1.6), designating zones (cl 2.1) and mapping land into those zones (cl 2.2 and the Land Zoning Map), and attaching to each zone (via the Land Use Table) the types of development that are permitted without consent, permitted only with consent, and prohibited (cl 2.3 and the Land Use Table). The Plan also: prescribes exempt development (Part 3, cl 3.1 and Schedule 2) and complying development (cl 3.2 and Schedule 3), sets principal development standards including minimum subdivision lot sizes (Part 4, cl 4.1 and related clauses), and establishes a range of local development controls (Part 5 and Part 6) addressing heritage (cl 5.10 and Schedule 5), biodiversity (cl 6.4), riparian land and watercourses (cl 6.6), groundwater vulnerability (cl 6.5), stormwater (cl 6.3) and flood planning (cl 5.21), among others.
The Plan references and defers to State-level instruments and Acts in multiple places. It is expressly subject to any State environmental planning policy that prevails over it under s 3.28 of the Environmental Planning and Assessment Act (cl 1.9), and it repeatedly cross‑refers to the Act and to other statutes (for example, Local Government Act 1993, Heritage Act 1977, Crown Land Management Act 2016, Biodiversity Conservation Act 2016 and Fisheries/Marine Acts) when conferring or limiting powers and when excluding or requiring consultation. Maps and numerical standards (for example minimum lot sizes) are implemented by reference to the Lot Size Map, Heritage Map, Terrestrial Biodiversity Map, Groundwater Vulnerability Map and other maps that are published and maintained alongside the Plan (cl 1.7; multiple clauses).
Current sections
Direct links to the current provisions in Cobar Local Environmental Plan 2012.
State Environmental Planning Policy (Transport and Infrastructure) 2021, Chapter 2—relating to infrastructure facilities, including air transport, correction, education, electricity generating works and solar energy systems, health services, ports, railways, roads, waste management and water supply systems
Agritourism; Air transport facilities; Airstrips; Animal boarding or training establishments; Aquaculture; Bed and breakfast accommodation; Boat launching ramps; Boat sheds; Building identification signs; Business identification signs; Camping grounds; Cellar door premises; Cemeteries; Community facilities; Correctional centres; Depots; Dual occupancies; Dwelling houses; Eco-tourist facilities; Environmental facilities; Extractive industries; Farm buildings; Farm stay accommodation; Forestry; Freight transport facilities; Helipads; Highway service centres; Home businesses; Home industries; Home occupations (sex services); Industrial training facilities; Intensive livestock agriculture; Intensive plant agriculture; Jetties; Mooring pens; Moorings; Open cut mining; Recreation areas; Recreation facilities (major); Recreation facilities (outdoor); Roadside stalls; Rural industries; Rural workers’ dwellings; Water recreation structures; Water supply systems
4
Prohibited
4 Prohibited
4 Prohibited
Any development not specified in item 2 or 3
Part 3
Exempt and complying development
Part 3 Exempt and complying development
Part 3 Exempt and complying development
Part 4
Principal development standards
Part 4 Principal development standards
Part 4 Principal development standards
Part 5
Miscellaneous provisions
Part 5 Miscellaneous provisions
Part 5 Miscellaneous provisions
5
Relevant acquisition authority
5 Relevant acquisition authority
5.1 Relevant acquisition authority
(1) The objective of this clause is to identify, for the purposes of section 3.15 of the Act, the authority of the State that will be the relevant authority to acquire land reserved for certain public purposes if the land is required to be acquired under Division 3 of Part 2 of the Land Acquisition (Just Terms Compensation) Act 1991 (the owner-initiated acquisition provisions).
Note.
If the landholder will suffer hardship if there is any delay in the land being acquired by the relevant authority, section 23 of the Land Acquisition (Just Terms Compensation) Act 1991 requires the authority to acquire the land.
(2) The authority of the State that will be the relevant authority to acquire land, if the land is required to be acquired under the owner-initiated acquisition provisions, is the authority of the State specified below in relation to the land shown on the Land Reservation Acquisition Map (or, if an authority of the State is not specified in relation to land required to be so acquired, the authority designated or determined under those provisions).
| Type of land shown on Map | Authority of the State |
| Zone RE1 Public Recreation and marked “Local open space” | Council |
| Zone RE1 Public Recreation and marked “Regional open space” | The corporation constituted under section 2.5 of the Act |
| Zone SP2 Infrastructure and marked “Classified road” | Transport for NSW |
| Zone C1 National Parks and Nature Reserves and marked “National Park” | Minister administering the National Parks and Wildlife Act 1974 |
(3) Development on land acquired by an authority of the State under the owner-initiated acquisition provisions may, before it is used for the purpose for which it is reserved, be carried out, with development consent, for any purpose.
Note.
When this Plan was made, no land in the zones listed in the Table to subclause (2) was included on the Land Reservation Acquisition Map.
Part 6
Additional local provisions
Part 6 Additional local provisions
Part 6 Additional local provisions
6
Earthworks
6 Earthworks
6.1 Earthworks
(1) The objectives of this clause are as follows—
(a) to ensure that earthworks for which development consent is required will not have a detrimental impact on environmental functions and processes, neighbouring uses, cultural or heritage items or features of the surrounding land,
(b) to allow earthworks of a minor nature without requiring a separate development consent.
(2) Development consent is required for earthworks unless—
(a) the earthworks are exempt development under this Plan or another applicable environmental planning instrument, or
(b) the earthworks are ancillary to other development for which development consent has been given.
(3) Before granting development consent for earthworks, the consent authority must consider the following matters—
(a) the likely disruption of, or any detrimental effect on, existing drainage patterns and soil stability in the locality of the development,
(b) the effect of the development on the likely future use or redevelopment of the land,
(c) the quality of the fill or the soil to be excavated, or both,
(d) the effect of the proposed development on the existing and likely amenity of adjoining properties,
(e) the source of any fill material and the destination of any excavated material,
(f) the likelihood of disturbing relics,
(g) the proximity to, and potential for adverse impacts on, any watercourse, drinking water catchment or environmentally sensitive area.
Exempt development may be carried out without the need for development consent under the Act. Such development is not exempt from any approval, licence, permit or authority that is required under any other Act and adjoining owners’ property rights and the common law still apply.
(When this Plan was made this Schedule was blank.)
