Australian Jobs Act 2013
22AProject proponent must notify estimated completion date for a new relevant facility
Start here
Get a plain-English read of 22A
Turn the raw legal text into a practical explanation grounded in Australian Jobs Act 2013.
22A Project proponent must notify estimated completion date for a new relevant facility
(1) If: (a) the project proponent for a major project gives a draft AIP plan for the project to the Authority; and (b) the project involves establishing a new relevant facility; and (c) the establishment of the facility has not been completed; the project proponent must: (d) notify the Authority of the estimated date of completion of the establishment of the facility; and (e) do so at or about the same time as the draft AIP plan is given to the Authority. (2) A notification under subsection (1) must be in a form approved, in writing, by the Authority.