34B Details of certain changes to a project must be included in offsets report
An offsets report for a reporting period for a project must include details of any of the following changes made to the project since the section 22 application or section 128 application for the project was made or since the last offsets report was given to the Regulator:
(a) a project treatment facility being added to the project or an existing project treatment facility being changed;
(b) a project biomethane facility being added to the project, or an existing project biomethane facility being changed, in which case, the report must also include:
(i) the intended recipients of biomethane produced by the new or changed project biomethane facilities; and
(ii) a declaration from the project proponent that biomethane produced by the new or changed project biomethane facility can reasonably be expected to be combusted within Australia as a natural gas substitute;
(c) a biogas upgrading system being added to the project or an existing biogas upgrading system being changed;
(d) an additional facility providing eligible material for the project, or any additional source of organic effluent being established;
(e) any other change in the information provided in the section 22 application or section 128 application for the project, in accordance with sections 9 to 9A.