Classification and reclassification of public land
Schedule 4 Classification and reclassification of public land
Schedule 4 Classification and reclassification of public land
(Clause 5.2)
Schedule 5
Environmental heritage
Schedule 5 Environmental heritage
Schedule 5 Environmental heritage
(Clause 5.10)
| Suburb | Item name | Address | Property description | Significance | Item number |
| Cobar | Church of England | Barton Street | Lot 13 Section 1, DP 459; Lot 1, DP 344526; Lot 1, DP 724770 | Local | I5 |
| Cobar | Cobar Courthouse | Barton Street | Lot 11, Section 1, DP 459 | Local | I6 |
| Cobar | Police Station, lock up and cells (former) | Barton Street | Lot 10, Section 1, DP 459 | Local | I17 |
| Cobar | Police Station and barracks | Barton Street | Lot 9, Section 1, DP 459 | Local | I18 |
| Cobar | Professional offices (former Tattersalls then Course House Hotel) | Barton Street, (corner Broomfield Street) | Lot 11, DP 627815 | Local | I19 |
| Cobar | St. Margaret’s Uniting Church | Barton Street | Lot 17, Section 1, DP 459; Lot 1, DP 105639; Lot 1, DP 913246 | Local | I23 |
| Cobar | Cobar Fire Station | 39 Barton Street | Lot 15, Section 1, DP 459 | Local | I7 |
| Cobar | CSIRO, Soil Research Division (former School of Arts) | 13 Becker Street | Lot 15, Section 3, DP 2659 | Local | I11 |
| Cobar | Dwelling house (former St. Margaret’s Presbyterian Manse) | 28 Becker Street | Lot 6, DP 513634 | Local | I12 |
| Cobar | School Masters Residence | 10 Blakey Street | Lot A, DP 32924 | Local | I20 |
| Cobar | Masonic Hall | 16 Bourke Street | Lot 1, DP 334489 | Local | I15 |
| Cobar | Dwelling house | Brough Street | Lot 2, Section 9, DP 3177 | Local | I13 |
| Cobar | Towser’s Huts | Fort Bourke Hill, off Kidman Way, Chesney Gold Mine | Lot 2, DP 1019612 | Local | I24 |
| Cobar | Cobar Post Office | Linsley Street | Lot 222, DP 733322 | Local | I9 |
| Cobar | Hotel Corner, Great Western Hotel 1895 | Linsley Street (corner Marshall Street) | Lot 11, DP 635658 | Local | I14 |
| Cobar | Municipal Council Chambers (former) | Linsley Street | Lot 82, DP 539846 | Local | I16 |
| Cobar | Bulk Store (Former Wright Heaton & Co Ltd) | Linsley Street (North) | Lots 1 and 2, Section 2, DP 2780 | Local | I4 |
| Cobar | Brick cottage | 5 Murray Street | Lots 20 and 21, DP 599 | Local | I1 |
| Cobar | Brick cottage | 11 Murray Street | Lots 27 and 30, DP 599 | Local | I2 |
| Cobar | “Woodleigh” | 13 Murray Street | Lot 2, DP 521345 | Local | I25 |
| Cobar | Cobar Pastoral and Mining Technology Museum 1910 (former Mining Administration Offices, Great Cobar Mines) | Nyngan Road | Lot 181, DP 1036962 | Local | I8 |
| Cobar | Building (former Roman Catholic Presbytery circa 1880) | Prince Street | Lot 93, DP 599 | Local | I3 |
| Cobar | Sisters of Mercy Convent and classrooms 1884 | Prince Street | Lots 123, 125 and 126, DP 599 | Local | I21 |
| Cobar | St. Lawrence O’Toole Roman Catholic Church | Prince Street | Lot 124, DP 599 | Local | I22 |
| Cobar | Cobar Railway Station and yard | South Railway Parade, Nyngan-Cobar railway | Lot 1, DP 839948 | State | I10 |
Schedule 6
Pond-based and tank-based aquaculture
Schedule 6 Pond-based and tank-based aquaculture
Schedule 6 Pond-based and tank-based aquaculture
(Clause 5.19)
Division 1
Site location requirements
Division 1 Site location requirements
Division 1 Site location requirements
Division 2
Operational requirements
Division 2 Operational requirements
Division 2 Operational requirements
7
Conservation exclusion zones
7 Conservation exclusion zones
7 Conservation exclusion zones
(1) Must not be carried out on the following land, except to the extent necessary to gain access to water—
(c) land within a wetland of international significance declared under the Ramsar Convention on Wetlands.
Note.
Nothing in this clause affects any requirement under an Act relating to land specified in this clause to obtain a licence or other authority under that Act for development of the land.
8
Flood liability
8 Flood liability
8 Flood liability
Must be designed or constructed on land so that it will not be inundated by the discharge of a 1:100 ARI (average recurrent interval) flood event.
9
Species selection
9 Species selection
9 Species selection
Species of fish or marine vegetation cultivated or kept must be consistent with the relevant aquaculture industry development plan (within the meaning of clause 5.19).
10
Pond design
10 Pond design
10 Pond design
(1) Must not require the construction of new ponds, water storages, dams or buildings.
(2) Must not be located on permanent watercourses, creeks, billabongs or isolated outreaches of creeks or rivers.
(3) Must be capable of preventing the escape of stock into natural waterbodies or wetlands.
11
Culture water
11 Culture water
11 Culture water
Must use freshwater.
Source text: opening excerpt
Sourced from legislation.nsw.gov.au, CC BY 4.0.
Part 1 Preliminary
Part 1 Preliminary
Part 1 Preliminary
1 Name of Plan
1 Name of Plan
1.1 Name of Plan
This Plan is Cobar Local Environmental Plan 2012.
1 Commencement
1 Commencement
1.1AA Commencement
This Plan commences on the day on which it is published on the NSW legislation website.
1 Aims of Plan
1 Aims of Plan
1.2 Aims of Plan
(1) This Plan aims to make local environmental planning provisions for land in Cobar in accordance with the relevant standard environmental planning instrument under section 3.20 of the Act.
(2) The particular aims of this Plan are as follows—
(aa) to protect and promote the use and development of land for arts and cultural activity, including music and other performance arts,
(a) to protect, enhance and conserve agricultural land through the proper management, development and conservation of natural and man-made resources,
(b) to encourage a range of housing, employment, recreation and community facilities to meet the needs of existing and future residents of Cobar,
(c) to promote the efficient and equitable provision of public services, infrastructure and amenities.
The Dictionary at the end of this Plan defines words and expressions for the purposes of this Plan.
1 Notes
1 Notes
1.5 Notes
Notes in this Plan are provided for guidance and do not form part of this Plan.
1 Consent authority
There are also discrete local measures with immediate operational effect. Examples drawn from the Plan include: the savings provision that requires pre-commencement development applications to be determined under the pre-existing controls (cl 1.8A); a broad suspension of private covenants and similar instruments to the extent necessary to enable development in accordance with the Plan, subject to enumerated exclusions (cl 1.9A); a prohibition on canal estate development (cl 2.9); a cap on temporary uses to 52 days in any 12-month period (cl 2.8); and a prohibition on refusing consent for licensed premises solely because of certain features of live or amplified music or entertainment where noise can be managed (cl 5.20).
Finally, the Plan sets out the procedural and evidentiary matters that a consent authority must consider before granting consent for specified development types (for example, intensive livestock agriculture at cl 5.18, eco-tourist facilities at cl 5.13, and airspace operations in the vicinity of Cobar Airport at cl 6.8). Where the Plan is silent on penalty or enforcement mechanisms, it invokes the relevant provisions of the Act and other statutes for implementation and enforcement (see multiple references to the Act, for example cl 1.2 and cl 1.6).
Main concepts
The Plan uses a conventional territorial zoning model implemented through a Land Use Table and map layers. The principal concepts are:
Zoning and the Land Use Table: The Plan lists zones (cl 2.1) , rural (RU1, RU3, RU5), residential (R1, R2, R5), employment (E1, E4), special purpose (SP2), recreation (RE1, RE2) and conservation (C1, C3). For each zone the Land Use Table sets out the objectives for development in the zone and then categorises development as permitted without consent, permissible with consent, or prohibited (cl 2.3 and the Land Use Table). The consent authority must have regard to zone objectives when deciding applications (cl 2.3(2)).
Maps and maps-as-evidence: Clause 1.7 makes named maps (Land Zoning Map, Lot Size Map, Heritage Map, Terrestrial Biodiversity Map, Groundwater Vulnerability Map, Watercourse Map, Wetlands Map, Land Reservation Acquisition Map, Obstacle Limitation Surface Map, Noise Exposure Forecast Contour Map and others) part of the Plan and requires public availability. Many standards and applicability thresholds are implemented solely by reference to those maps (for example lot sizes under cl 4.1).
Development consent as gate: Development consent is required for the majority of land uses and for subdivision (cl 2.6) and demolition (cl 2.7), unless a use is expressly permitted without consent by the Land Use Table or is exempt/compliant under Part 3. The Plan creates a three-pathway system: exempt development (cl 3.1 and Schedule 2), complying development (cl 3.2 and Schedule 3) and development requiring consent (Land Use Table and zone provisions).
Exempt, complying and environmentally sensitive area exclusions: Part 3 identifies exempt and complying development, but it also excludes such development from environmentally sensitive areas defined in cl 3.3 (for example coastal waters, Ramsar wetlands, land of high Aboriginal cultural significance and other mapped areas).
Principal development standards and exceptions: Part 4 establishes minimum lot sizes for subdivision and special lot-size rules for strata/community schemes (cl 4.1, cl 4.1AA, cl 4.1A). Clause 4.6 provides a discretionary mechanism to allow departures from development standards where the applicant demonstrates that compliance is unreasonable or unnecessary and that there are sufficient environmental planning grounds; the consent authority must keep a record of the assessment (cl 4.6(3)-(4)). Clause 4.6 expressly excludes application to some standards (for complying development, BASIX commitments, and clauses 5.4 and 5.5 as identified).
