201 Standard of work certificate (permit demolition work)
(1) Within the prescribed period after permit demolition work is completed, the responsible person for the work must –
(a) provide the relevant building surveyor with –
(i) a standard of work certificate (permit demolition work) for the work; and
(ii) a copy of any as-constructed plans for the work that have not previously been provided to the building surveyor; and
(b) provide a copy of the standard of work certificate (permit demolition work) to the owner of the premises where the work was performed.
(2) A standard of work certificate (permit demolition work) is to be in an approved form.