Bellingen Local Environmental Plan 2010 sets the legal rules for land in Bellingen: zoning, permitted and prohibited uses, consent pathways, subdivision and standards (lot sizes, heights, floor-space ratios), exemptions/complying development and environmental and heritage controls, implemented by maps and schedules. It affects landowners, developers, the Council and state agencies by determining what development needs consent and what activities are restricted. The Plan states aims such as supporting arts and ecological sustainability (cl 1.2); those aims are realised through technical controls that create compliance costs and change development incentives.
This local environmental plan sets the planning framework that determines what may and may not be done with land in the Bellingen local government area, and the procedural rules for deciding development applications. Mechanically, it:
Applies to the land identified on the Land Application Map and Land Zoning Map (cl 1.3; cl 2.2).
Fixes the consent authority as the Council, subject to the Act (cl 1.6).
Establishes the zoning regime (cl 2.1; cl 2.3): twenty-one zones are defined (for example RU1 Primary Production, R1 General Residential, E1 Local Centre, C2 Environmental Conservation, W1 Natural Waterways), with objectives, permitted without‑consent development, development permitted with consent, and prohibited development set out in the Land Use Table (cl 2.3; Land Use Table).
Determines principal development standards: minimum lot sizes and exceptions (cl 4.1; cl 4.1AA; cl 4.1AB; cl 4.1AC), height limits (cl 4.3), floor space ratio and how to calculate it (cl 4.4; cl 4.5), and the mechanism for exception to development standards (cl 4.6).
Prescribes categories of exempt and complying development and their limits (Part 3, cl 3.1-3.3; Schedule 2; Schedule 3). It excludes exempt/complying development from environmentally sensitive areas (cl 3.3).
Imposes topic-based local controls: subdivision consent requirements (cl 2.6), demolition consent (cl 2.7), temporary uses (cl 2.8 , 52 days per year as default), prohibition on canal estate development (cl 2.9), heritage controls (cl 5.10 and Schedule 5), acid sulfate soils (cl 7.1), water and biodiversity protections (cll 7.4-7.5), flood planning (cl 5.21), aquaculture controls (cl 5.19 and Schedule 6), intensive livestock agriculture (cl 5.18), signage and other small-scale exemptions (Schedule 2).
Current sections
Direct links to the current provisions in Bellingen Local Environmental Plan 2010.
State Environmental Planning Policy (Transport and Infrastructure) 2021, Chapter 2—relating to infrastructure facilities, including air transport, correction, education, electricity generating works and solar energy systems, health services, ports, railways, roads, waste management and water supply systems
Aquaculture; Bed and breakfast accommodation; Building identification signs; Business identification signs; Cellar door premises; Dual occupancies (attached); Dwelling houses; Extractive industries; Farm buildings; Home industries; Intensive livestock agriculture; Intensive plant agriculture; Neighbourhood shops; Open cut mining; Roads; Roadside stalls; Secondary dwellings; Any other development not specified in item 2 or 4
4
Prohibited
4 Prohibited
4 Prohibited
Amusement centres; Boat building and repair facilities; Camping grounds; Car parks; Caravan parks; Cemeteries; Centre-based child care facilities; Commercial premises; Depots; Eco-tourist facilities; Entertainment facilities; Exhibition homes; Exhibition villages; Freight transport facilities; Function centres; Health services facilities; Heavy industrial storage establishments; Highway service centres; Home occupations (sex services); Industrial retail outlets; Industrial training facilities; Industries; Information and education facilities; Local distribution premises; Marinas; Mooring pens; Mortuaries; Passenger transport facilities; Places of public worship; Public administration buildings; Recreation facilities (indoor); Recreation facilities (major); Recreation facilities (outdoor); Registered clubs; Residential accommodation; Respite day care centres; Restricted premises; Service stations; Sex services premises; Signage; Storage premises; Tourist and visitor accommodation; Transport depots; Truck depots; Vehicle body repair workshops; Vehicle repair stations; Veterinary hospitals; Warehouse or distribution centres; Wharf or boating facilities; Wholesale supplies
Part 3
Exempt and complying development
Part 3 Exempt and complying development
Part 3 Exempt and complying development
Part 4
Principal development standards
Part 4 Principal development standards
Part 4 Principal development standards
Part 5
Miscellaneous provisions
Part 5 Miscellaneous provisions
Part 5 Miscellaneous provisions
5
Relevant acquisition authority
5 Relevant acquisition authority
5.1 Relevant acquisition authority
(1) The objective of this clause is to identify, for the purposes of section 3.15 of the Act, the authority of the State that will be the relevant authority to acquire land reserved for certain public purposes if the land is required to be acquired under Division 3 of Part 2 of the Land Acquisition (Just Terms Compensation) Act 1991 (the owner-initiated acquisition provisions).
Note.
If the landholder will suffer hardship if there is any delay in the land being acquired by the relevant authority, section 23 of the Land Acquisition (Just Terms Compensation) Act 1991 requires the authority to acquire the land.
(2) The authority of the State that will be the relevant authority to acquire land, if the land is required to be acquired under the owner-initiated acquisition provisions, is the authority of the State specified below in relation to the land shown on the Land Reservation Acquisition Map (or, if an authority of the State is not specified in relation to land required to be so acquired, the authority designated or determined under those provisions).
| Type of land shown on Map | Authority of the State |
| Zone RE1 Public Recreation and marked “Local open space” | Council |
| Zone RE1 Public Recreation and marked “Regional open space” | The corporation constituted under section 2.5 of the Act |
| Zone SP2 Infrastructure and marked “Classified road” | Transport for NSW |
| Zone C1 National Parks and Nature Reserves and marked “National Park” | Minister administering the National Parks and Wildlife Act 1974 |
(3) Development on land acquired by an authority of the State under the owner-initiated acquisition provisions may, before it is used for the purpose for which it is reserved, be carried out, with development consent, for any purpose.
Note.
If land, other than land specified in the Table to subclause (2), is required to be acquired under the owner-initiated acquisition provisions, the Minister for Planning is required to take action to enable the designation of the acquiring authority under this clause. Pending the designation of the acquiring authority for that land, the acquiring authority is to be the authority determined by order of the Minister for Planning (see section 21 of the Land Acquisition (Just Terms Compensation) Act 1991).
Part 6
Urban release areas
Part 6 Urban release areas
Part 6 Urban release areas
6
Arrangements for designated State public infrastructure
6 Arrangements for designated State public infrastructure
6.1 Arrangements for designated State public infrastructure
(1) The objective of this clause is to require satisfactory arrangements to be made for the provision of designated State public infrastructure before the subdivision of land in an urban release area to satisfy needs that arise from development on the land, but only if the land is developed intensively for urban purposes.
(2) Development consent must not be granted for the subdivision of land in an urban release area if the subdivision would create a lot smaller than the minimum lot size permitted on the land immediately before the land became, or became part of, an urban release area, unless the Director-General has certified in writing to the consent authority that satisfactory arrangements have been made to contribute to the provision of designated State public infrastructure in relation to that lot.
(3) Subclause (2) does not apply to—
(a) any lot identified in the certificate as a residue lot, or
(b) any lot to be created by a subdivision of land that was the subject of a previous development consent granted in accordance with this clause, or
(c) any lot that is proposed in the development application to be reserved or dedicated for public open space, public roads, public utility undertakings, educational facilities or any other public purpose, or
(d) a subdivision for the purpose only of rectifying an encroachment on any existing lot.
(4) This clause does not apply to land in an urban release area if all or any part of the land is in a region within the meaning of the Act, Division 7.1, Subdivision 4.
(1) The objective of this clause is to ensure that development does not disturb, expose or drain acid sulfate soils and cause environmental damage.
(2) Development consent is required for the carrying out of works described in the Table to this subclause on land shown on the Acid Sulfate Soils Map as being of the class specified for those works.
| Class of land | Works |
| 1 | Any works. |
| 2 | Works below the natural ground surface.Works by which the watertable is likely to be lowered. |
| 3 | Works more than 1 metre below the natural ground surface.Works by which the watertable is likely to be lowered more than 1 metre below the natural ground surface. |
| 4 | Works more than 2 metres below the natural ground surface.Works by which the watertable is likely to be lowered more than 2 metres below the natural ground surface. |
| 5 | Works within 500 metres of adjacent Class 1, 2, 3 or 4 land that is below 5 metres Australian Height Datum and by which the watertable is likely to be lowered below 1 metre Australian Height Datum on adjacent Class 1, 2, 3 or 4 land. |
(3) Development consent must not be granted under this clause for the carrying out of works unless an acid sulfate soils management plan has been prepared for the proposed works in accordance with the Acid Sulfate Soils Manual and has been provided to the consent authority.