Local environmental protections layered into consent tests: A range of local matters are mandatory considerations for consent authorities. Examples include heritage (cl 5.10 and Schedule 5), terrestrial biodiversity (cl 6.4 and Terrestrial Biodiversity Map), riparian land and watercourses (cl 6.6 and Watercourse Map), groundwater vulnerability (cl 6.5 and Groundwater Vulnerability Map), stormwater management (cl 6.3), intensive livestock agriculture (cl 5.18) and flood planning and climate-change considerations (cl 5.21). For many of these the consent authority must be satisfied that the development will avoid significant adverse environmental impacts or, if not, that impacts will be minimised or mitigated (see cl 6.4(4), 6.5(4), 6.6(4) and 6.7(4)).
Specific local rules: The Plan contains numerous specific rules for particular land uses, such as the limits on bed and breakfast rooms and farm stay rooms (cl 5.4(1) and (5)), maximum retail floor areas for neighbourhood shops and industrial retail outlets (cl 5.4(4), (7)), limits on temporary use duration (cl 2.8), the prohibition of canal estate development (cl 2.9), and the obligation to consult Commonwealth aviation authorities where structures would penetrate airport surfaces (cl 6.8).
Interface with State instruments and other statutes: The Plan is expressly subject to State environmental planning policies and references numerous Acts for matters of detail or exclusion (cl 1.9, cl 1.9A, many clauses that refer to the Heritage Act, Rural Fires Act, Crown Land Management Act, Biodiversity Conservation Act and Fisheries Management Act).
Administrative instruments: The Plan creates administrative obligations on the consent authority, such as record-keeping when exercising discretion under cl 4.6, consultation obligations where heritage or Commonwealth aviation interests are engaged (cl 5.10(7)-(9), cl 6.8(2)), and required consideration of particular industry codes and strategies (cl 5.19(5)).
In short, the Plan is a mapped, zone-based regulatory instrument that operates primarily by setting what can occur where (via maps and the Land Use Table) and by conditioning consent on the satisfaction of local environmental, heritage, infrastructure and amenity criteria.
Who it affects
Owners and occupiers of land in Cobar
All landowners within the area identified on the Land Application Map (cl 1.3) are affected because the Plan determines permissible uses, subdivision standards and environmental controls for their land. Practical consequences include limits on development types, minimum lot sizes for subdivision (cl 4.1), and required consents for demolition (cl 2.7) and subdivision (cl 2.6).
Applicants and developers
Anyone proposing development in the Plan area must engage with the consent pathways (exempt, complying or development application) set out in Part 3 and the Land Use Table. They must prepare the documents that the consent authority requires, including statements of environmental effects and, where relevant, heritage management documents or heritage conservation management plans (cl 5.10(5)-(6)). Applicants for proposals that contravene development standards must prepare the evidence required by cl 4.6 and the regulations referenced in the note to cl 4.6.
The Council (consent authority)
The Council is the designated consent authority (cl 1.6). Responsibilities imposed by the Plan include determining applications against the Land Use Table and zone objectives (cl 2.3(2)), considering the local environmental provisions (Part 5 and Part 6), keeping records of assessments under cl 4.6(4), and following notification and consultation duties (for example cl 5.10(7)-(9)). The Council also handles classification/reclassification of public land as operational or community land in accordance with the Local Government Act (cl 5.2).
State agencies and other public authorities
The Plan expressly contemplates participation by State bodies. For example, SP2 infrastructure land and classified roads are linked to Transport for NSW as the relevant authority for acquisition (cl 5.1(2)), the corporation under s 2.5 of the Act is the relevant authority for regional open space acquisitions (cl 5.1(2)), and the Minister administering the National Parks and Wildlife Act is the acquisition authority for national park land (cl 5.1(2)). Clause 6.8 requires consultation with the relevant Commonwealth body if proposed development penetrates the airport Limitation or Operations Surface. The Plan also defers to State environmental planning policies (cl 1.9) and to other Acts for specialist approvals and exclusions (see multiple references to Heritage Act, Rural Fires Act, Biodiversity and Fisheries-related laws).
Neighbours and the local community
Adjoining owners and the surrounding community are affected by the Plan’s controls that protect amenity and environmental values, including noise and music provisions (cl 5.20), bush fire hazard reduction provisions (cl 5.11), and riparian/wetland protection (cl 6.6, cl 6.7). The Plan also creates mechanisms that limit neighbours’ ability to rely on private covenants in certain circumstances (cl 1.9A), which can alter private property expectations.
Businesses and licensed premises
Businesses, especially those proposing commercial, industrial or tourism-related development (zones E1, E4, RE2 and RU5 among others), must work within the local permissible uses and caps on things like retail floor area (cl 5.4(4), (7), (7AA)). Licensed premises are specifically protected from refusal on certain aesthetic or entertainment-related grounds (cl 5.20), subject to the consent authority being satisfied that noise can be managed.
Primary producers and agricultural businesses
Rural land uses are governed by RU1 and related rural zone provisions, minimum lot-size rules that seek to prevent fragmentation (cl 4.1 and cl 4.1AA), and rules on rural workers’ dwellings (cl 4.2B) and farm stay/farm gate premises (cl 5.24 and 5.25). Intensive livestock agriculture has its own consent thresholds and permitted lower-capacity exclusions (cl 5.18).
Heritage and conservation stakeholders
Owners of heritage items listed in Schedule 5 and land within heritage conservation areas are subject to additional consent requirements and procedural steps (cl 5.10). Conservation interests are engaged by the Plan’s biodiversity, watercourse and wetland controls (cl 6.4, cl 6.6, cl 6.7) and by the conservation exclusion zones in the aquaculture schedules (Schedule 6, Part 1 and Part 2 Divisions).
Crown land holders
The Plan contains provisions affecting Crown land and Crown interests. Clause 1.9A preserves rights and interests of public authorities under registered instruments. Clause 5.12 makes clear the Plan does not restrict infrastructure development or the use of existing Crown buildings as permitted under the State environmental planning policy referenced. The classification and reclassification provisions (cl 5.2 and Schedule 4) affect public land held by the Council and may require Governor approval for reclassifying reserves to operational land (note to cl 5.2).
Who pays and who decides
The consent authority (Council) decides on development applications subject to Plan provisions and relevant Acts (cl 1.6). Applicants bear direct costs: preparing documentation, engaging consultants for environmental/heritage assessments, meeting conditions of consent, and potentially providing infrastructure or mitigation measures required as conditions. The Plan also creates potential costs for adjoining landowners where new uses are permitted nearby (for example, farm gate, aquaculture, or licensed premises with music) and it places administrative and consultation obligations on the Council and on State bodies where specific interactions (eg aviation or heritage consultation) are required.
Key duties and rights
Duties on applicants and owners
Obtain development consent where required: The Plan specifies numerous instances where development consent is required , subdivision (cl 2.6), demolition (cl 2.7), most land uses set out in the Land Use Table (cl 2.3), and many additional local controls (Part 5 and Part 6). Exempt and complying development paths are available where the development and site meet the relevant schedules and standards (cl 3.1-3.2).
Demonstrate compatibility with mapped environmental constraints: For mapped areas the consent authority must be satisfied that development will avoid, minimise or mitigate significant adverse environmental impacts. Examples include terrestrial biodiversity (cl 6.4(3)-(4)), groundwater vulnerability (cl 6.5(3)-(4)), riparian land and watercourses (cl 6.6(3)-(4)), wetlands (cl 6.7(3)-(4)) and flood planning (cl 5.21(2)-(3)). Applicants must therefore supply sufficient environmental information to enable the consent authority to make those satisfactions.
Address minimum lot sizes and subdivision conditions: Subdivision must comply with the minimum lot sizes shown on the Lot Size Map unless a specific clause applies (cl 4.1). Special rules apply for subdivisions under community title and strata schemes (cl 4.1AA, cl 4.1A). Development consent must not be granted in some circumstances where subdivision would separate a principal and secondary dwelling in contravention of minimum lot sizes (cl 2.6(2)).
Meet local quantitative limits and operational requirements: Applicants must observe local floor-area limits, guest-room caps and similar numeric limits (cl 5.4(1), (4), (5), (7), (7AA)). For pond/tank-based aquaculture, specific site location and operational requirements are mandatory (Schedule 6, Part 1 and Part 2).
