Building Act 2016
327Accrual of cause of action
Start here
Get a plain-English read of 327
Turn the raw legal text into a practical explanation grounded in Building Act 2016.
327 Accrual of cause of action
(1) In this section –
cause of action, in relation to building work or plumbing work, means –
(a) a cause of action for damages, other than damages for death or bodily injury, incurred as a result of –
(i) defective building work or defective associated building work; or
(ii) defective plumbing work or defective associated plumbing work; or
(b) a counterclaim to such an action;
(2) A cause of action for any permit building work in respect of a building accrues –
(a) on the date on which an occupancy permit in respect of the building is issued after the completion of the permit building work; or
(b) if that permit is not issued –
(i) on the date of the first occupation of the building; or
(ii) 2 years after the issue of a building permit relating to that building, if the building is intended to be occupied but has not been occupied since the permit building work was completed; or
(c) if the building is occupied and there is no occupancy permit, on the date on which the work is completed.
(3) A cause of action for any permit plumbing work accrues –
(a) on the date on which a certificate of completion is issued in respect of the permit plumbing work; or
(b) if that certificate is not issued –
(i) on the date of the first use of the permit plumbing work; or
(ii) 2 years after the issue of a plumbing permit relating to that plumbing work, if the plumbing work is not used.
(4) A cause of action for any permit demolition work accrues –
(a) on the date on which a certificate of completion is issued in respect of the permit demolition work; or