(4) Despite subclause (2), development consent is not required under this clause for the carrying out of works if—
(a) a preliminary assessment of the proposed works prepared in accordance with the Acid Sulfate Soils Manual indicates that an acid sulfate soils management plan is not required for the works, and
(b) the preliminary assessment has been provided to the consent authority and the consent authority has confirmed the assessment by notice in writing to the person proposing to carry out the works.
(5) Despite subclause (2), development consent is not required under this clause for the carrying out of any of the following works by a public authority (including ancillary work such as excavation, construction of access ways or the supply of power)—
(a) emergency work, being the repair or replacement of the works of the public authority required to be carried out urgently because the works have been damaged, have ceased to function or pose a risk to the environment or to public health and safety,
(b) routine maintenance work, being the periodic inspection, cleaning, repair or replacement of the works of the public authority (other than work that involves the disturbance of more than 1 tonne of soil),
(c) minor work, being work that costs less than $20,000 (other than drainage work).
(6) Despite subclause (2), development consent is not required under this clause to carry out any works if—
(a) the works involve the disturbance of less than 1 tonne of soil, such as occurs in carrying out agriculture, the construction or maintenance of drains, extractive industries, dredging, the construction of artificial water bodies (including canals, dams and detention basins) or foundations or flood mitigation works, or
(b) the works are not likely to lower the watertable.
(1) This clause applies to land at Railway Street, Dorrigo, being Lot 70, DP 1191049.
(2) Development for the purpose of a medical centre is permitted with development consent on the part of the land in Zone E4 General Industrial.
(3) Development consent under subclause (2) must not be granted after 5 years from the commencement of this clause.
4A
Use of certain land at 105 Cabans Road, Raleigh
4A Use of certain land at 105 Cabans Road, Raleigh
4A Use of certain land at 105 Cabans Road, Raleigh
(1) This clause applies to land at 105 Cabans Road, Raleigh, being Lots 63, 224, 258 and 293, DP 755553.
(2) Development for the purpose of a dwelling house is permitted with development consent, if all the lots are consolidated into a single lot.
(3) Development consent under subclause (2) must not be granted after 5 years from the commencement of this clause.
8
Use of certain land at Darkwood Road, Thora
8 Use of certain land at Darkwood Road, Thora
8 Use of certain land at Darkwood Road, Thora
(1) This clause applies to land at Darkwood Road, Thora, being Lot 23, DP 755542.
(2) Development for the purpose of a dwelling house is permitted with consent.
(3) Development consent under subclause (2) must not be granted after 5 years from the commencement of this Plan.
9
Use of certain land at Waterfall Way, Thora
9 Use of certain land at Waterfall Way, Thora
9 Use of certain land at Waterfall Way, Thora
(1) This clause applies to land at 2233, 2237 and 2239 Waterfall Way, Thora, being Lots 6 and 7, DP 264514 and Lot 1, DP 416923.
(2) Development for the purpose of a dwelling house on each lot is permitted with consent.
(3) Development consent under subclause (2) must not be granted after 6 August 2015.
10
10
10 (Repealed)
11
Use of certain land at Schnapper Beach Road, Urunga
11 Use of certain land at Schnapper Beach Road, Urunga
11 Use of certain land at Schnapper Beach Road, Urunga
(1) This clause applies to land at Schnapper Beach Road, Urunga, being the land shown as “Land at Schnapper Beach Road Urunga” on the Additional Permitted Uses Map.
(2) Development for the purpose of not more than 3 dwelling houses is permitted with consent.
(3) Development consent under subclause (2) must not be granted after 5 years from the commencement of this Plan.
12
Use of certain land at Wollumbin Drive, Urunga
12 Use of certain land at Wollumbin Drive, Urunga
12 Use of certain land at Wollumbin Drive, Urunga
(1) This clause applies to 52 and 54 Wollumbin Drive, Urunga, being Lots 2 and 3, DP 271191.
(2) Development for the purpose of a dwelling house on each lot is permitted with consent.
13
Use of certain land at Darkwood Road, Darkwood
13 Use of certain land at Darkwood Road, Darkwood
13 Use of certain land at Darkwood Road, Darkwood
(1) This clause applies to Lot 2, DP 755542, 975 Darkwood Road, Darkwood.
(2) Development for the purposes of a single dwelling house is permitted with development consent.
Exempt development may be carried out without the need for development consent under the Act. Such development is not exempt from any approval, licence, permit or authority that is required under any other Act and adjoining owners’ property rights and the common law still apply.
(1) Must not be the principal driveway to a domestic garage or carport.
(2) Must not be in Zone C1, C2, C3, W1 or W2.
(3) Must only be for stock, pedestrian or vehicle movements within land held in the one ownership and for the purposes of normal property management and operation.
(4) Must not require cut or fill more than 600mm below or above ground level (existing).
(5) Must not involve the construction of a bridge or causeway or obstruct the flow of water.
sch.2-sec-oc.2
Dams (on Zones RU1, RU2, RU4 and E4)
sch.2-sec-oc.2 Dams (on Zones RU1, RU2, RU4 and E4)
Display and advertising of goods and services on footpaths
sch.2-sec-oc.3 Display and advertising of goods and services on footpaths
Display and advertising of goods and services on footpaths
(1) This clause applies to the use of tables and other structures or items on a footpath adjoining a road in respect of which the Council is the roads authority under the Roads Act 1993 for the purpose of displaying or advertising any goods or services for sale.
(2) The following applies to the use to which this clause applies—
(a) must relate to a lawful use of the land on which the goods or services are offered or advertised for sale,
(b) the table or other structure or item in use must be erected and located in accordance with the Footpath Activities Policy adopted by the Council on 27 September 2017,
(c) the goods or services must be displayed or advertised in accordance with the Footpath Activities Policy adopted by the Council on 27 September 2017.
sch.2-sec-oc.4
Farm buildings—other than stock holding yards, grain silos and grain bunkers
sch.2-sec-oc.4 Farm buildings—other than stock holding yards, grain silos and grain bunkers
Farm buildings—other than stock holding yards, grain silos and grain bunkers
(5) Must be located at least 50m from any property boundary.
(6) Maximum height—3m.
(7) Must be constructed of prefabricated metal, free-standing and erected in accordance with manufacturer’s specifications.
(8) Must be kept in accordance with AS 1940–1993The storage and handling of flammable and combustible liquids.
(9) Must be clear from power lines in accordance with relevant electricity authority requirements.
(10) Only 1 per dwelling.
sch.2-sec-oc.6
Signage—general requirements
sch.2-sec-oc.6 Signage—general requirements
Signage—general requirements
(1) Must not be on land subject to the discharge of a 1:100 ARI (average recurrent interval) flood event unless the sign is a temporary sign, a real estate sign or fixed to a building.
(2) Must advertise only businesses or events that are operating legally.
(3) Must be located on the land or premises to which the sign relates, unless it is a temporary sign and the consent of the owner of the property is obtained.
Note.
Sign erected on or over a public road requires consent under the Roads Act 1993.
(4) Must not cover mechanical ventilation inlets or outlets.
(5) Must be of a professional standard and finish.
(6) Must not result in the total area of signage on a premises exceeding 5m2.
(7) All signs painted on windows must not be opaque and must not cover more than 3m2 per premises.
(8) Must not be located on any roof or above the line of any guttering, verandah or awning.
Note.
Signs on the fascia of the verandah or awning are included.
(9) Must not be attached to a tree.
(10) Must not cover more than 25% of any exterior wall.
(11) Must not be illuminated.
(12) Must not be suspended under an awning sign (unless in an employment zone) or a vertical or horizontal projecting wall sign.
(13) If a free standing structure, must not be higher than 1.8m.
sch.2-sec-oc.7
Signage—“A” frame signs on footpaths
sch.2-sec-oc.7 Signage—“A” frame signs on footpaths
Signage—“A” frame signs on footpaths
(1) This clause applies to “A” frame signage that is located on a footpath adjoining a road in respect of which the Council is the roads authority under the Roads Act 1993.
(2) The following applies to signage to which this clause applies—
(a) must relate to a lawful use of the land on which the sign is located,
(b) must be erected and located in accordance with the Footpath Activities Policy adopted by the Council on 27 September 2017,
(c) maximum of 1 per commercial premises,
(d) must be located on a section of the footpath adjoining the building to which the sign relates.