Provide for heritage protections if applicable: Where land contains a heritage item or lies in a heritage conservation area, demolition, alteration of exterior/interior fabric, disturbance of archaeological sites and the like require consent, and the consent authority may require heritage management documents or conservation management plans (cl 5.10(2), (4)-(6)).
Consult and notify certain stakeholders: For heritage sites and archaeological land the Plan requires the consent authority to notify the Heritage Council and consider any response (cl 5.10(7), (9)). For Aboriginal places of heritage significance the consent authority must notify local Aboriginal communities and consider responses (cl 5.10(8)). For development that is likely to penetrate airport operational surfaces, the consent authority must consult the relevant Commonwealth body and must not grant consent if the Commonwealth body objects (cl 6.8(2)-(4)).
Duties on the consent authority (Council)
Have regard to zone objectives: The consent authority must consider zone objectives when deciding development applications (cl 2.3(2)).
Fulfil statutory consideration and consultation duties: The Council must follow the consultation and notification steps in cl 5.10 for heritage/archaeology, and consult Commonwealth aviation authorities under cl 6.8 where applicable.
Record-keeping when exercising discretion: Where the consent authority relies on cl 4.6 to allow a contravention of a development standard, it must keep a record of the assessment (cl 4.6(4)).
Satisfy environmental tests before granting consent: For many mapped environmental constraints the consent authority must be satisfied that potential adverse environmental impacts will be avoided, minimised or mitigated (eg cl 6.4(4), 6.5(4), 6.6(4), 6.7(4)).
Manage public land classification and acquisition processes: The Council may classify or reclassify public land as operational or community land under cl 5.2 and must follow Governor approval steps where required for discharging trusts (note to cl 5.2). The Plan also identifies the relevant acquisition authority under cl 5.1 for land on the Land Reservation Acquisition Map.
Rights and entitlements
Right to rely on exempt and complying development pathways: Where development is specified as exempt (Schedule 2) or complying (Schedule 3, and the SEPP it cross-references) and satisfies the conditions and standards, the proponent has a statutory pathway to carry out development without going through the full development application process (cl 3.1-3.2).
Right to seek consent for non-prohibited uses: If a use is in the Land Use Table as “permitted with consent,” an applicant can lodge a development application for that use and seek consent, subject to satisfying the consent authority on the relevant matters (cl 2.3).
Right to seek variation of development standards under cl 4.6: An applicant may seek consent even if a development would contravene a development standard, by making the demonstration required by cl 4.6(3). The consent authority must keep a record of its assessment (cl 4.6(4)). Note the clause excludes certain standards from variation (cl 4.6(8)).
Right to the applicable maps and public information: Maps and adopted data are required to be kept and made available for public access (cl 1.7); proponents and affected parties can rely on those published maps when planning and lodging applications.
Limits, exclusions and interactions that constrain duties/rights
Suspension of covenants limited: Clause 1.9A suspends private covenants to the extent necessary to enable development in accordance with the Plan, but it excludes covenants imposed or required by the Council and several classes of conservation agreements and instruments (cl 1.9A(2)). It also preserves public authority rights under registered instruments (cl 1.9A(3)).
Environmentally sensitive areas restrict exempt/compliant pathways: Exempt or complying development cannot be carried out on environmentally sensitive areas defined in cl 3.3, even if otherwise listed as exempt or complying.
Some standards cannot be varied: Clause 4.6 excludes certain standards from its flexibility (cl 4.6(8)) including development standards for complying development and BASIX commitments where applicable.
Pre-existing development applications preserved: The savings provision (cl 1.8A) preserves the rule that development applications lodged before this Plan commenced must be determined as if the Plan had not commenced, which affects the rights and duties of applicants whose applications straddle the change‑over date.
In every instance the Plan ties duties and rights to the Act and other statutes it references, so exercising these rights or fulfilling these duties will routinely require conforming to statutory procedures and to the Plan’s mapped and schedule-based criteria.
Penalties and enforcement
The Plan, as presented, does not itself set fines or specific enforcement penalties. Instead the instrument establishes permissions, prohibitions and consent thresholds and repeatedly invokes the Environmental Planning and Assessment Act and other legislation for the legal framework in which enforcement, penalties and compliance mechanisms operate. The Plan therefore functions primarily as a rule‑setting instrument and leaves enforcement detail to the Act and associated regulations and enforcement machinery.
What the Plan does prescribe that affects enforcement and compliance:
Consent‑threshold framing: By classifying a wide range of works and land uses as permitted only with development consent, the Plan creates a compliance trigger , carrying out development without required consent will fall into whatever compliance and enforcement regime applies under the Act and related laws (for example, those referred to throughout the Plan).
Mapped constraints and mandatory satisfactions: The Plan imposes mandatory satisfaction tests for many mapped environmental categories (eg biodiversity, groundwater, riparian areas, wetlands, flood planning). These tests create objective decision points for the consent authority and can be invoked in compliance and enforcement actions where work proceeds without adequate assessment or in breach of consent conditions (see cl 6.4(4), 6.5(4), 6.6(4), 6.7(4), 5.21(2)).
Record-keeping and assessment obligations that assist enforcement: Clause 4.6 requires the consent authority to keep a record of its assessment when granting consent for a contravention of a development standard. That record will be relevant in any subsequent scrutiny of the consent decision or enforcement action.
Specific prohibitions and “must not grant” rules: Some clauses contain absolute or near‑absolute prohibitions on granting consent in particular circumstances (for example cl 4.2A(3) prohibits consent for an erection of a dwelling in certain circumstances; cl 6.8(4) requires the consent authority to not grant consent where the relevant Commonwealth body advises the development should not be constructed).
Heritage and Aboriginal consultation steps that create administrative dependencies: Clause 5.10 imposes notification duties to the Heritage Council and local Aboriginal communities and requires the consent authority to take any responses into account. Failure to follow these processes could expose the consent authority’s decision to legal challenge and complicate enforcement.
Suspension of covenants: Clause 1.9A temporarily suspends private covenants to allow development under the Plan, subject to defined exclusions. That mechanism changes the practical enforcement landscape for private covenants: the Plan itself overrides those covenants to the extent necessary for Plan-consistent development, while preserving council-imposed covenants and specified conservation agreements.
What the Plan does not do (and thus creates compliance uncertainty that must be resolved under other laws):
No express penalty levels, enforcement powers or procedural sanctions are set out in the Plan itself. There are multiple references to “the Act” and to other legislation for matters such as acquisition, classification and the operation of certain State policies; therefore precise enforcement mechanisms, penalty amounts, notice and appeal rights are those provided in the Act and the other statutes, not in the Plan text. The Plan is thus a source of obligations and prohibitions but not the repository of the enforcement sanctions that implement them.
No local criminal or civil fines are described in the Plan; remedies for non‑compliance (injunctions, contempt, orders to restore land, penalty notices, fines, orders to cease and desist, remediation costs) are matters for the Act and other relevant instruments.
Implementation and enforcement practicalities and risks
Administrative capacity and discretionary exercises: The Plan imposes numerous duties on the consent authority to assess environmental matters, seek specialist reports, consult external bodies and keep records (cl 5.10, cl 6.8, cl 4.6). Effective enforcement will therefore depend on the Council’s capacity, resourcing and administrative systems to undertake those tasks and to monitor compliance with consent conditions.
Evidence and proof: The Plan frequently requires the consent authority to be “satisfied” of particular facts before granting consent (eg cl 5.19(2)(a), cl 6.4(4), cl 6.6(4), cl 5.21(2)). Enforcement action where development has occurred without satisfying those tests will depend on documentary and expert evidence about environmental impact, heritage significance or flood risk.
Overlap with State and Commonwealth regimes: Because the Plan defers to State environmental planning policies and other Acts (cl 1.9 and multiple cross‑references), enforcement actions may require coordination across multiple agencies and legal instruments. The Plan’s requirement to consult Commonwealth aviation authorities (cl 6.8) provides a clear example where a local consent decision may be constrained or overturned by a Commonwealth assessment.
Legal challenge risk: Decisions to grant consent that rely on cl 4.6 (exceptions to development standards) must be recorded and justified. Failure to properly record or apply the cl 4.6 tests could increase the risk of merits or judicial review proceedings, although the Plan itself does not discuss appeal rights; those would be matters under the Act.
