10A Claimable variations
(1) This section sets out the classes of variation to a construction contract (the claimable variations) that may be taken into account in calculating the amount of a progress payment to which a person is entitled in respect of that construction contract.
(2) The first class of variation is a variation where the parties to the construction contract agree—
(a) that work has been carried out or goods and services have been supplied; and
(b) as to the scope of the work that has been carried out or the goods and services that have been supplied; and
(c) that the doing of the work or the supply of the goods and services constitutes a variation to the contract; and
(d) that the person who has undertaken to carry out the work or to supply the goods and services under the contract is entitled to a progress payment that includes an amount in respect of the variation; and
(e) as to the value of that amount or the method of valuing that amount; and
(f) as to the time for payment of that amount.
(3) The second class of variation is a variation where—
(a) the work has been carried out or the goods and services have been supplied under the construction contract; and
(b) the person for whom the work has been carried out or the goods and services supplied or a person acting for that person under the construction contract requested or directed the carrying out of the work or the supply of the goods and services; and
(c) the parties to the construction contract do not agree as to one or more of the following—
(i) that the doing of the work or the supply of goods and services constitutes a variation to the contract;
(ii) that the person who has undertaken to carry out the work or to supply the goods and services under the construction contract is entitled to a progress payment that includes an amount in respect of the work or the goods and services;
(iii) the value of the amount payable in respect of the work or the goods and services;
(iv) the method of valuing the amount payable in respect of the work or the goods and services;
(v) the time for payment of the amount payable in respect of the work or the goods and services; and
(d) subject to subsection (4), the consideration under the construction contract at the time the contract is entered into—
(i) is $5 000 000 or less; or
(ii) exceeds $5 000 000 but the contract does not provide a method of resolving disputes under the contract (including disputes referred to in paragraph (c)).