37Stay of payments
Start here
Get a plain-English read of 37
Turn the raw legal text into a practical explanation grounded in Building and Construction Industry Security of Payment Act 2002.
37 Stay of payments
(1) If—
(a) a notice of claim is served on a principal under this Division in relation to the payment of money owed to a respondent under a contract; and
(b) before the notice was served, the principal had commenced proceedings in a court against the respondent in relation to that contract—
the principal may apply to the court for a stay of payments under this Division in respect of the notice of claim.
(2) The court may grant a stay applied for under subsection (1) and make any ancillary orders it considers necessary.
(3) Despite anything to the contrary in this Division, if a stay is granted under this section the principal is not required to make payments under this Division for the period of the stay.