In short, the Plan sets the permissions and prohibitions and public‑administrative obligations; the actual enforcement architecture, sanctions and procedures lie in the Act and other statutes the Plan repeatedly references. Practitioners should therefore always place Plan requirements alongside the enforcement and penalties set out in the Act and relevant regulations when advising clients or preparing applications.
How it interacts with other laws
The Plan is embedded within a web of State and Commonwealth legislative instruments. The Plan itself repeatedly references and defers to other laws, and its application is defined against those instruments. The interactions are both hierarchical and functional:
Priority of State environmental planning policies and the Act
Clause 1.9 explicitly provides that the Plan is subject to any State environmental planning policy (SEPP) that prevails under s 3.28 of the Act. The Plan therefore operates underneath the State policy layer: where a SEPP expressly prevails or has mandatory content, that SEPP will override inconsistent Plan provisions. The Plan also depends on the Act for the creation and enforcement of development consent processes (see multiple references to the Act, including cl 1.2, the aim to make provisions in accordance with standard instruments under s 3.20 of the Act).
Cross‑references to specific statutes that create limits or trigger other approvals
Heritage: The Plan cross-references the Heritage Act 1977 for State Heritage Register items and interim heritage orders (cl 3.1(3)(d), cl 5.10). The heritage consent pathway and notification obligations sit alongside and interact with the Heritage Act’s own approvals and enforcement mechanisms.
Crown and Crown instrument interactions: Clause 1.9A expressly excludes certain relevant instruments from the suspension of covenants, including instruments under the Crown Land Management Act 2016 and conservation agreements under National Parks and Wildlife Act 1974, indicating that Crown-held interests and statutory conservation agreements operate independently of the Plan’s suspension mechanism.
Local Government Act 1993: Clause 5.2 relies on the Local Government Act for classification and reclassification of public land and for the consequences of reclassification (cl 5.2 and its note referring to s 30 of the Local Government Act). Governor approval steps for discharging trusts are also invoked and required under that Act.
Land Acquisition (Just Terms Compensation) Act 1991: Clause 5.1 refers to the owner‑initiated acquisition provisions of that Act and designates relevant State authorities for acquisitions identified on the Land Reservation Acquisition Map.
Rural Fires Act 1997: Clause 5.11 makes bush fire hazard reduction work authorised by the Rural Fires Act permissible without development consent, linking the Plan to that regime.
Biodiversity, Fisheries and Marine statutes: Clauses and schedules reference the Biodiversity Conservation Act 2016, Fisheries Management Act 1994 and Marine Estate Management Act 2014 in respect of wetlands, aquatic reserves, priority oyster aquaculture and conservation exclusion zones (eg Schedule 6 and cl 5.19). Those Acts supply licence regimes, species protections and additional approvals that operate alongside the Plan’s controls.
Building, plumbing and BASIX: Part 3 requires exempt or complying development to meet provisions of the Building Code of Australia and not to cause non-compliance with the Building Code. Clause 4.6 excludes BASIX commitments from its variation power (cl 4.6(8)(b)), meaning BASIX obligations remain mandatory and cannot be the subject of a development standard variation under cl 4.6.
Functional interactions and thresholds
Mapping and thresholds in the Plan operate as spatial triggers for other statutory regimes. For example, land identified on the Terrestrial Biodiversity Map triggers the application of cl 6.4; land within a Riparian area on the Watercourse Map triggers cl 6.6; land in an ANEF contour triggers cl 6.9 (aircraft noise) which then requires compliance with AS 2021,2000 and consultation with the Commonwealth airport‑responsible department.
Exempt and complying development: The Plan defers to State SEPPs and the Environmental Planning and Assessment Regulation for the circumstances in which exempt and complying development applies. Schedule 3 explicitly references the State SEPP (Exempt and Complying Development Codes) 2008 and cross‑links conditions to that SEPP.
Limitations and carve-outs
The Plan carves out or excludes the operation of certain private instruments: cl 1.9A suspends covenants to the extent necessary for Plan-consistent development, but enumerates categories of instruments that are not suspended (for example Council‑imposed covenants and certain conservation instruments).
Some Plan clauses are explicitly not adopted in the Cobar Plan. The document contains a number of headings with “[Not adopted]” or “[Not applicable]” (for example height of buildings cl 4.3, floor space ratio cl 4.4, development below mean high water mark cl 5.7). Practitioners must therefore not assume the Plan imposes controls in those domains; instead, they must look to other instruments or the Act where necessary.
Consultation and referral pathways
When development would penetrate airport surfaces, the Plan requires the consent authority to consult the relevant Commonwealth body and to refuse consent if that body advises against the development (cl 6.8(2)-(4)). For heritage and archaeological sites, the Plan requires notification to and consideration of responses from the Heritage Council and local Aboriginal communities (cl 5.10(7)-(9)). For oyster aquaculture the consent authority must consider aquaculture industry development plans and the NSW Oyster Industry Sustainable Aquaculture Strategy where applicable (cl 5.19(5)).
Practical consequence for practitioners
Any application under the Plan must be prepared with an eye to the overlapping statutory regimes. The Plan’s maps and local rules determine whether a proposal is permitted and set mandatory assessment criteria, but many proposals will also require or be constrained by separate State licences, statutory approvals, or Commonwealth considerations. The Plan therefore functions as a local layer that must be read and applied in conjunction with State and Commonwealth frameworks referenced throughout the text.
Amendment history
The Plan includes inline amendment notations. The source text records a series of amendments over time; these appear as marginal notes or parenthetical annotations. The Plan’s amendment record in the text shows the following notable changes and years (each entry cites the clause where the amendment is recorded):
2016 (168), Sch 1[2]: Amendments recorded in the Land Use Table notes (Land Use tbl amendment reference).
2017 (493), Sch 1.1[1] and 2017 (584), cl 4: Further Land Use Table amendments (see Land Use tbl note).
2018 (406), Sch 1.34 [1] [2]: Clause 5.4 (Controls relating to miscellaneous permissible uses) was amended (cl 5.4: Am 2018 (406), Sch 1.34[1][2]).
2019 (97), cl 4(1): Schedule 1 (Additional permitted uses) amended to add the Knight Drive clause (Schedule 1, sch 1: Am 2019 (97), cl 4(1)).
2019 (137), Sch 6 [1]: Land Use Table further amended in 2019 (see Land Use tbl note).
2019 (621), Sch 5[1] and Sch 5[2]-[4]: Clause 1.8A (Savings provision relating to development applications) was added or amended in 2019 (cl 1.8A: Am 2019 (621), Sch 5[1]). Clause 1.9A (Suspension of covenants, agreements and instruments) is recorded as amended in 2019 (cl 1.9A: Am 2019 (621), Sch 5[2]-[4]).
2021 (225), Sch 1: Clause 6.2 was repealed in 2021 (cl 6.2: Rep 2021 (225), Sch 1).
2022 (314), Sch 1 and 2022 (831), Sch 1.4: The zoning list and certain clauses were amended in 2022. Specifically:
Clause 2.1 (Land use zones) is noted as amended in 2022 (cl 2.1: Am 2022 (831), Sch 1.4[1]).
The Land Use Table carries amendment notations for 2022 (Land Use tbl: Am 2022 (314), Sch 1; 2022 (831), Sch 1.4[2]).
Clause 4.1A (Minimum subdivision lot size for strata plan schemes in Zone RU1) was added/amended in 2022 (cl 4.1A: Am 2022 (831), Sch 1.4[3]).
Clause 4.2A (Erection of dwelling houses on land in certain rural and conservation zones) was amended in 2022 (cl 4.2A: Am 2022 (831), Sch 1.4[4][5]).
Clause 4.6 (Exceptions to development standards) was amended in 2022 (cl 4.6: Am 2022 (831), Sch 1.4[6]).
Clause 6.3 (Stormwater management) was amended in 2022 (cl 6.3: Am 2022 (831), Sch 1.4[7]).
2023 (458), Sch 1[4] and Sch 2.21[1][2]: Clauses 5.24 (Farm stay accommodation) and 5.25 (Farm gate premises) were substituted in 2023 (cl 5.24: Subst 2023 (458), Sch 1[4]; cl 5.25: Subst 2023 (458), Sch 1[4]). Land Use Table amendment references include 2023 entries (Land Use tbl: 2023 (458), Sch 2.21[1] [2]).
