ACTIn ForceRegulation
Building (General) Regulation 2008
36AGeneral requirements for plans—Act, s 63A
Start here
Get a plain-English read of 36A
Turn the raw legal text into a practical explanation grounded in Building (General) Regulation 2008.
36A General requirements for plans—Act, s 63A
(1) This section applies to plans accompanying an application for a
demolition order to demolish a building.
Demolition orders Division 3.6
(2) The plans must—
(a) be drawn in accordance with AS 1100, unless the plans were
drawn before the standard commenced; and
Note The standard may be purchased at www.standards.org.au.
(b) show any area covered by the plans that is marked as an
easement in the land titles register or on a deposited plan; and
(c) if the demolition will require the disconnection of a pipe to the
sewerage system—show any point of disconnection of the pipe
to the sewerage system; and
(d) if the demolition will require the disconnection of a pipe to a
water main—show any point of disconnection of the pipe to the
water main; and
(e) if the demolition will require the disconnection of a pipe to a
stormwater drain—show any point of disconnection of the pipe
to the stormwater system; and
(f) if the demolition will, when finished, alter the surface
stormwater drainage on the parcel of land where the work is to
be done—show the proposed surface stormwater drainage on the
parcel at the completion of the work; and
(g) for the parcel of land where the demolition is to be done—
include a site plan on a scale of not less than 1:200 showing—
(i) the block and section number of the land (or for land under
a land sublease, the sublease plan number); and
(ii) the boundaries and dimensions of the land.