(1) Must meet the general requirements for signage.
(2) Must only contain the name and occupation of the resident.
(3) Maximum of 1 per premises.
(4) Must be located on the premises to which the sign relates.
(5) Maximum area—0.75m2.
(6) Must not be on a heritage item or within a heritage conservation area.
sch.2-sec-oc.9
Signage—real estate signs
sch.2-sec-oc.9 Signage—real estate signs
Signage—real estate signs
(1) Must meet the general requirements for signage.
(2) May involve a heritage item or be located within a conservation area.
(3) Must be located on the premises to which the sign relates.
(4) Maximum of 1 sign per agent, with a maximum of 4 signs per premises.
(5) Maximum area—
(a) in residential and rural zones—1.2m × 0.6m for a standard sign and 1.2m × 0.9m for an auction sign, or
(b) in Zone E4—2.5m2.
(6) Must not be attached to a tree.
(7) Must only be erected during the period for which the property is for sale or lease, except in the case of an auction sign, where the sign may be erected no more than four weeks before the auction date.
(8) Must not be displayed more than 7 days after contracts are exchanged for the sale of the premises or the premises are leased.
sch.2-sec-oc.10
Signage—suspended under awning signs in Zone E1
sch.2-sec-oc.10 Signage—suspended under awning signs in Zone E1
Signage—suspended under awning signs in Zone E1
(1) Must meet the general requirements for signage.
(2) If over a public road, must be at least 600mm from kerb edge.
(3) If located within Zone E1 in Urunga, may be illuminated, but must not include flashing lights.
(4) Maximum of 1 per premises.
(5) Must not be closer than 3m to another under awning sign, whether on the same property or not.
(6) Maximum area—1.5m2.
(7) If it extends over a public road, must be suspended at a height not less than 2.6m above ground level.
(8) Any opening created must be weatherproofed.
(9) Must not be located on a street frontage elevation of the building.
(10) Must not be on a heritage item or within a heritage conservation area.
sch.2-sec-oc.11
Signage—temporary signs for social, cultural, political or recreational events (other than erected by the Council)
sch.2-sec-oc.11 Signage—temporary signs for social, cultural, political or recreational events (other than erected by the Council)
Signage—temporary signs for social, cultural, political or recreational events (other than erected by the Council)
(1) Must meet the general requirements for signage.
(2) Must not be commercial advertising, but may name the event sponsor.
(3) Must not be displayed earlier than 28 days before the event or later than 7 days after the event.
(4) Must be safely constructed and securely fixed to prevent a nuisance or hazard.
(5) Must not be of a design (eg lettering size, style, number of words) or in a location that is a hazard to traffic.
sch.2-sec-oc.12
Subdivision of council public roads
sch.2-sec-oc.12 Subdivision of council public roads
Subdivision of council public roads
Must relate to land comprising a council public road proposed for closure under the Roads Act 1993, Part 4, Division 3.
This Plan is Bellingen Local Environmental Plan 2010.
1 Commencement
1 Commencement
1.1AA Commencement
This Plan commences on the day on which it is published on the NSW legislation website.
1 Aims of Plan
1 Aims of Plan
1.2 Aims of Plan
(1) This Plan aims to make local environmental planning provisions for land in Bellingen in accordance with the relevant standard environmental planning instrument under section 3.20 of the Act.
(2) The particular aims of this Plan are as follows—
(aa) to protect and promote the use and development of land for arts and cultural activity, including music and other performance arts,
(a) to give effect to the desired outcomes, strategic principles, policies and actions contained in the Council’s adopted strategic planning documents,
(b) to identify land that is suitable for development or environmental protection purposes and to encourage or restrict development accordingly,
(c) to progressively respond to changes in the natural, social and economic environment in a manner that is consistent with the principles of ecologically sustainable development.
The Dictionary at the end of this Plan defines words and expressions for the purposes of this Plan.
1 Notes
1 Notes
1.5 Notes
Notes in this Plan are provided for guidance and do not form part of this Plan.
Provides special local instruments: additional permitted uses for particular parcels (Schedule 1), urban release area arrangements including infrastructure certification and development control plan requirements (Part 6, cll 6.1-6.2), classification/reclassification of public land (cl 5.2 and Schedule 4).
Allows limited suspension of private covenants to enable development to proceed under the Plan (cl 1.9A), but lists exceptions (1.9A(2)) and preserves public authority interests (1.9A(3)).
Notes precedence and interaction with State instruments: the Plan is subject to SEPPs that prevail under section 3.28 of the Act (cl 1.9(1)).
The Plan therefore operates mainly by zoning and mapping controls, bespoke local limitations, and the imposition of standards and pre-conditions that must be satisfied before the Council may grant development consent. It delegates decision-making primarily to the Council but reserves particular roles for State agencies or the Director‑General in the urban release/infrastructure context (cl 6.1(2)-(3)). The Plan also imports and cross‑references requirements from a range of State Acts and SEPPs (see cll 1.9, 1.9A, 5.12 and elsewhere), so approvals under other regimes remain relevant.
The Plan presents its stated aims in cl 1.2: to implement the relevant standard environmental planning instrument under s 3.20 of the Act; to protect and promote arts and cultural activity (cl 1.2(2)(aa)); to give effect to Council’s strategic planning; to identify land for development or protection; and to respond progressively consistent with ecologically sustainable development (cl 1.2). Those are claimants’ policy purposes; the instrument’s concrete mechanics are the zoning, mapped standards, and topic clauses cited above.
Main concepts
The Plan builds around a small set of recurring statutory mechanisms and mapped instruments:
Zoning and the Land Use Table (cl 2.1-2.3; Land Use Table). Each zone has express objectives and three categories of uses: permitted without consent, permitted with consent, and prohibited. The consent authority must have regard to zone objectives when deciding DAs (cl 2.3(2)). The Land Use Table is the primary “what you may do where” instrument.
Maps and mapped standards. The Plan relies heavily on role‑specific maps: Land Zoning Map, Land Application Map, Lot Size Map, Height of Buildings Map, Floor Space Ratio Map, Natural Resources Sensitivity maps (Water and Biodiversity), Heritage Map and others (cl 1.7; cl 2.2; cl 4.1(3); cl 4.3; cl 4.4; cl 7.4; cl 7.5; cl 5.10). A map reference can constrain both permissibility and numerical standards.
Development consent framework. Most development that is not exempt or complying requires development consent from the Council (cl 2.6; cl 2.7; Part 3). The Plan specifies circumstances where consent is required (demolition cl 2.7), where consent must meet preconditions (acid sulfate soils cl 7.1(3)), and where consent must not be granted (e.g., flood planning cl 5.21(2)) unless the consent authority is satisfied particular risk criteria are met.
Exempt and complying development carve-outs. The Plan identifies additional exempt and complying development beyond State SEPPs (Part 3, cll 3.1-3.3; Schedules 2-3). However environmentally sensitive areas are excluded from exempt/compliant pathways (cl 3.3). Exempt development still must comply with the Building Code of Australia and other approvals may still be required (cl 3.1(3) and Note).
Development standards and exception process. The Plan fixes minimum lot sizes, height and floor space ratios. It also provides a mechanism for the consent authority to grant consent that contravenes a development standard, but only after the applicant demonstrates that compliance would be unreasonable or unnecessary and there are sufficient environmental planning grounds (cl 4.6(2)-(3)); the authority must record its assessment (cl 4.6(4)). Clause 4.6 expressly excludes some standards from variation (cl 4.6(8)).
Interaction with other laws. The Plan is not standalone; it treats SEPPs, the Heritage Act, Crown land and reserves Acts, the Local Government Act and other State statutes as co‑ordinating laws (cl 1.9; cl 1.9A; cl 5.2; cl 5.12; various Notes). Where the Plan is inconsistent with a SEPP the SEPP prevails (cl 1.9(1)).
Parcel-specific exceptions. Schedule 1 makes permitted uses for specific parcels (e.g. medical centre at part of Railway Street, Dorrigo , Schedule 1, cl 2A), generally time-limited (consents not to be granted after five years in many entries).
These concepts combine to create a rules‑based system where mapped constraints, zone objectives, and specialist topic rules determine entitlement and informational requirements for consent. The Plan repeatedly shifts regulatory burden to the DA process: the Council must be satisfied on specific matters before consent is granted (see cll 5.19(2) for aquaculture, 7.1(3) for acid sulfate soils, 5.21(2) for flood planning).
