147 Extension of duration of building permit
(1) A person may apply to the permit authority that issued a building permit for an extension of the period for which that permit is in effect.
(1A) [Section 147 Subsection (1A) inserted by No. 39 of 2018, s. 24, Applied:01 Jan 2017] An application for an extension of the period for which a building permit is in effect must be made at least 5 business days before the building permit expires, unless the Director of Building Control has determined that special circumstances exist.
(2) An application for an extension of the period for which a building permit is in effect is to –
(a) be in an approved form; and
(b) include such information as is determined by the Director of Building Control; and
(c) [Section 147 Subsection (2) amended by No. 39 of 2018, s. 24, Applied:01 Jan 2017] be accompanied by such documentation as is required by the Director of Building Control and the permit authority.
(d) [Section 147 Subsection (2) amended by No. 39 of 2018, s. 24, Applied:01 Jan 2017] . . . . . . . .
(3) Before making a decision in respect of an application under subsection (1) in relation to a building permit –
(a) the permit authority is to request the relevant building surveyor to provide, within a specified period, advice regarding the permit building work being performed under the permit; and
(b) the building surveyor must comply with the request within that period.
(4) The permit authority that receives an application under subsection (1) in relation to a building permit may –
(a) extend the period for which the building permit is in effect; or
(b) refuse to extend the period for which the building permit is in effect; or