83 Additional conditions—activity of decommissioning an NNP facility in a designated zone
(1) This section applies if the regulated activity authorised by the licence is the facility activity of decommissioning an NNP facility in a designated zone.
Decommissioning plan
(2) It is a condition that the regulated activity is, so far as reasonably practicable, conducted in accordance with the decommissioning plan for the facility.
(3) It is a condition that the decommissioning plan must ensure nuclear safety during and after the decommissioning of the facility.
(4) It is a condition that the licence holder must ensure that the decommissioning plan is effectively implemented and maintained throughout the period of the licence.
(a) it is a condition that the licence holder must, on the day the Act commences, provide information and documents that describe and document the decommissioning plan for the facility to the Regulator; and
(b) it is a condition that the licence holder must, on the day that is 6 months after the commencement of the Act, provide a preliminary disposal plan for the NNP facility to the Regulator.