Who it affects
Primary actors and their roles under the Plan are set out in the instrument text.
Landowners and prospective developers. They are the main group affected. They must check the maps (cl 1.3; cl 2.2), the Land Use Table and schedules to determine whether their proposed activity is prohibited, permitted with consent, complying, or exempt. They bear the cost of obtaining assessments and approvals: environmental statements, heritage management documents (cl 5.10(5)-(6)), acid sulfate soils management plans (cl 7.1(3)), flood and biodiversity assessments (cl 5.21(3); cl 7.5(3)), aquaculture compliance with Schedule 6 (cl 5.19(2)), and any infrastructure certification required for urban release subdivisions (cl 6.1(2)-(3)). Subdivision applicants must also respect minimum lot sizes (cl 4.1) and community title conditions (cl 4.1AA; cl 7.11).
Council (consent authority). The Council is formally the consent authority (cl 1.6) and decides DAs, applies zone objectives (cl 2.3(2)), enforces local conditions (for example conservation covenants as conditions per cl 4.5(9)), and administers exempt development policies (Schedule 2). The Council also carries out public land classification/reclassification under cl 5.2 with the Local Government Act mechanics embedded, and must prepare or approve development control plans in an urban release area before grant of certain consents (cl 6.2).
State agencies and the Director‑General. The Plan reserves particular functions to State bodies: SEPPs prevail over the Plan (cl 1.9(1)); the Director‑General (or the relevant State official) must certify adequate arrangements for designated State public infrastructure before certain urban release subdivisions proceed (cl 6.1(2)); acquisition under the Land Acquisition (Just Terms Compensation) Act is allocated to authorities in cl 5.1; the corporation under s 2.5 of the Act is the acquiring authority for Regional open space (cl 5.1(2) table). State agencies also retain rights under registered instruments despite clause 1.9A(3).
Heritage and Aboriginal communities. Land with listed heritage items, conservation areas, archaeological sites or Aboriginal places will attract heightened consent requirements. The consent authority must notify the Heritage Council or local Aboriginal communities in specified circumstances and consider their responses (cl 5.10(7)-(9)). Those parties therefore are stakeholders in DA processes affecting heritage or Aboriginal places.
Utilities and infrastructure providers. Infrastructure needs are explicit: essential services must be available or adequate arrangements made before consent (cl 7.9); works under State SEPP (Transport and Infrastructure) are not restricted by this Plan (cl 5.12); and arrangements for State public infrastructure are required in urban release areas (cl 6.1).
Neighbours and the community. The Plan sets amenity and environmental protections that limit disturbance from activities such as intensive livestock (cl 5.18) and playing/performing music (cl 5.20), but it also allows temporary events up to 52 days per year (cl 2.8). Neighbours will be affected by development outcomes and will be involved through DA notification and heritage/Aboriginal consultation obligations where triggered (cl 5.10(8)).
Who pays: applicants pay for specialist reports and compliance; Council budgets for statutory processing and enforcement; State agencies may incur costs for designation/certification work; the broader community bears opportunity and environmental costs and gains arising from land use decisions. Who decides: Council as consent authority unless another instrument or SEPP applies, in which case the State role can intrude (cl 1.9; cl 6.1). What behaviour changes: developers will choose between exempt/compliant pathways and DAs depending on site maps and constraints; some uses (e.g., canal estates) are precluded entirely (cl 2.9), redirecting investment decisions; owners of heritage or environmentally sensitive parcels face heightened consenting costs and restrictions; owners of parcels in urban release areas face infrastructure certification processes before intensified subdivision (cl 6.1).
Key duties and rights
The Plan sets specific duties on the consent authority, applicants, and other parties; it also recognises certain discretionary rights.
Duties and obligations
Consent authority (Council) duties:
To determine DAs in accordance with the Act and this Plan; and to have regard to zone objectives when deciding DAs (cl 2.3(2)).
To refuse consent on flood planning grounds unless satisfied the development meets the flood planning tests in cl 5.21(2) (cl 5.21(2)).
To require heritage management documents or conservation management plans when development affects heritage items or heritage conservation areas (cl 5.10(5)-(6)), and to notify the Heritage Council or local Aboriginal communities where specified (cl 5.10(7)-(9)).
To consider the matters listed for intensive livestock agriculture, aquaculture, biodiversity, water and earthworks before granting consent (cll 5.18(3), 5.19(2), 7.5(3), 7.4(3), 7.2(3)).
To keep records of assessments for an application seeking to contravene a development standard under cl 4.6(4).
In an urban release area, not to grant subdivision consent that creates smaller lots than previously permitted unless the Director‑General has certified satisfactory arrangements for designated State public infrastructure (cl 6.1(2)).
Applicant duties:
To ensure proposed works meet exempt/compliant development requirements if relying on those tracks (cl 3.1-3.2), and to provide necessary approvals under other Acts (cl 3.1 Note).
To provide specialist documents where required: acid sulfate soils management plans for works in mapped classes (cl 7.1(3)); heritage management documents where required (cl 5.10(5)); statements of environmental effects or EIS as required by the Act (cl 5.18(3)(a) references adequacy of information).
To demonstrate, if seeking a variation to a development standard, that compliance is unreasonable or unnecessary and that there are sufficient environmental planning grounds (cl 4.6(3)); the Regulation requires an accompanying document for such applications (cl 4.6 Note).
Public authorities:
The Plan preserves public authority rights and excludes some instruments from the covenant suspension mechanism (cl 1.9A(2)-(3)), and it does not restrict development permitted under State SEPP Chapter 2 for infrastructure (cl 5.12(1)).
Rights and discretions
Applicants have the right to seek consent and to seek a variation to a development standard under cl 4.6, but must meet the evidentiary threshold and the consent authority must keep a record of its assessment (cl 4.6(3)-(4)).
Schedule 1 confers bespoke rights to particular parcels (e.g., permitted uses on named lots), sometimes time-limited (Schedule 1 entries; most include five-year limits).
The Plan allows temporary uses for up to 52 days per year by consent (cl 2.8(2)), and sales offices for new release areas can exceed that (cl 2.8(4)).
Exempt and complying pathways are rights available subject to the exclusions in cl 3.3; however environmentally sensitive areas cannot use those pathways (cl 3.3(1)).
Procedural duties and limits
Exempt development must meet the Building Code of Australia requirements and must not be designated development or be on land listed on the State Heritage Register (cl 3.1(3)(a)-(d)).
For heritage‑sensitive works, the consent authority must consider effects on heritage significance and is empowered to require a heritage management document or a conservation management plan, and can approve conservation incentives if conservation is facilitated by the proposed development (cl 5.10(4)-(10)).
For acid sulfate soils, a management plan prepared in accordance with the Acid Sulfate Soils Manual is required before consent is granted for works in mapped classes; preliminary assessment may avoid the need for a management plan if confirmed by the consent authority in writing (cl 7.1(3)-(4)).
Notice and consultation duties
The consent authority must notify the Heritage Council and local Aboriginal communities where required and consider any response within 28 days (cl 5.10(7)-(9)).
For urban release subdivisions that require Director‑General certification for State infrastructure, the DA may be held until that certificate is provided (cl 6.1(2)).
Taken together, the Plan allocates decision rights to Council but embeds a set of mandatory considerations and documentary preconditions that applicants must satisfy. The Plan confers conditional entitlements (exempt/compliant development categories) while reserving many developments for discretionary consent subject to specialist tests and mapped constraints.
Penalties and enforcement
The Plan itself is a statutory environmental planning instrument; it prescribes permissibility, conditions and processes rather than setting out standalone criminal penalties. The enforcement and penalty architecture is therefore primarily that of the Environmental Planning and Assessment Act and supporting regulations, which operate together with this Plan. The Plan contributes to enforcement in the following concrete ways:
It establishes where development requires consent, and where it is exempt or complying (Part 3; Schedule 2-3). Carrying out development inconsistent with these provisions will engage the enforcement powers and penalties under the Act and regulations (note: the Plan does not restate those penalties; it cross‑references the Act).
The Plan prescribes conditions or preconditions whose breach may lead to enforcement action. Examples include:
Carrying out works in acid sulfate soils areas without the required acid sulfate soils management plan (cl 7.1(3)) , omission could be the subject of an enforcement notice under the Act.