The Plan’s internal amendment notes appear at multiple clause headings and in the Land Use Table footer, indicating a history of staged updates to zoning categories, particular local clauses (for example farm stay/farm gate provisions and minimum lot size rules), and deletion or substitution of clauses. The presence of “Not adopted” headings for certain standard categories (for example height of buildings cl 4.3 and floor space ratio cl 4.4) indicates the Plan has intentionally left some conventional controls unadopted, consistent with local drafting choices that have not been subject to later amendment.
Users should treat the above list as the amendment references recorded within the Plan text itself. The Plan does not include a consolidated external amending instrument list in the text provided here, so practitioners should consult the NSW legislation website and the Plan’s published consolidated version for the full formal amendment history and to confirm commencement dates of individual amendments where precise timing matters for transitional or savings provisions.
Litigation history
The Plan text supplied does not contain any case names, judicial decisions, or a litigation history. The instrument references statutory processes, consultation and record-keeping duties (for example cl 4.6(4) and cl 5.10 notification steps) that are relevant to administrative review or judicial review under the Environmental Planning and Assessment Act and related legislation, but the Plan itself does not report or summarise any litigation.
Because the Plan repeatedly cross‑refers to the Act and to State environmental planning policies, decisions about the Plan’s application in particular cases could be the subject of merits review or judicial review under the Act or other statutes. Those dispute pathways, remedies and reported cases would be found in court and tribunal records, not in the Plan text. Practitioners looking for litigation precedent that interprets the Plan’s provisions must therefore search administrative and judicial decisions external to the Plan document and consider the Act’s appeal and review mechanisms.
In short, the supplied text contains no litigation history or named cases. Any legal advice or argument that seeks to rely on case law must identify decisions outside this Plan text.
Gotchas
This Plan contains numerous drafting and operational features that can produce unexpected outcomes if practitioners or landowners assume conventional rules apply without checking the Plan’s text and maps carefully. The main practical “gotchas” are:
Maps determine outcomes; check the maps first: Many key standards are implemented by reference to maps (Lot Size Map, Land Zoning Map, Heritage Map, Terrestrial Biodiversity Map, Groundwater Vulnerability Map, Watercourse Map, Wetlands Map, Land Reservation Acquisition Map, Obstacle Limitation Surface Map, Noise Exposure Forecast Contour Map). For example, minimum lot sizes in cl 4.1 are the sizes shown on the Lot Size Map. Failure to inspect the maps will lead to incorrect assumptions about permissibility and standards; cl 1.7 makes maps part of the Plan and requires public availability.
Savings for pre‑commencement development applications: If a development application was lodged before this Plan commenced and was not finally determined, the application must be determined as if this Plan had not commenced (cl 1.8A). This can preserve an applicant’s entitlement under a prior instrument and is a common trap for those who assume the new Plan immediately governs every pending application.
Suspension of private covenants is not absolute: Clause 1.9A suspends private covenants and similar instruments to the extent necessary to enable Plan-consistent development, but several instruments are excluded (Council-imposed covenants, Crown instruments, conservation agreements, property vegetation plans, biobanking agreements and planning agreements). If a proponent plans development relying on covenant suspension, they must check whether the covenant falls into an excluded category (cl 1.9A(2)) and must consider public authority rights under registered instruments (cl 1.9A(3)).
Environmental exclusions for exempt/compliant development: Exempt and complying development are not available in “environmentally sensitive areas for exempt or complying development” (cl 3.3(1)). These areas include coastal waters, Ramsar wetlands, land of high Aboriginal cultural or biodiversity significance identified in any instrument and other listed categories. A development that would otherwise be exempt or complying could require full development consent if it is in a mapped environmentally sensitive area.
Many standard clauses are “Not adopted”: Several traditional LEP controls are shown as “[Not adopted]” or “[Not applicable]” in the Plan (for example cl 4.3 height of buildings; cl 4.4 floor space ratio; cl 4.5 calculation of FSR and site area; cl 5.7 development below mean high water mark). Practitioners must not assume the presence of numerical limits for height or FSR unless those limits are included on maps or in local clauses.
Clause 4.6 variation process and its limits: Clause 4.6 allows the consent authority to grant consent to development that contravenes a development standard if the applicant demonstrates that compliance is unreasonable or unnecessary and there are sufficient environmental planning grounds. However, cl 4.6 excludes some standards from variation (such as complying development standards and BASIX commitments). Also, cl 4.6(6) prevents consent being granted under cl 4.6 for subdivisions in certain zones if the subdivision will result in two or more lots below the minimum area or a lot below 90% of the minimum. The consent authority must keep a record of its assessment under cl 4.6(4), which practitioners should ensure is properly documented.
Canal estate prohibition: Clause 2.9 prohibits canal estate development. The definition is broader than simply building canals; it captures combinations of canals, dwellings and specific earthworks (fill or excavation). A developer contemplating waterfront or artificially-created waterways must check cl 2.9 carefully.
Music and entertainment protections for licensed premises: Clause 5.20 substantially narrows grounds on which consent can be refused for licensed premises where the proposal involves music, dancing or stage orientation, if the consent authority is satisfied the noise may be managed and minimised. Practitioners for objecting neighbours should be aware this clause limits refusal grounds; conversely, proponents for licensed premises have a strengthened right to apply subject to noise being manageable.
Variable quantitative limits across uses: The Plan contains several small numeric limits that can be decisive in an application , for example, bed and breakfast rooms capped at five (cl 5.4(1)); home business and home industry floor area caps at 100 m2 (cl 5.4(2)-(3)); neighborhood shop retail floor area capped at 100 m2 (cl 5.4(7)); neighbourhood supermarket cap at 1,000 m2 (cl 5.4(7AA)); industrial retail outlet retail limits (cl 5.4(4)). These caps can change the classification of the use and whether consent is required.
Multiple concurrent statutory approvals may be required: Several Plan provisions point to separate licensing processes under other Acts (for example fisheries/aquaculture licences, Crown land licences, heritage approvals). The Plan’s permissions do not remove the need for separate approvals where another Act requires them (see notes in Schedule 6 and cl 3.1(5)). Applicants often mistake Plan consent for comprehensive statutory clearance; the Plan’s notes caution that other statutory approvals may still be necessary.
Airport and aircraft noise controls: The Plan requires consultation with the Commonwealth body where structures would penetrate airport Limitation or Operations Surfaces (cl 6.8), and it requires development in ANEF contours to meet Australian Standard AS 2021,2000 indoor design sound levels (cl 6.9(3)). Proposals near the airport have both consultative and technical obligations.
Public land classification consequences: Reclassification of public land as operational or community land is provided (cl 5.2 and Schedule 4). The reclassification of land that is a public reserve can discharge trusts and alter the land’s legal status; Governor approval is required in some cases as noted. Failure to consider trust or reservation consequences can frustrate intended uses.
Intensive livestock exemptions are capacity-limited and location-sensitive: Clause 5.18(4) permits certain small-capacity intensive livestock developments to proceed without consent but only where they comply with detailed locational constraints (eg not within specified distances of dwellings, not in environmentally sensitive areas). Practitioners must check both the capacity thresholds (cl 5.18(5)) and the location constraints (cl 5.18(4)(b)).
These are concrete operational traps that arise from the Plan’s structure and from the particulars of the local rules. Practitioners should begin every Cobar planning enquiry by identifying the zoning, the mapped overlays, any relevant schedule entries, the lot-size mapping and any cross‑references to State or Commonwealth instruments.
How to comply
A pragmatic compliance checklist and procedural steps for applicants, landowners and advisers dealing with development in the Cobar Plan area, grounded in the Plan text.
Confirm the land and maps that apply
Identify the land precisely and consult the Land Application Map and Land Zoning Map (cl 1.3; cl 2.2). Check overlay maps referenced in the Plan (Lot Size Map; Heritage Map; Terrestrial Biodiversity Map; Groundwater Vulnerability Map; Watercourse Map; Wetlands Map; Land Reservation Acquisition Map; Obstacle Limitation Surface Map; Noise Exposure Forecast Contour Map). Map location determines which clauses apply and which environmental constraints trigger additional requirements.
