47A Relevant building surveyor must notify Authority and relevant council of certain information
(1) For the purposes of section 25AD(1) of the Act, the following events are prescribed—
(a) the builder named in a building permit ceases to be engaged to carry out the building work to which the permit relates;
(b) the relevant building surveyor changes the builder named on a building permit.
(2) For the purposes of section 25AD(1) of the Act, the following information is prescribed—
(a) if the builder named in a building permit ceases to be engaged to carry out building work to which the permit relates—
(i) the building permit number; and
(ii) the address of the building or land to which the building permit relates; and
(iii) the builder named in the building permit; and
(iv) the day that the builder named in the building permit ceased to be engaged to carry out the building work;
(b) if the relevant building surveyor changes the builder named on a building permit—
(i) the building permit number; and
(ii) the address of the building or land to which the building permit relates; and
(iii) the name of the builder named in the building permit and the builder's registration number (if applicable); and
(iv) the day on which the relevant building surveyor changed the name of the builder named in the building permit.