Ignoring heritage consent requirements (cl 5.10(2)-(3)) where consent is required for demolition, structural changes to heritage items, or excavation , such breaches invite heritage enforcement and potential orders to remediate.
Failing to comply with conditions attached to a complying development certificate as set out in Schedule 3 and State SEPPs (cl 3.2(4)).
Constructing in flood planning areas without meeting the cl 5.21 requirements.
Administrative enforcement: the Plan requires the consent authority to keep records of assessments under cl 4.6(4) and to take specific consultative steps (e.g. notice to Heritage Council and local Aboriginal communities with 28‑day consultation windows, cl 5.10(7)-(9)). Failures in these procedures could affect the validity of a consent and be subject to review or challenge under the Act.
Land classification and discharge of trusts (cl 5.2(5)) imposes procedural safeguards, including gubernatorial approval for certain reclassifications; failure to follow statutory procedure in making classifications could be subject to challenge.
What the Plan does not specify
The Plan does not list specific monetary fines or criminal penalties within its text. Those are contained in the Act and regulations governing unauthorised development, failure to comply with orders, or breach of development consent. The Plan does, however, create discretionary and mandatory duties that trigger the enforcement regime under the Act when not observed.
Practical enforcement implications
Enforcement action will typically be taken under the Act by Council or other authorised officers. The Plan multiplies enforcement touchpoints because it demands specialist pre‑conditions (heritage plans, acid sulfate management plans, flood and biodiversity tests), each of which introduces an additional compliance hurdle and enforcement focal point.
The Plan creates compliance risks where multiple regimes overlap (heritage, water, biodiversity, native title and Crown land instruments referenced in cl 1.9A), requiring careful cross‑agency coordination to enforce.
In short, penalties and enforcement are exercised under the procedural and sanctioning framework of the Act, with the Plan furnishing the detailed rules and conditions whose breach gives rise to enforcement action. The Plan itself prescribes the circumstances where consent is required and what documentary or pre‑condition duties must be met; it does not reproduce the Act’s penalty schedules.
How it interacts with other laws
The Plan is embedded in a statutory network. The instrument itself repeatedly cross‑references State legislation and State environmental planning policies, and it allocates particular tasks to State authorities. Key interactions shown in the text include:
The Environmental Planning and Assessment Act. The Plan expressly implements the LEP mechanism under s 3.20 of the Act (cl 1.2) and is subject to provisions of State environmental planning policies under s 3.28 as noted in cl 1.9(1). It uses terminology and consent pathways established by the Act (development consent, exempt and complying development, consent authority roles).
State Environmental Planning Policies (SEPPs). The Plan acknowledges that any SEPP that prevails over the Plan will do so (cl 1.9(1)). It also lists particular State SEPPs that may be relevant (Land Use Table note). Clause 5.12 explicitly defers to State SEPP (Transport and Infrastructure) Chapter 2 for public authority infrastructure works and existing Crown buildings.
Heritage Act 1977. The Plan requires consent for works affecting items listed on the State Heritage Register or subject to interim heritage orders (cl 3.1(3)(d)) and structures its heritage controls alongside the Heritage Act in cl 5.10, requiring notification to the Heritage Council and heritage management documents where appropriate.
Crown Land and National Parks regimes. Clause 1.9A excludes certain instruments from the covenant suspension power (the clause lists relevant instruments, including certain Crown land instruments under the Crown Land Management Act 2016 (cl 1.9A(2)(b)), conservation agreements under the National Parks and Wildlife Act 1974 (cl 1.9A(2)(c)), and other named instruments). Clause 5.2 interacts with the Local Government Act in classifying and reclassifying public land, and cl 5.1 allocates relevant acquisition authorities with reference to the Land Acquisition (Just Terms Compensation) Act 1991.
Fisheries, Water and Aquaculture law. The Plan’s detailed aquaculture controls (cl 5.19 and Schedule 6) cross‑refer to the Fisheries Management Act 1994 and to the Fisheries Management (Aquaculture) Regulation 2017 (definitions) and require consistency with aquaculture industry development plans and strategies. Dams in particular zones must be authorised under the Water Management Act 2000 (Schedule 2 item).
Local Government Act 1993. Public land classification/reclassification is governed by cl 5.2 with explicit reference to Part 2 of Chapter 6 of the Local Government Act.
Rural Fires Act 1997. The Plan defers to bush fire hazard reduction works carried out under the Rural Fires Act, allowing those works without development consent (cl 5.11).
Building Code and BASIX/BASIX‑like commitments. Exempt and complying development must meet the Building Code of Australia (cl 3.1(3)(a)-(b)). Clause 4.6(8) excludes contraventions to standards arising from BASIX commitments or certain clauses (e.g. clauses 5.4, 5.5, 6.1 or 7.9) from the cl 4.6 exception pathway.
Community Land Development Act and Strata Acts. The Plan adjusts subdivision rules to accommodate strata and community title subdivisions (cl 4.1(4); cl 4.1AA), and provides special rules for rural landsharing community development consistent with the Community Land Development Act (cl 7.11).
Consequences of these interactions
State instruments prevail where inconsistent (cl 1.9(1)). Practically this means applicants must check SEPPs first; the Plan supplements rather than replaces SEPP obligations.
Multi‑regime approvals. Many developments will need multiple approvals or licences under other Acts even if the Plan allows the use. For example, an exempt dam on RU zones still “must be authorised” under the Water Management Act (Schedule 2, dams item). The Plan’s Notes make clear that exempt development is not exempt from other Acts (cl 3.1 Note; Schedule 2 Note).
Covenant suspension is limited. Clause 1.9A creates a power to suspend private covenants to allow development in accordance with the Plan, but lists statutory instruments and agreements that are not affected and preserves public authority rights (1.9A(2)-(3)). This produces a hybrid interaction between private property encumbrances and the LEP consent regime.
Administrative coordination. The Plan anticipates coordination: Director‑General certification for State infrastructure in urban release areas (cl 6.1(2)); referrals and consultation for heritage and Aboriginal places (cl 5.10(7)-(9)); and the Plan’s references to the Department’s maps and guidelines (cl 1.7 Note; cl 5.21 references to flood guideline and Flood Risk Management Manual) embed State policy and technical guidance.
In summary, the Plan operates as the local manifestation of State planning policy but prescribes local variations, parcel‑specific allowances and constraints, and detailed local controls that sit alongside and in many cases require separate compliance with other statutory instruments.
Amendment history
The Plan text contains explicit amendment annotations. The instrument has been modified multiple times since its commencement; the Act’s amendment notes in the text allow us to trace the major updates recorded in the Plan itself. Key amendment entries in the provided text include:
2010 original making (the Plan is Bellingen Local Environmental Plan 2010 per cl 1.1).
Clause 1.9 (Application of SEPPs) was amended 2016 (2016 (310), Sch 4.3) , annotation shows cl 1.9: Am 2016 (310), Sch 4.3.
Clause 1.9A (Suspension of covenants) records amendments in 2011 and 2019: Am 2011 (363), Sch 4 [1]; 2019 (621), Sch 5[2]-[4].
Clause 1.8A (Savings provision relating to development applications) inserted/amended in 2019 (cl 1.8A: Am 2019 (621), Sch 5[1]).
Zone list cl 2.1: Amended 2022 (828), Sch 1.4[1] , indicating zoning updates in 2022.
Land Use Table records a long sequence of amendments: 2011 (363), Sch 4 [2]-[26]; 2011 No 62 Sch 2.5; 2014 (31) Sch 1 [1]; 2016 (168) Sch 1 [2]; 2016 No 55 Sch 3.1; 2017 (493) Sch 1.1 [1]; 2018 (488) Sch 1.1 [1]; 2019 (137) Sch 6 [1]; 2019 No 1 Sch 2.1; 2022 (314) Sch 1; 2022 (828) Sch 1.4[2]; 2023 (411) Sch 1[1]. This series indicates iterative updates to permitted uses across zones.
Clause 3.3 (Environmentally sensitive areas excluded) was amended 2011 (cl 3.3: Am 2011 (363), Sch 4 [27]).
Clauses and provisions concerning subdivision and strata/community title (cl 4.1AA, cl 4.1AB, cl 4.1AC) show insertions and later amendments: cl 4.1AA inserted 2011 (Ins 2011 (363), Sch 4 [28]) and later amended 2022 (2022 (828), Sch 1.4[3]); cl 4.1AB Ins 2014 (31), Sch 1 [2], Am 2016 (660) cl 5; 2022 (828) Sch 1.4[3]-[5]; 2024 (42) Sch 1.5[1]; cl 4.1AC Ins 2014 (31), Sch 1 [2]; Am 2022 (250) Sch 1[1][2]; 2022 (828), Sch 1.4[7].
