Carbon Credits (Carbon Farming Initiative—Domestic, Commercial and Industrial Wastewater) Methodology Determination 2015
8IApplications about other projects
Start here
Get a plain-English read of 8I
Turn the raw legal text into a practical explanation grounded in Carbon Credits (Carbon Farming Initiative—Domestic, Commercial and Industrial Wastewater) Methodology Determination 2015.
8I Applications about other projects
(1) This section applies to the following:
(a) the section 22 application or section 128 application for a biomethane conversion and displacement project or biomethane displacement-only project;
(b) the section 22 application for a restarting biomethane conversion and displacement project or restarting biomethane displacement-only project.
(2) An application to which this section applies must include the following information:
(a) which project type the project will be;
(b) which project activities will be carried out as part of the project;
(c) if the application relates to a biomethane conversion and displacement project or a restarting biomethane conversion and displacement project—a description of at least one project treatment facility that will be used in the project and the following details about each project treatment facility that will be used in the project:
(iii) the capacity of the facility, in ML or m3 of eligible wastewater treated by the facility per year;
(iv) the deep open anaerobic lagoons that are to be replaced by anaerobic digesters that are installed as part of the project at the facility;
(v) evidence of the historical sources of wastewater for the project to be treated at the facility;
Note: Project treatment facilities may also be adopted later, provided that they are documented in accordance with Part 5.
(d) a description of at least one project biomethane facility that will be used in the project and the following details about each project biomethane facility that will be used in the project:
(iii) the capacity of the facility, in m3 of biomethane produced by the facility per year;
(iv) any known proposal for the expansion of the facility over the course of the project;
(v) the intended recipients of biomethane produced by the project biomethane facility;
Note: Project biomethane facilities may also be adopted later, provided that they are documented in accordance with Part 5.
(e) a description of at least one biogas upgrading system that will be used in the project and the following details of each biogas upgrading system that will be used in the project:
(i) a brief description of the system;
(ii) the location of the system;
(f) a declaration from the project proponent that biomethane produced by project biomethane facilities can reasonably be expected to be combusted within Australia as a natural gas substitute;
(g) a description as to how the project can reasonably be expected to result in eligible carbon abatement.