TASIn ForceAct
Building Act 2016
177Standard of work certificate (permit plumbing work)
Start here
Get a plain-English read of 177
Turn the raw legal text into a practical explanation grounded in Building Act 2016.
### 177 Standard of work certificate (permit plumbing work)
> > (1) Within the prescribed period after permit plumbing work is completed, the responsible person for the work must –
> >
> > > > (a) provide the relevant permit authority with –
> > > >
> > > > > > (i) a standard of work certificate (permit plumbing work) for the work; and
> > > > >
> > > > > > (ii) a copy of any as-constructed plans for the work that have not previously been provided to the permit authority; and
> > >
> > > > (b) provide a copy of the standard of work certificate (permit plumbing work) to the owner of the premises where the work was performed.
>
> > (2) A standard of work certificate (permit plumbing work) is to be in an approved form.