Determine permissible pathways for the proposed development
Check the Land Use Table for the zone: is the proposed use permitted without consent, permitted with consent, or prohibited (cl 2.3 and Land Use Table)? If permitted with consent, the project will require a development application under the Act. If permitted without consent, confirm whether it is nonetheless subject to Part 5 (environmental assessment) requirements per the Land Use Table note.
Check Schedule 2 for local exempt development (cl 3.1 and Schedule 2) and consult the State SEPP (Exempt and Complying Development Codes) 2008 for any State-wide exempt categories. For complying development, check Schedule 3 and the State SEPP for complying development types and conditions (cl 3.2 and Schedule 3).
If the land is in an environmentally sensitive area for exempt/compliant development (cl 3.3), the exempt/compliant pathways may be unavailable and a full development application may be necessary.
Check lot sizes and subdivision rules
For subdivisions, consult the Lot Size Map and cl 4.1. If subdividing under community title or strata plans, check cl 4.1AA and cl 4.1A for minimum lot size rules specific to those arrangements. Note cl 2.6(2) prohibits subdivision that would separate principal and secondary dwellings if resulting lots would be below the minimum on the Lot Size Map.
Identify mandatory local controls triggered by the proposal
If the site is mapped for terrestrial biodiversity (cl 6.4), groundwater vulnerability (cl 6.5), riparian land and watercourses (cl 6.6), wetlands (cl 6.7), or within the flood planning area (cl 5.21), prepare the necessary technical reports and demonstrate how the development will avoid, minimise, or mitigate adverse environmental impacts. The consent authority must be satisfied of this before granting consent (see cl 6.4(4), 6.5(4), 6.6(4), 6.7(4), 5.21(2)).
If the site contains or adjoins a heritage item or lies in a heritage conservation area, prepare heritage impact statements and expect the consent authority to require heritage management documents or heritage conservation management plans (cl 5.10(4)-(6)). If the application affects an archaeological site or a nominated State heritage item, follow the notification steps to the Heritage Council (cl 5.10(7), (9)).
For licensed premises proposing music or dancing, be prepared to demonstrate that noise can be managed to an acceptable level (cl 5.20). The consent authority may not refuse consent on listed aesthetic grounds if satisfied noise is manageable (cl 5.20(1)-(2)).
Check special use‑specific rules
For eco-tourist facilities, the consent authority must be satisfied of connection to ecological/cultural values and the existence of a management strategy addressing listed matters (cl 5.13).
For intensive livestock agriculture, check capacity thresholds and locational constraints to determine whether consent is required (cl 5.18(4)-(5)) and prepare environmental impact information on odour, pollution, soil degradation and industry codes (cl 5.18(3)).
For aquaculture, follow the site location and operational requirements in Schedule 6 and consult any aquaculture industry development plans and the NSW Oyster Industry Sustainable Aquaculture Strategy for oyster aquaculture (cl 5.19; Schedule 6).
Consider planning variations early if needed
If the proposal would contravene a development standard, prepare the cl 4.6 submission demonstrating that compliance is unreasonable or unnecessary and that environmental planning grounds justify the contravention. Remember cl 4.6 excludes certain standards (cl 4.6(8)). The consent authority must keep a record of its assessment under cl 4.6(4), so structure the evidence to support a transparent record.
Check for other statutory approvals and licences
Identify other Acts that may require separate approvals regardless of Plan consent , for example, Heritage Act approvals, Fisheries/aquaculture licences, Crown land licences, water extraction licences, sewage/disposal or building approvals. The Plan’s notes repeatedly emphasise_that Plan consent is not a substitute for licences under other Acts (see Schedule 6 notes; cl 3.1(5) note).
Fulfil consultation and notification obligations
Where the Plan requires notification to external bodies (Heritage Council, local Aboriginal communities, Commonwealth aviation body), factor time for those notifications and any potential responses into the project timetable (cl 5.10(7)-(9); cl 6.8(2)). For airport-related matters, the consent authority must consult the Commonwealth body and may not grant consent if the Commonwealth body advises the development should not be constructed (cl 6.8(3)-(4)).
Anticipate conditions and infrastructure/service tests
The Plan requires satisfaction that essential services will be available (cl 6.10). Be prepared to address water supply, electricity, sewage disposal, stormwater and road access. If the Council is not satisfied, consent may be refused or conditioned accordingly.
Prepare documentation with cross-references
Prepare statements of environmental effects or environmental impact statements that directly address the Plan’s clauses relevant to the site (for example, address cl 6.4 biodiversity tests, cl 6.5 groundwater vulnerability, cl 6.6 riparian tests, cl 5.21 flood planning and cl 5.18 if livestock issues apply). Where cl 4.6 is invoked prepare clear planning grounds and demonstrate alternatives that were considered.
Record-keeping and audit trail
When seeking a departure under cl 4.6, ensure the consent authority’s decision is supported by a written record, including the applicant’s written grounds, the assessment against each part of cl 4.6(3), and any conditions imposed. The Plan requires the consent authority to keep such a record (cl 4.6(4)).
Engage early with the Council and relevant agencies
Early liaison with the Council (the consent authority per cl 1.6), Commonwealth aviation authorities (cl 6.8), the Heritage Council (if heritage is engaged, cl 5.10), and State agencies (where SEPPs or other Acts apply) will reduce the risk of unexpected refusals or lengthy referral processes.
Check transitional and pre-commencement application rules
If the proposal or application spans Plan commencement, check cl 1.8A for the savings rule which preserves the right to have a pre-commencement application determined under the previous instrument. Verify which version of the Plan or previous LEP applies to avoid misapplication of standards.
Consider timing for temporary uses and events
Temporary use consents are limited to 52 days in any 12-month period unless for specified sales offices (cl 2.8). Apply for temporary use consent with clear restoration plans required under cl 2.8(3)(d).
Documentation for public land and acquisition matters
If land is within areas identified on the Land Reservation Acquisition Map, check cl 5.1 for the relevant acquisition authority and consequences. If public land classification or reclassification is proposed, follow the steps and Governor approvals noted in cl 5.2.
This compliance pathway maps Plan provisions to the practical steps applicants and advisers must follow. For complex or borderline cases, prepare technical reports that directly map to the Plan clauses (for example, a biodiversity assessment that addresses each cl 6.4 question), and expect the consent authority to require heritage management documents or heritage conservation plans where cl 5.10 applies.
Practitioners should also verify amendments and consult the consolidated Plan on the NSW legislation website to confirm current map versions and recent amendments recorded in the Plan’s annotation history.
The consent authority for the purposes of this Plan is (subject to the Act) the Council.
1 Maps
1 Maps
1.7 Maps
(1) A reference in this Plan to a named map adopted by this Plan is a reference to a map by that name—
(a) approved by the local plan-making authority when the map is adopted, and
(b) as amended or replaced from time to time by maps declared by environmental planning instruments to amend or replace that map, and approved by the local plan-making authority when the instruments are made.
(1AA) (Repealed)
(2) Any 2 or more named maps may be combined into a single map. In that case, a reference in this Plan to any such named map is a reference to the relevant part or aspect of the single map.
(3) Any such maps are to be kept and made available for public access in accordance with arrangements approved by the Minister.
(4) For the purposes of this Plan, a map may be in, and may be kept and made available in, electronic or paper form, or both.
Note.
The maps adopted by this Plan are to be made available on the NSW Planning Portal. Requirements relating to the maps are set out in the documents entitled Standard technical requirements for LEP maps and Standard requirements for LEP GIS data which are available on the website of the Department of Planning and Environment.
1 Repeal of planning instruments applying to land
1 Repeal of planning instruments applying to land
1.8 Repeal of planning instruments applying to land
(1) All local environmental plans and deemed environmental planning instruments applying only to the land to which this Plan applies are repealed.
Note.
The following local environmental plans are repealed under this provision—
Cobar Local Environmental Plan 2001
(2) All local environmental plans and deemed environmental planning instruments applying to the land to which this Plan applies and to other land cease to apply to the land to which this Plan applies.
1 Savings provision relating to development applications
1 Savings provision relating to development applications
1.8A Savings provision relating to development applications
If a development application has been made before the commencement of this Plan in relation to land to which this Plan applies and the application has not been finally determined before that commencement, the application must be determined as if this Plan had not commenced.
Note.
