186Duration of certificate of likely compliance (permit demolition work)
Start here
Get a plain-English read of 186
Turn the raw legal text into a practical explanation grounded in Building Act 2016.
### 186 Duration of certificate of likely compliance (permit demolition work)
> > (1) A certificate of likely compliance (permit demolition work) issued under this Subdivision expires 12 months from the date of issue.
>
> > (2) Despite [subsection (1)](#GS186@Gs1@EN) , a certificate of likely compliance (permit demolition work) issued under this Subdivision that is in force when submitted with an application for a demolition permit –
> >
> > > > (a) is taken to form part of any demolition permit issued as a result of that application; and
> > >
> > > > (b) remains in force until that demolition permit expires or lapses.