Building and Construction Industry Security of Payment Act 1999
11Due date for payment
Start here
Get a plain-English read of 11
Turn the raw legal text into a practical explanation grounded in Building and Construction Industry Security of Payment Act 1999.
11 Due date for payment
11 Due date for payment
(1) Subject to this section and any other law, a progress payment to be made under a construction contract is payable in accordance with the applicable terms of the contract.
(1A) A progress payment to be made by a principal to a head contractor under a construction contract (other than an exempt residential construction contract) becomes due and payable on—
(a) the date occurring 15 business days after a payment claim is made under Part 3 in relation to the payment, except to the extent paragraph (b) applies, or
(b) an earlier date as provided in accordance with the terms of the contract.
(1B) A progress payment to be made to a subcontractor under a construction contract (other than an exempt residential construction contract) becomes due and payable on—
(a) the date occurring 20 business days after a payment claim is made under Part 3 in relation to the payment, except to the extent paragraph (b) applies, or
(b) an earlier date as provided in accordance with the terms of the contract.
(1C) A progress payment to be made under an exempt residential construction contract becomes due and payable—
(a) on the date on which the payment becomes due and payable in accordance with the terms of the contract, or
(b) if the contract makes no express provision with respect to the matter, on the date occurring 10 business days after a payment claim is made under Part 3 in relation to the payment.
(2) Interest is payable on the unpaid amount of a progress payment that has become due and payable at the rate—
(a) prescribed under section 101 of the Civil Procedure Act 2005, or
(b) specified under the construction contract,
whichever is the greater.
(3) If a progress payment becomes due and payable, the claimant is entitled to exercise a lien in respect of the unpaid amount over any unfixed plant or materials supplied by the claimant for use in connection with the carrying out of construction work for the respondent.