However, under Division 3.5 of the Act, a development application may be made for consent to carry out development that may only be carried out if the environmental planning instrument applying to the relevant development is appropriately amended or if a new instrument, including an appropriate principal environmental planning instrument, is made, and the consent authority may consider the application. The Division requires public notice of the development application and the draft environmental planning instrument allowing the development at the same time, or as closely together as is practicable.
cl 1.8A: Am 2019 (621), Sch 5[1].
1 Application of SEPPs
1 Application of SEPPs
1.9 Application of SEPPs
(1) This Plan is subject to the provisions of any State environmental planning policy that prevails over this Plan as provided by section 3.28 of the Act.
(2) The following State environmental planning policies (or provisions) do not apply to the land to which this Plan applies—
1 Suspension of covenants, agreements and instruments
1 Suspension of covenants, agreements and instruments
1.9A Suspension of covenants, agreements and instruments
(1) For the purpose of enabling development on land in any zone to be carried out in accordance with this Plan or with a consent granted under the Act, any agreement, covenant or other similar instrument that restricts the carrying out of that development does not apply to the extent necessary to serve that purpose.
(2) This clause does not apply—
(a) to a covenant imposed by the Council or that the Council requires to be imposed, or
(b) to any relevant instrument within the meaning of section 13.4 of the Crown Land Management Act 2016, or
(c) to any conservation agreement within the meaning of the National Parks and Wildlife Act 1974, or
(d) to any Trust agreement within the meaning of the Nature Conservation Trust Act 2001, or
(e) to any property vegetation plan within the meaning of the Native Vegetation Act 2003, or
(f) to any biobanking agreement within the meaning of Part 7A of the Threatened Species Conservation Act 1995, or
(g) to any planning agreement within the meaning of Subdivision 2 of Division 7.1 of the Act.
(3) This clause does not affect the rights or interests of any public authority under any registered instrument.
(4) Under section 3.16 of the Act, the Governor, before the making of this clause, approved of subclauses (1)–(3).
cl 1.9A: Am 2019 (621), Sch 5[2]–[4].
Part 2 Permitted or prohibited development
Part 2 Permitted or prohibited development
Part 2 Permitted or prohibited development
2 Land use zones
2 Land use zones
2.1 Land use zones
The land use zones under this Plan are as follows—
Rural Zones
RU1 Primary Production
RU3 Forestry
RU5 Village
Residential Zones
R1 General Residential
R2 Low Density Residential
R5 Large Lot Residential
Employment Zones
E1 Local Centre
E4 General Industrial
Special Purpose Zones
SP2 Infrastructure
Recreation Zones
RE1 Public Recreation
RE2 Private Recreation
Conservation Zones
C1 National Parks and Nature Reserves
C3 Environmental Management
cl 2.1: Am 2022 (831), Sch 1.4[1].
2 Zoning of land to which Plan applies
2 Zoning of land to which Plan applies
2.2 Zoning of land to which Plan applies
For the purposes of this Plan, land is within the zones shown on the Land Zoning Map.
2 Zone objectives and Land Use Table
2 Zone objectives and Land Use Table
2.3 Zone objectives and Land Use Table
(1) The Land Use Table at the end of this Part specifies for each zone—
(a) the objectives for development, and
(b) development that may be carried out without development consent, and
(c) development that may be carried out only with development consent, and
(d) development that is prohibited.
(2) The consent authority must have regard to the objectives for development in a zone when determining a development application in respect of land within the zone.
(3) In the Land Use Table at the end of this Part—
(a) a reference to a type of building or other thing is a reference to development for the purposes of that type of building or other thing, and
(b) a reference to a type of building or other thing does not include (despite any definition in this Plan) a reference to a type of building or other thing referred to separately in the Land Use Table in relation to the same zone.
(4) This clause is subject to the other provisions of this Plan.
Notes.
2
1
Schedule 1 sets out additional permitted uses for particular land.
2
2
Schedule 2 sets out exempt development (which is generally exempt from both Parts 4 and 5 of the Act). Development in the land use table that may be carried out without consent is nevertheless subject to the environmental assessment and approval requirements of Part 5 of the Act.
2
3
Schedule 3 sets out complying development (for which a complying development certificate may be issued as an alternative to obtaining development consent).
2
4
Clause 2.6 requires consent for subdivision of land.
2
5
Part 5 contains other provisions which require consent for particular development.
2 Unzoned land
2 Unzoned land
2.4 Unzoned land
(1) Development may be carried out on unzoned land only with development consent.
(2) In deciding whether to grant development consent, the consent authority—
(a) must consider whether the development will impact on adjoining zoned land and, if so, consider the objectives for development in the zones of the adjoining land, and
(b) must be satisfied that the development is appropriate and is compatible with permissible land uses in any such adjoining land.
2 Additional permitted uses for particular land
2 Additional permitted uses for particular land
2.5 Additional permitted uses for particular land
(1) Development on particular land that is described or referred to in Schedule 1 may be carried out—
(a) with development consent, or
(b) if the Schedule so provides—without development consent,
in accordance with the conditions (if any) specified in that Schedule in relation to that development.
(2) This clause has effect despite anything to the contrary in the Land Use Table or other provision of this Plan.
2 Subdivision—consent requirements
2 Subdivision—consent requirements
2.6 Subdivision—consent requirements
(1) Land to which this Plan applies may be subdivided, but only with development consent.
Notes.
(2) Development consent must not be granted for the subdivision of land on which a secondary dwelling is situated if the subdivision would result in the principal dwelling and the secondary dwelling being situated on separate lots, unless the resulting lots are not less than the minimum size shown on the Lot Size Map in relation to that land.
Note.
The definition of secondary dwelling in the Dictionary requires the dwelling to be on the same lot of land as the principal dwelling.
2
1
If a subdivision is specified as exempt development in an applicable environmental planning instrument, such as this Plan or State Environmental Planning Policy (Exempt and Complying Development Codes) 2008, the Act enables it to be carried out without development consent.
2
2
Part 6 of State Environmental Planning Policy (Exempt and Complying Development Codes) 2008 provides that the strata subdivision of a building in certain circumstances is complying development.
2 Demolition requires development consent
2 Demolition requires development consent
2.7 Demolition requires development consent
The demolition of a building or work may be carried out only with development consent.
Note.
If the demolition of a building or work is identified in an applicable environmental planning instrument, such as this Plan or State Environmental Planning Policy (Exempt and Complying Development Codes) 2008, as exempt development, the Act enables it to be carried out without development consent.
2 Temporary use of land
2 Temporary use of land
2.8 Temporary use of land
(1) The objective of this clause is to provide for the temporary use of land if the use does not compromise future development of the land, or have detrimental economic, social, amenity or environmental effects on the land.
(2) Despite any other provision of this Plan, development consent may be granted for development on land in any zone for a temporary use for a maximum period of 52 days (whether or not consecutive days) in any period of 12 months.
(3) Development consent must not be granted unless the consent authority is satisfied that—
(a) the temporary use will not prejudice the subsequent carrying out of development on the land in accordance with this Plan and any other applicable environmental planning instrument, and
(b) the temporary use will not adversely impact on any adjoining land or the amenity of the neighbourhood, and
(c) the temporary use and location of any structures related to the use will not adversely impact on environmental attributes or features of the land, or increase the risk of natural hazards that may affect the land, and
(d) at the end of the temporary use period the land will, as far as is practicable, be restored to the condition in which it was before the commencement of the use.
(4) Despite subclause (2), the temporary use of a dwelling as a sales office for a new release area or a new housing estate may exceed the maximum number of days specified in that subclause.
(5) Subclause (3) (d) does not apply to the temporary use of a dwelling as a sales office mentioned in subclause (4).
2 Canal estate development prohibited
2 Canal estate development prohibited
2.9 Canal estate development prohibited
(1) Canal estate development is prohibited on land to which this Plan applies.
(2) In this Plan, canal estate development means development that involves—
(a) a constructed canal, or other waterway or waterbody, that—
(i) is inundated by surface water or groundwater movement, or
(ii) drains to a waterway or waterbody by surface water or groundwater movement, and
(b) the erection of a dwelling, and
(c) one or both of the following—
(i) the use of fill material to raise the level o
This is an opening excerpt, not the complete document.