79Additional conditions—activity of preparing a site for an NNP facility in a designated zone
Start here
Get a plain-English read of 79
Turn the raw legal text into a practical explanation grounded in Australian Naval Nuclear Power Safety Regulations 2025.
79 Additional conditions—activity of preparing a site for an NNP facility in a designated zone
(1) This section applies if the regulated activity authorised by the licence is the facility activity of preparing a site for an NNP facility in a designated zone.
Plan for preparing the site
(2) It is a condition that the regulated activity is, so far as reasonably practicable, conducted in accordance with the plan for preparing the site for the proposed NNP facility.
(3) It is a condition that the plan for preparing the site must ensure nuclear safety during the preparation of the site.
(4) It is a condition that the licence holder must ensure that the plan for preparing the site is effectively implemented and maintained throughout the period of the licence.
(a) it is a condition that the licence holder must, on the day the Act commences, provide information and documents that describe and document the plan for preparing the site for the facility to the Regulator; and
(b) it is a condition that the licence holder must, on the day that is 6 months after the commencement of the Act, provide a preliminary decommissioning plan for the proposed NNP facility to the Regulator.