15 Requirements for demolition performed as part of work
(1) A person must not demolish, or remove, a building as part of building work or demolition work unless he or she has –
(a) removed, in accordance with the Act or any other Act, all known hazardous substances and materials from the premises, where the work is to be performed; and
(b) received written advice from –
(i) each relevant electricity entity that supplies electricity to the building, that –
(A) all supply of electricity to the building has been disconnected; and
(B) all aerial or underground electricity supply cables have been removed; and
(ii) each relevant gas entity that supplies gas to the building, that –
(A) all supply of gas to the building has been disconnected; and
(B) all supply lines for gas have been removed; and
(c) provided written notification to the following persons, or ensured that the following persons have received written notification, in respect of the following matters:
(i) the general manager of the relevant municipal area in respect of the timetable for capping any stormwater services on the premises as part of the work;
(ii) the relevant regulated entity in respect of the timetable in which –
(A) all sewers on the premises will be capped as part of the work; and
(B) all water supply lines on the premises will be sealed off as part of the work;
(iii) the Chief Officer in respect of the timetable in which –
(A) all telephone lines, or other signalling devices, associated with the monitoring of fire protection equipment monitored by the Tasmania Fire Service on the premises will be disconnected as part of the work; and
(B) the water supply to the building, or water supply device, booster or other assembly associated with fire protection equipment on the premises, will be removed, dismantled or altered as part of the work; and
Section 15 - Building Regulations 2016 - Requirements for demolition performed as part of work | Zoe
(C) all occupant safety systems including emergency warning intercommunication systems, air-handling systems, stairwell pressurisation systems or smoke or fire doors on the premises will be removed, dismantled or altered as part of the work.
Penalty: In the case of –
(a) a natural person, a fine not exceeding 50 penalty units; or
(b) a body corporate, a fine not exceeding 100 penalty units.
(2) A person must not, as part of permit building work or permit demolition work, demolish or remove a building in which essential building services that are fire safety requirements are present unless he or she has provided the Chief Officer with a copy of the relevant permit no later than the specified period before the work is to be performed.
Penalty: In the case of –
(a) a natural person, a fine not exceeding 50 penalty units; or
(b) a body corporate, a fine not exceeding 100 penalty units.
(3) A person, when demolishing or removing a building as part of building work or demolition work, must ensure that –
(a) all reasonable steps are taken at each point in the work to prevent building materials and debris falling onto or into –
(i) a place which is open to members of the public; and
(ii) premises adjacent to the premises where the demolition is being performed; and
(b) the positions of capped sewer and stormwater services, and sealed-off water supply lines, are clearly marked at the premises; and
(c) on completion of the demolition or removal –
(i) the site of the demolition or removal is clean and tidy; and
(ii) all glass, or other dangerous or hazardous materials, that is debris from the demolition or removal has been removed from the premises.
Penalty: In the case of –
(a) a natural person, a fine not exceeding 50 penalty units; or
(b) a body corporate, a fine not exceeding 100 penalty units.