TASIn ForceAct
Building Act 2016
110Performing notifiable plumbing work
Start here
Get a plain-English read of 110
Turn the raw legal text into a practical explanation grounded in Building Act 2016.
### 110 Performing notifiable plumbing work
> > (1) A person must not perform any notifiable plumbing work, or cause or permit any notifiable plumbing work to be performed, unless he or she –
> >
> > > > (a) is satisfied that a certificate of likely compliance (notifiable plumbing work) is in force in respect of the work; and
> > >
> > > > (b) has notified the relevant permit authority that he or she intends to start the notifiable plumbing work; and
> > >
> > > > (c) has been provided with authorisation to start the work, and a unique authorisation number for the work, by the permit authority.
> >
> > Penalty: Fine not exceeding 100 penalty units.
>
> > (2) A person must perform any notifiable plumbing work in accordance with –
> >
> > > > (a) the most recent notice of work provided in respect of the work to the permit authority; and
> > >
> > > > (b) the certificate of likely compliance (notifiable plumbing work) provided in respect of the work.
> >
> > Penalty: Fine not exceeding 100 penalty units.
>
> > (3) If a responsible person for notifiable plumbing work ceases to be the responsible person for the work –
> >
> > > > (a) the work must stop; and
> > >
> > > > (b) the person who is to become the new responsible person for the work must notify the relevant permit authority of that fact before permitting the work to be performed.
>
> > (4) [*\[Section 110 Subsection (4) amended by No. 39 of 2018, s. 14, Applied:01 Jan 2017\]*](/view/html/inforce/2017-01-01/act-2018-039#GS14@Hpa@EN) If notifiable plumbing work has not been completed within 2 years after the authorisation to start the work was provided by a permit authority under [subsection (1)(c)](#GS99@Gs1@Hpc@EN) , the responsible person for the work must obtain, from the relevant permit authority at least 5 business days before the expiry of that period, written approval to continue with the notifiable plumbing work after the expiry of that period.
> >
> > Penalty: Fine not exceeding 100 penalty units.
>
> > (4A) [*\[Section 110 Subsection (4A) inserted by No. 39 of 2018, s. 14, Applied:01 Jan 2017\]*](/view/html/inforce/2017-01-01/act-2018-039#GS14@Hpb@EN) If the Director of Building Control has determined that special circumstances exist, a permit authority may give written approval under [subsection (4)](#GS99@Gs4@EN) whether or not that approval is given at least 5 business days before the expiry of the period specified in that subsection.
>
> > (5) The written approval of the permit authority under [subsection (4)](#GS99@Gs4@EN) is to specify one further period in which the notifiable plumbing work must be completed.