68 Record keeping requirements
Choices and certification
(1) The project proponent for the project must keep a record:
(a) in relation to each choice made under Division 3 of Part 3 (including evidence of the day of the decision); and
(b) of any certification given by an accredited statistician under subsection 15(3).
Information about sites
(2) The project proponent must also keep a record of the following information about sites:
(a) the address, in the form approved by the Regulator, of every site that is or has been included in a population in the project;
(b) for a site that is affected by attrition in the population during the project—the day the site was affected by attrition and the circumstances in which the attrition occurred;
(c) for a site added to the population during the project—the circumstances in which the site was added.
Disposal of equipment and building components
(3) If, as part of the treatment under the project, the project proponent, the project proponent’s agent, or a person contracted by the project proponent:
(a) removes energy‑consuming equipment (the removed equipment) that is not being directly replaced; or
(b) delivers, installs, or facilitates the delivery or installation of, energy‑consuming equipment, and that equipment replaces other energy‑consuming equipment (the replaced equipment);
the project proponent must also keep a record of evidence that the removed equipment, or replaced equipment, was disposed of in accordance with relevant Commonwealth, State or Territory legislative requirements.
(4) If:
(a) as part of the treatment under the project, the project proponent, the project proponent’s agent, or a person contracted by the project proponent, (the relevant person) removes a building component or other equipment that is not removed equipment or replaced equipment; and
(b) the relevant person disposes of the building component or other equipment;
the project proponent must also keep a record of evidence that the disposal of the building component or other equipment was in accordance with relevant Commonwealth, State or Territory legislative requirements.