10Limitation of time for building certifier to decide application for
Start here
Get a plain-English read of 10
Turn the raw legal text into a practical explanation grounded in BUILDING REGULATIONS 1993.
10 Limitation of time for building certifier to decide application for building permit The time within which a building certifier must decide an application for a building permit is: (a) if additional information is not required by the building certifier under section 58 of the Act – 20 days from the day that a completed application is made to the building certifier; or (b) if additional information is required by the building certifier under section 58 of the Act – 20 days from the day that all the additional information required by the building certifier is supplied to the building certifier.