Clause 4.2A (Erection of dwelling houses on land in certain rural and conservation zones) shows multiple amendments: Am 2010 No 119 Sch 2.5; 2011 (363) Sch 4 [29]; 2014 (31) Sch 1 [3]; 2022 (828) Sch 1.4[3][6][8]; 2023 (485) Sch 1[1][2].
Clause 4.6 (Exceptions to development standards) was amended 2011 (cl 4.6: Am 2011 (363), Sch 4 [32]).
Clause 5.1 (Relevant acquisition authority) and cl 5.2 (Classification and reclassification of public land) show amendments in 2011, 2019, 2020 and other years , cl 5.1 Note and cl 5.2: Am 2011, Sch 4 [37]; Sch 4 Am 2020 (445), cl 5(1).
Clause 5.5 (Controls relating to secondary dwellings on land in a rural zone) was substituted 2021 (cl 5.5 Subst 2021 (714), Sch 11.3).
Clause 5.10 (Heritage conservation) was substituted or amended in 2011 and 2013 and 2024 (cl 5.10 notes Subst 2011 (578), Sch 1 [5]; Am 2013 (435), Sch 1 [1]-[3]; 2024 (499), Sch 1[3]).
Clause 5.18 (Intensive livestock agriculture) and cl 5.19 (pond-based/tank aquaculture) carry amendments and cross-references to State aquaculture rules; cl 5.19 has been amended repeatedly, as annotated.
The amendment annotations in the Plan are extensive and indicate active maintenance; they show the Plan has been progressively modernised, with notable waves in 2011, 2014, 2016, 2019, 2022 and 2023. The annotations identify the amending instrument (year and citation fragment) but do not provide the amending text in full within the text you provided. Where the Plan has a Note that a clause was “Not adopted” or “Repealed” the text shows which local clauses have been left unused or removed (for example cl 5.13 inserted 2011 but “Not applicable”, cl 5.14 “Not adopted”).
If you need a clause‑by‑clause tracking table showing the exact textual changes introduced on each amendment date, I can extract each amendment note and present them chronologically with the clause references and citation fragments included in the Plan.
Litigation history
The instrument as provided does not include any case law or judicial decisions. The Plan text itself lists repeals, insertions and amendments but does not record litigation outcomes.
What the Plan records and what it does not
The Plan text records its own amendment history by marginal notes, and lists repealed planning instruments it replaced (cl 1.8(1) notes that all local environmental plans and deemed environmental planning instruments applying only to the land are repealed, specifically naming Bellingen LEP 2003).
The Plan does not compile or reproduce any judicial review, merits review or enforcement decisions. There are no cases cited in the body of the Plan.
Any litigation history , for example, judicial review of a Council decision or interpretation disputes about cl 4.6 exceptions to development standards , would be found in court or tribunal records, not in the Plan text itself.
Implication for practitioners
The absence of recorded litigation in the instrument text does not mean there has been no litigation. It means the Plan does not itself document decisions about its interpretation or enforcement. Practitioners seeking precedent on how particular clauses (for example cl 4.6 exception tests or cl 5.21 flood compatibility tests) have been interpreted should search case law databases and tribunal records for decisions mentioning Bellingen LEP 2010 or the particular clauses.
For review challenges to a Council decision, the Act’s judicial review and merits review pathways remain the relevant venues.
If you would like, I can prepare a search checklist (keywords, clauses and authorities) that you should use in commercial legal databases to locate decisions involving these specific LEP clauses.
Gotchas
The Plan contains a number of specific, high‑impact drafting features that commonly surprise practitioners and owners. These are concrete traps or friction points, with the clause citations that create them.
Exempt/compliant development exclusion in environmentally sensitive areas (cl 3.3)
Exempt or complying development is not available on multiple categories of environmentally sensitive areas (coastal waters, Ramsar wetlands, land within 100 metres of specified conservation areas, land identified as high Aboriginal cultural significance or high biodiversity significance). Practitioners must check the Natural Resources Sensitivity maps and the Heritage Map before assuming an exempt or complying pathway.
Savings provision for existing development applications (cl 1.8A)
A development application made before the Plan’s commencement that has not been finally determined must be determined as if this Plan had not commenced. This can be strategically important: DAs lodged prior to the Plan continue under the old rules and mapping, which may advantage some applicants and surprise neighbours relying on the Plan’s current mapping.
Suspension of covenants (cl 1.9A)
The Plan permits the suspension of private covenants to the extent necessary to enable development consistent with the Plan, but there are explicit exceptions (covenants required by Council, certain Crown land instruments, conservation agreements, biobanking agreements, planning agreements) and public authority interests are preserved (cl 1.9A(2)-(3)). Do not assume a private covenant can be overridden; check whether it falls within the listed exceptions.
Clause 4.6 exception to development standards has excluded items (cl 4.6(8))
The flexibility to contravene a development standard is constrained. Clause 4.6 excludes standards for complying development, BASIX commitments, clause 5.4, clause 5.5, clause 6.1, clause 7.9 and some other standards from the variation power. Attempting to use cl 4.6 to escape these excluded rules is not permitted.
Subdivision limits in rural and conservation zones (cl 4.6(6) and cl 4.2)
The Plan expressly prevents consent under cl 4.6 for subdivisions in certain zones that would create multiple lots under minimum areas or lots under 90% of minimum size. Rural subdivision flexibility exists (cl 4.2) but with caveats: e.g., a lot created under cl 4.2 cannot have a dwelling erected (cl 4.2(5)).
Floor space ratio “double dipping” and covenant remedy (cl 4.5(9)-(10))
The Plan contemplates covenants preventing “double dipping” floor area credits across consolidated lots. When consents use such covenants, future development on other parcels may have reduced allowable FSR (cl 4.5(9)-(10)). Practitioners must check whether existing consents carry such covenants.
Heritage procedural traps (cl 5.10)
The Plan empowers the consent authority to require heritage management documents and conservation management plans and to notify the Heritage Council. Failure to follow the notification obligations or to properly assess heritage impacts can lead to review or to invalid consents. The Plan allows conservation incentives (cl 5.10(10)), but only if conservation is demonstrably facilitated and conditioned.
Aquaculture and freshwater discharge restrictions (cl 5.19 and Schedule 6)
Intense aquaculture pond and tank projects must not discharge freshwater to natural waterbodies except from open flow‑through systems (Schedule 6 Div 2, cl 4). Pond design must avoid escape of stock (Schedule 6 cl 5). Projects in mapped conservation exclusion zones are restricted. Oyster aquaculture enjoys special exceptions in priority oyster aquaculture areas (cl 5.19(6)), which requires careful map checks and cross-reference to aquaculture industry development plans.
Canal estate prohibition (cl 2.9)
Canal estate development is prohibited throughout the Plan area. That is a categorical prohibition that will block projects involving constructed canals intended to drain/inundate and create residential waterway lots.
Temporary use limit and sales office exception (cl 2.8)
Temporary use consent generally capped at 52 days per 12 months. However, sales offices for new release areas may exceed this number (2.8(4)). Applications must justify non‑prejudice to future development and amenity safeguards (2.8(3)).
Exempt development and State heritage register (cl 3.1(3)(d))
Exempt development cannot be carried out on land listed on the State Heritage Register or subject to an interim heritage order. Do not assume small works are permissible without checking the Register.
Director‑General certification for urban release subdivisions (cl 6.1(2))
Subdivision that would create smaller lots than previously permitted in an urban release area requires certification from the Director‑General that satisfactory arrangements for designated State public infrastructure have been made. This is a State-level gate that can delay or block certain intensified subdivisions.
Essential services pre-condition (cl 7.9)
The consent authority must be satisfied essential services will be available or that adequate arrangements exist before granting consent. For projects in poorly serviced areas, this is a practical blocker.
Complexity of maps and multiple overlays
The Plan uses numerous maps: Land Zoning, Lot Size Map, Height Map, Floor Space Ratio Map, Heritage Map, Natural Resource Sensitivity maps, Land Reservation Acquisition Map. A single parcel can therefore be subject to multiple overlapping constraints; practitioners must compile and reconcile all relevant map overlays before advising.
