### 192 Refusal of application for demolition permit
> > (1) A permit authority may refuse an application for a demolition permit under [section 190](#GS190@EN) if the permit authority considers the refusal to be reasonable in the circumstances.
>
> > (2) A permit authority must refuse an application for a demolition permit under [section 190](#GS190@EN) if the permit authority is satisfied that –
> >
> > > > (a) the proposed permit demolition work will not comply with this Act; or
> > >
> > > > (b) all appropriate protection work has not been, or will not be, performed in respect of the work; or
> > >
> > > > (c) the proposed permit demolition work will not be performed by persons qualified as required under [section 180(a)](#GS180@HpaEN) ; or
> > >
> > > > (d) the responsible person for the work does not meet the requirements of [section 5](#GS5@EN) .
>
> > (3) If a permit authority refuses an application for a demolition permit under [section 190](#GS190@EN) , the permit authority must notify the applicant in writing of –
> >
> > > > (a) the refusal of the application; and
> > >
> > > > (b) the reason for the refusal of the application; and
> > >
> > > > (c) the right of appeal under this Act in respect of the decision to refuse the application.