VICIn ForceRegulation
Building Regulations 2018
205Information to be supplied to council
Start here
Get a plain-English read of 205
Turn the raw legal text into a practical explanation grounded in Building Regulations 2018.
205 Information to be supplied to council
In addition to the requirements of section 73 of the Act, the relevant building surveyor must within 7 days—
(a) after issuing a certificate of final inspection, give to the relevant council a copy of the certificate; and
(b) after issuing an occupancy permit or a certificate of final inspection, give to the relevant council the approved dates of the inspections carried out of the mandatory notification stages of building work carried out on the building or land.