193 Granting of application for demolition permit
(1) A permit authority may grant an application for a demolition permit under section 190 if –
(a) the permit authority is satisfied that the proposed permit demolition work will comply with this Act; and
(b) the building administration fee payable in respect of the demolition permit has been paid.
(2) A permit authority may grant an application for a demolition permit under subsection (1) subject to any condition imposed in accordance with section 195 .
(3) If a permit authority grants an application for a demolition permit under subsection (1) , the permit authority is to issue a demolition permit to each of the following persons:
(a) the applicant for the permit;
(b) the owner of the premises where the permit demolition work is to be performed;
(c) the building surveyor for the permit demolition work;
(d) each licensed builder named on the permit, or his or her business entity;
(e) each person prescribed for the purposes of this section.
(4) If an application for a demolition permit under section 190 is an application for a staged permit, the permit authority may specify, at the time of granting the application for the permit –
(a) that the permit is in effect for –
(i) such period, of more than 2 years, as may be specified in the permit; or
(ii) such period as may be specified in the permit for each stage of the permit; and
(b) that a certificate of completion (permit demolition work) is only required in respect of the completion of the last stage of the permit demolition work.
(5) The granting of an application for a staged permit under subsection (1) does not entitle the applicant to be granted any other permit in respect of any other stage of the permit demolition work.