Those “gotchas” are all grounded in the Plan clauses cited. They are practical traps because they shift costs onto applicants (specialist reports, design changes), impose non‑negotiable prohibitions (canal estates) or require State‑level certification (urban release infrastructure). The Plan intentionally ties many discretionary outcomes to preconditions and documentary tests; failing to spot one of these triggers is a common source of delay and review.
How to comply
Complying with the Plan requires a methodical, map‑driven approach together with the early procurement of specialist inputs where applicable. Below is a practical compliance workflow, linked to the relevant clauses and schedules in the Plan text.
Establish the applicable mapping and zoning
Consult the Land Zoning Map and Land Application Map to confirm the zone and any special mapping overlays (cl 1.3; cl 2.2).
Check the Lot Size Map, Height of Buildings Map and Floor Space Ratio Map for numerical limits (cll 4.1(3); 4.3; 4.4).
Review the Natural Resources Sensitivity,Water and ,Biodiversity maps, the Heritage Map and the Mineral Resource Area Map for overlays that trigger special requirements (cll 7.4; 7.5; cl 7.6; cl 5.10; Schedule 6 references).
Determine permissibility under the Land Use Table
Use cl 2.3 and the Land Use Table to see whether the proposed use is:
Permitted without consent (exempt development or permitted without consent but nevertheless subject to Part 5 of the Act),
Complying development (Schedule 3), or
Permitted only with development consent (and therefore requires a DA).
If the use is prohibited, the application cannot proceed under this Plan (cl 2.3(1)(d) & Land Use Table).
Check exempt and complying development exclusions
If considering an exempt or complying pathway, check cl 3.3: environmentally sensitive areas will exclude these options and the Building Code of Australia compliance rules apply (cl 3.1-3.3; Schedule 2-3).
Identify required specialist assessments early
Heritage: if the land contains a heritage item, is in a heritage conservation area or archaeological site, prepare a heritage management document or heritage conservation management plan as the consent authority may require one (cl 5.10(5)-(6)).
Acid sulfate soils: for works in mapped classes, prepare an acid sulfate soils management plan in accordance with the Acid Sulfate Soils Manual (cl 7.1(2)-(4)).
Flooding: for land in a flood planning area, prepare flood risk assessment and show how the design meets cl 5.21(2) tests and takes account of the Considering Flooding guideline and Flood Risk Management Manual (cl 5.21(3)-(4)).
Biodiversity: if on “Sensitive land” per the Natural Resources Sensitivity,Biodiversity Map, prepare ecological assessments addressing cl 7.5(3) and show avoidance, minimisation or mitigation measures (cl 7.5).
Water impacts: where the project is near waterways (cl 7.4), prepare water quality and bank stability assessments as required by cl 7.4(3)-(4).
Intensive livestock or aquaculture: check cl 5.18 (intensive livestock) and cl 5.19/Schedule 6 for specific capacity limits, species selection requirements and discharge rules (cl 5.18(4)-(5); Schedule 6 Divisions 1-2).
Earthworks: if significant, prepare an earthworks management plan addressing cl 7.2(3) matters.
Essential services: ensure arrangements for water, electricity, sewage, stormwater and vehicular access are documented (cl 7.9).
Evaluate whether any development standard variation will be required
If the proposal contravenes a Plan development standard, prepare the cl 4.6 “exceptions” justification documenting why compliance is unreasonable or unnecessary and the environmental planning grounds that justify the contravention (cl 4.6(3)). The Act’s regulations require a supporting document for such applications (cl 4.6 Note).
Confirm that the particular standard is not excluded from variation by cl 4.6(8).
Parcel‑specific checks
If the site is listed in Schedule 1 (additional permitted uses), confirm whether the proposed development fits the schedule conditions and any invocation deadlines (most Schedule 1 consents cannot be granted after five years).
Check whether any prior consent includes covenants that affect floor space calculation or subdivision (cl 4.5(9)-(10)).
Prepare the development application
Bundle the DA with:
Statements of environmental effects (including responses to the matters listed in cll 5.18(3), 7.4(3), 7.5(3), 5.21(3));
Heritage/archaeological assessments where relevant (cl 5.10(5));
Acid sulfate soils plans where required (cl 7.1(3));
Evidence of essential services or arrangements to provide them (cl 7.9);
For urban release subdivision, evidence of Director‑General certification for designated State public infrastructure where required (cl 6.1(2)); and
Any cl 4.6 justification if seeking to vary a development standard.
Make sure the Building Code of Australia matters are addressed for exempt/compliant paths (cl 3.1(3)).
Engage consultation/notification obligations early
Where heritage or Aboriginal places are affected, notify the Heritage Council or local Aboriginal communities as required and factor their response windows into the project timeline (cl 5.10(7)-(9)).
Where proposals might impact neighbours or public amenity (noise, odour, flooding), consider pre‑lodgement consultation and mitigation measures, especially given the Plan’s tests on amenity (e.g., intensive livestock cl 5.18(3)(b)-(f), music standards cl 5.20).
Consider statutory time windows and savings
If your DA was lodged before the Plan’s commencement, it will be determined under the earlier instrument by virtue of cl 1.8A. That can alter strategy (hold or re-apply) depending on comparative rules.
Post‑consent conditions and monitoring
Be alert to consent conditions requiring covenants (cl 4.5(9)), the carrying out of heritage conservation work (cl 5.10(10)(c)), environmental monitoring for aquaculture or intensive livestock, or staged infrastructure delivery for urban release areas (cl 6.1(3)). Prepare to register covenants where required.
Avoid forbidden development routes
Remember that canal estate development is prohibited (cl 2.9). Do not attempt to re-characterise canal estate features under another use.
Compliance auditing
For ongoing operations that were permitted without consent under thresholds (e.g., certain intensive livestock (cl 5.18(4)-(5)), oyster aquaculture in priority areas (cl 5.19(6))), keep documentation proving compliance with the site location and operational requirements in Schedule 6 and cl 5.19(2) as the consent authority may require compliance evidence.
Cross‑check other statutory approvals
Confirm and obtain any required licences or approvals under other Acts (Water Management Act, Fisheries Act, Crown land approvals, Heritage Act, Local Government Act approvals for on‑site effluent systems if unsewered per cl 3.2(3)(c)).
Practical tips for advisers
Map audit first. A parcel map audit that overlays every relevant Plan map with SEPP overlays and State maps (flood, oyster priority areas, biodiversity, heritage) will reveal most constraints.
Pre‑lodgement conference. Use a pre‑lodgement meeting with Council (and where relevant, with State referral agencies) to identify required documents and likely consent conditions.
Package the DA tightly. The consent authority’s obligations are many and specific; front‑loading the DA with the requisite assessments reduces requests for additional information and the risk of refusal or referral delays.
Watch the clock on consultation windows (heritage 28 days; others as required) and on schedule expiry (many Schedule 1 entries are time‑limited).
Check the excluded standards under cl 4.6(8) before relying on a variation strategy.
Following that sequence and addressing the clauses cited will materially reduce the risk of delays, refusals or enforcement action. If you want, I can turn the workflow into a checklist tailored to a particular parcel: specify the lot and DP and I will check the zones and relevant schedules in the Plan text you provided and list the exact assessments likely required.
The consent authority for the purposes of this Plan is (subject to the Act) the Council.
1 Maps
1 Maps
1.7 Maps
(1) A reference in this Plan to a named map adopted by this Plan is a reference to a map by that name—
(a) approved by the local plan-making authority when the map is adopted, and
(b) as amended or replaced from time to time by maps declared by environmental planning instruments to amend or replace that map, and approved by the local plan-making authority when the instruments are made.
(1AA) (Repealed)
(2) Any 2 or more named maps may be combined into a single map. In that case, a reference in this Plan to any such named map is a reference to the relevant part or aspect of the single map.
(3) Any such maps are to be kept and made available for public access in accordance with arrangements approved by the Minister.
(4) For the purposes of this Plan, a map may be in, and may be kept and made available in, electronic or paper form, or both.
Note.
The maps adopted by this Plan are to be made available on the NSW Planning Portal. Requirements relating to the maps are set out in the documents entitled Standard technical requirements for LEP maps and Standard requirements for LEP GIS data which are available on the website of the Department of Planning and Environment.
1 Repeal of planning instruments applying to land
1 Repeal of planning instruments applying to land
1.8 Repeal of planning instruments applying to land
(1) All local environmental plans and deemed environmental planning instruments applying only to the land to which this Plan applies are repealed.
Note.
