189Demolition permit required before performing permit demolition work
Start here
Get a plain-English read of 189
Turn the raw legal text into a practical explanation grounded in Building Act 2016.
### 189 Demolition permit required before performing permit demolition work
> > (1) A person must not perform permit demolition work unless –
> >
> > > > (a) there is a valid demolition permit in force in respect of the demolition work; or
> > >
> > > > (b) the demolition work is incidental to the performance of permit building work and there is a valid building permit in force in respect of the permit building work.
> >
> > Penalty: Fine not exceeding 100 penalty units.
>
> > (2) In addition to any penalty imposed under this section, a permit authority may take any necessary action, in relation to permit demolition work performed other than in accordance with a demolition permit, a building permit or an order under this Act, required to ensure the work complies with this Act.