### 201 Standard of work certificate (permit demolition work)
> > (1) Within the prescribed period after permit demolition work is completed, the responsible person for the work must –
> >
> > > > (a) provide the relevant building surveyor with –
> > > >
> > > > > > (i) a standard of work certificate (permit demolition work) for the work; and
> > > > >
> > > > > > (ii) a copy of any as-constructed plans for the work that have not previously been provided to the building surveyor; and
> > >
> > > > (b) provide a copy of the standard of work certificate (permit demolition work) to the owner of the premises where the work was performed.
>
> > (2) A standard of work certificate (permit demolition work) is to be in an approved form.