The following local environmental plans are repealed under this provision—
Bellingen Local Environmental Plan 2003.
(2) All local environmental plans and deemed environmental planning instruments applying to the land to which this Plan applies and to other land cease to apply to the land to which this Plan applies.
1 Savings provision relating to development applications
1 Savings provision relating to development applications
1.8A Savings provision relating to development applications
If a development application has been made before the commencement of this Plan in relation to land to which this Plan applies and the application has not been finally determined before that commencement, the application must be determined as if this Plan had not commenced.
Note.
However, under Division 3.5 of the Act, a development application may be made for consent to carry out development that may only be carried out if the environmental planning instrument applying to the relevant development is appropriately amended or if a new instrument, including an appropriate principal environmental planning instrument, is made, and the consent authority may consider the application. The Division requires public notice of the development application and the draft environmental planning instrument allowing the development at the same time, or as closely together as is practicable.
cl 1.8A: Am 2019 (621), Sch 5[1].
1 Application of SEPPs
1 Application of SEPPs
1.9 Application of SEPPs
(1) This Plan is subject to the provisions of any State environmental planning policy that prevails over this Plan as provided by section 3.28 of the Act.
(2) The following State environmental planning policies (or provisions) do not apply to the land to which this Plan applies—
cl 1.9: Am 2016 (310), Sch 4.3.
1 Suspension of covenants, agreements and instruments
1 Suspension of covenants, agreements and instruments
1.9A Suspension of covenants, agreements and instruments
(1) For the purpose of enabling development on land in any zone to be carried out in accordance with this Plan or with a consent granted under the Act, any agreement, covenant or other similar instrument that restricts the carrying out of that development does not apply to the extent necessary to serve that purpose.
(2) This clause does not apply—
(a) to a covenant imposed by the Council or that the Council requires to be imposed, or
(b) to any relevant instrument within the meaning of section 13.4 of the Crown Land Management Act 2016, or
(c) to any conservation agreement within the meaning of the National Parks and Wildlife Act 1974, or
(d) to any Trust agreement within the meaning of the Nature Conservation Trust Act 2001, or
(e) to any property vegetation plan within the meaning of the Native Vegetation Act 2003, or
(f) to any biobanking agreement within the meaning of Part 7A of the Threatened Species Conservation Act 1995, or
(g) to any planning agreement within the meaning of Subdivision 2 of Division 7.1 of the Act.
(3) This clause does not affect the rights or interests of any public authority under any registered instrument.
(4) Under section 3.16 of the Act, the Governor, before the making of this clause, approved of subclauses (1)–(3).
The land use zones under this Plan are as follows—
Rural Zones
RU1 Primary Production
RU2 Rural Landscape
RU3 Forestry
RU4 Primary Production Small Lots
Residential Zones
R1 General Residential
R5 Large Lot Residential
Employment Zones
E1 Local Centre
E4 General Industrial
Special Purpose Zones
SP1 Special Activities
SP2 Infrastructure
Recreation Zones
RE1 Public Recreation
RE2 Private Recreation
Conservation Zones
C1 National Parks and Nature Reserves
C2 Environmental Conservation
C3 Environmental Management
C4 Environmental Living
Waterway Zones
W1 Natural Waterways
W2 Recreational Waterways
cl 2.1: Am 2022 (828), Sch 1.4[1].
2 Zoning of land to which Plan applies
2 Zoning of land to which Plan applies
2.2 Zoning of land to which Plan applies
For the purposes of this Plan, land is within the zones shown on the Land Zoning Map.
2 Zone objectives and Land Use Table
2 Zone objectives and Land Use Table
2.3 Zone objectives and Land Use Table
(1) The Land Use Table at the end of this Part specifies for each zone—
(a) the objectives for development, and
(b) development that may be carried out without development consent, and
(c) development that may be carried out only with development consent, and
(d) development that is prohibited.
(2) The consent authority must have regard to the objectives for development in a zone when determining a development application in respect of land within the zone.
(3) In the Land Use Table at the end of this Part—
(a) a reference to a type of building or other thing is a reference to development for the purposes of that type of building or other thing, and
(b) a reference to a type of building or other thing does not include (despite any definition in this Plan) a reference to a type of building or other thing referred to separately in the Land Use Table in relation to the same zone.
(4) This clause is subject to the other provisions of this Plan.
Notes.
2
1
Schedule 1 sets out additional permitted uses for particular land.
2
2
Schedule 2 sets out exempt development (which is generally exempt from both Parts 4 and 5 of the Act). Development in the land use table that may be carried out without consent is nevertheless subject to the environmental assessment and approval requirements of Part 5 of the Act.
2
3
Schedule 3 sets out complying development (for which a complying development certificate may be issued as an alternative to obtaining development consent).
2
4
Clause 2.6 requires consent for subdivision of land.
2
5
Part 5 contains other provisions which require consent for particular development.
2 Unzoned land
2 Unzoned land
2.4 Unzoned land
(1) Development may be carried out on unzoned land only with development consent.
(2) In deciding whether to grant development consent, the consent authority—
(a) must consider whether the development will impact on adjoining zoned land and, if so, consider the objectives for development in the zones of the adjoining land, and
(b) must be satisfied that the development is appropriate and is compatible with permissible land uses in any such adjoining land.
2 Additional permitted uses for particular land
2 Additional permitted uses for particular land
2.5 Additional permitted uses for particular land
(1) Development on particular land that is described or referred to in Schedule 1 may be carried out—
(a) with development consent, or
(b) if the Schedule so provides—without development consent,
in accordance with the conditions (if any) specified in that Schedule in relation to that development.
(2) This clause has effect despite anything to the contrary in the Land Use Table or other provision of this Plan.
2 Subdivision—consent requirements
2 Subdivision—consent requirements
2.6 Subdivision—consent requirements
(1) Land to which this Plan applies may be subdivided, but only with development consent.
Notes.
(2) Development consent must not be granted for the subdivision of land on which a secondary dwelling is situated if the subdivision would result in the principal dwelling and the secondary dwelling being situated on separate lots, unless the resulting lots are not less than the minimum size shown on the Lot Size Map in relation to that land.
Note.
The definition of secondary dwelling in the Dictionary requires the dwelling to be on the same lot of land as the principal dwelling.
2
1
If a subdivision is specified as exempt development in an applicable environmental planning instrument, such as this Plan or State Environmental Planning Policy (Exempt and Complying Development Codes) 2008, the Act enables it to be carried out without development consent.
2
2
Part 6 of State Environmental Planning Policy (Exempt and Complying Development Codes) 2008 provides that the strata subdivision of a building in certain circumstances is complying development.
2 Demolition requires development consent
2 Demolition requires development consent
2.7 Demolition requires development consent
The demolition of a building or work may be carried out only with development consent.
Note.
If the demolition of a building or work is identified in an applicable environmental planning instrument, such as this Plan or State Environmental Planning Policy (Exempt and Complying Development Codes) 2008, as exempt development, the Act enables it to be carried out without development consent.
2 Temporary use of land
2 Temporary use of land
2.8 Temporary use of land
(1) The objective of this clause is to provide for the temporary use of land if the use does not compromise future development of the land, or have detrimental economic, social, amenity or environmental effects on the land.
(2) Despite any other provision of this Plan, development consent may be granted for development on land in any zone for a temporary use for a maximum period of 52 days (whether or not consecutive days) in any period of 12 months.
(3) Development consent must not be granted unless the consent authority is satisfied that—
(a) the temporary use will not prejudice the subsequent carrying out of development on the land in accordance with this Plan and any other applicable environmental planning instrument, and
(b) the temporary use will not adversely impact on any adjoining land or the amenity of the neighbourhood, and
(c) the temporary use and location of any structures related to the use will not adversely impact on environmental attributes or features of the land, or increase the risk of natural hazards that may affect the land, and
(d) at the end of the temporary use period the land will, as far as is practicable, be restored to the condition in which it was before the commencement of the use.
(4) Despite subclause (2), the temporary use of a dwelling as a sales office for a new release area or a new housing estate may exceed the maximum number of days specified in that subclause.
(5) Subclause (3)(d) does not apply to the temporary use of a dwelling as a sales office mentioned in subclause (4).
2 Canal estate development prohibited
2 Canal estate development prohibited
2.9 Canal estate development prohibited
(1) Canal estate development is prohibited on land to which this Plan applies.
(2) In this Plan, canal estate development means development that involves—
(a) a constructed canal,
This is an opening excerpt, not the complete document.