TASIn ForceAct
Building Act 2016
113Completion of notifiable plumbing work
Start here
Get a plain-English read of 113
Turn the raw legal text into a practical explanation grounded in Building Act 2016.
### 113 Completion of notifiable plumbing work
> > (1) A responsible person for notifiable plumbing work must notify the relevant permit authority for the work when the work is completed.
> >
> > Penalty: Fine not exceeding 100 penalty units.
>
> > (2) After receiving notification under [subsection (1)](#GS113@Gs1@EN) , the relevant permit authority is to specify, to the responsible person for the notifiable plumbing work, when the completed work is to be inspected by the permit authority.
>
> > (3) The responsible person for the notifiable plumbing work must, unless it is unreasonable in the circumstances –
> >
> > > > (a) ensure that the work is accessible and ready to be inspected at the time specified by the permit authority; and
> > >
> > > > (b) be present, or ensure that a qualified representative of the responsible person is present, at the work during that inspection.
>
> > (4) A representative under [subsection (3)(b)](#GS113@Gs3@Hpb@EN) is a qualified representative if –
> >
> > > > (a) he or she is qualified to perform or rectify, without supervision, the notifiable plumbing work that is being inspected; and
> > >
> > > > (b) the person performing the inspection is satisfied of those qualifications.