This local environmental plan sets zoning, permitted/prohibited uses, development consent rules and technical standards for land in the Armidale Region (cl 1.3; cl 2.1; cl 2.3). It appoints the Council as consent authority (cl 1.6) and imposes rules on subdivision, minimum lot sizes, heritage controls, flood and airport buffers and other local controls (cl 4.1; cl 5.10; cl 5.21; cl 6.3). Applicants bear application and compliance costs; the Council decides and has calibrated discretion through exceptions and variation clauses (cl 4.6).
This instrument is the Armidale Regional Local Environmental Plan 2012 (the Plan). Mechanically it establishes a local planning regime for land identified on the Land Application Map, replacing prior local plans for the same land (cl 1.3, cl 1.8). The Plan sets the zoning system and the Land Use Table that determines permitted, permitted-with-consent and prohibited development in each zone (cl 2.1, cl 2.3). It prescribes principal development standards including minimum lot sizes for subdivision (Part 4, cl 4.1 and related clauses), building height limits by map (cl 4.3), a range of additional local controls (Part 6), and schedules that list exempt development (Schedule 2), complying development (Schedule 3), additional permitted uses for particular parcels (Schedule 1), heritage items and conservation areas (Schedule 5) and aquaculture standards (Schedule 6).
Operationally, the Plan makes the local council the consent authority for decisions under the Plan, subject to the Environmental Planning and Assessment Act 1979 (the Act) and State policies (cl 1.6, cl 1.9(1)). It requires development consent for many categories of activity including subdivision (cl 2.6), demolition (cl 2.7), and works affecting heritage items and archaeological sites (cl 5.10(2)). It also identifies development that is exempt or complying, and sets the technical and locational limits for those categories (cl 3.1, cl 3.2, Schedule 2, Schedule 3).
The Plan embeds specific local controls and site-based exceptions. Examples include limits on shop floor area for particular parcels (Schedule 1 and cl 6.9, cl 6.10), controls on earthworks and remediation of a defined former gasworks site (cl 6.1 and cl 6.8), airport-related processes requiring Commonwealth consultation where proposed development would penetrate mapped operational surfaces (cl 6.3), and protections for heritage via mandatory heritage assessment, notification and the possibility of heritage management plans (cl 5.10(4)-(6)). It also contains procedural savings: a development application made but not finally determined before commencement must be determined as if the Plan had not commenced (cl 1.8A), and a suspension-of-covenants mechanism that makes private restrictions inoperative to the extent necessary to allow development consistent with the Plan, subject to enumerated exceptions (cl 1.9A).
Current sections
Direct links to the current provisions in Armidale Regional Local Environmental Plan 2012.
State Environmental Planning Policy (Transport and Infrastructure) 2021, Chapter 2—relating to infrastructure facilities, including air transport, correction, education, electricity generating works and solar energy systems, health services, ports, railways, roads, waste management and water supply systems
Agriculture; Air transport facilities; Animal boarding or training establishments; Aquaculture; Boat launching ramps; Boat sheds; Building identification signs; Business identification signs; Camping grounds; Caravan parks; Cellar door premises; Cemeteries; Charter and tourism boating facilities; Community facilities; Correctional centres; Crematoria; Depots; Dual occupancies; Dwelling houses; Eco-tourist facilities; Educational establishments; Environmental facilities; Extractive industries; Farm buildings; Flood mitigation works; Function centres; Home-based child care; Home businesses; Home industries; Industrial training facilities; Information and education facilities; Intensive livestock agriculture; Jetties; Landscaping material supplies; Marinas; Mooring pens; Moorings; Mortuaries; Neighbourhood shops; Open cut mining; Places of public worship; Plant nurseries; Recreation areas; Recreation facilities (outdoor); Research stations; Roadside stalls; Rural industries; Rural supplies; Rural workers’ dwellings; Service stations; Tourist and visitor accommodation; Transport depots; Truck depots; Veterinary hospitals; Water recreation structures; Water supply systems
4
Prohibited
4 Prohibited
4 Prohibited
Hotel or motel accommodation; Serviced apartments; Any other development not specified in item 2 or 3
Part 3
Exempt and complying development
Part 3 Exempt and complying development
Part 3 Exempt and complying development
Part 4
Principal development standards
Part 4 Principal development standards
Part 4 Principal development standards
Part 5
Miscellaneous provisions
Part 5 Miscellaneous provisions
Part 5 Miscellaneous provisions
5
Relevant acquisition authority
5 Relevant acquisition authority
5.1 Relevant acquisition authority
(1) The objective of this clause is to identify, for the purposes of section 3.15 of the Act, the authority of the State that will be the relevant authority to acquire land reserved for certain public purposes if the land is required to be acquired under Division 3 of Part 2 of the Land Acquisition (Just Terms Compensation) Act 1991 (the owner-initiated acquisition provisions).
Note.
If the landholder will suffer hardship if there is any delay in the land being acquired by the relevant authority, section 23 of the Land Acquisition (Just Terms Compensation) Act 1991 requires the authority to acquire the land.
(2) The authority of the State that will be the relevant authority to acquire land, if the land is required to be acquired under the owner-initiated acquisition provisions, is the authority of the State specified below in relation to the land shown on the Land Reservation Acquisition Map (or, if an authority of the State is not specified in relation to land required to be so acquired, the authority designated or determined under those provisions).
| Type of land shown on Map | Authority of the State |
| Zone RE1 Public Recreation and marked “Local open space” | Council |
| Zone RE1 Public Recreation and marked “Regional open space” | The corporation constituted under section 2.5 of the Act |
| Zone SP2 Infrastructure and marked “Classified road” | Transport for NSW |
| Zone C1 National Parks and Nature Reserves and marked “National Park” | Minister administering the National Parks and Wildlife Act 1974 |
| Zone RE1 Public Recreation and marked “Local road” | Council |
(3) Development on land acquired by an authority of the State under the owner-initiated acquisition provisions may, before it is used for the purpose for which it is reserved, be carried out, with development consent, for any purpose.
Part 6
Additional local provisions
Part 6 Additional local provisions
Part 6 Additional local provisions
6
Earthworks
6 Earthworks
6.1 Earthworks
(1) The objective of this clause is to ensure that earthworks for which development consent is required will not have a detrimental impact on environmental functions and processes, neighbouring uses, cultural or heritage items or features of the surrounding land.
(2) Development consent is required for earthworks unless—
(a) the earthworks are exempt development under this Plan or another applicable environmental planning instrument, or
(b) the earthworks are ancillary to development that is permitted without consent under this Plan or to development for which development consent has been given.
(3) Before granting development consent for earthworks (or for development involving ancillary earthworks), the consent authority must consider the following matters—
(a) the likely disruption of, or any detrimental effect on, drainage patterns and soil stability in the locality of the development,
(b) the effect of the development on the likely future use or redevelopment of the land,
(c) the quality of the fill or the soil to be excavated, or both,
(d) the effect of the development on the existing and likely amenity of adjoining properties,
(e) the source of any fill material and the destination of any excavated material,
(f) the likelihood of disturbing relics,
(g) the proximity to, and potential for adverse impacts on, any waterway, drinking water catchment or environmentally sensitive area,
(h) any appropriate measures proposed to avoid, minimise or mitigate the impacts of the development.
(1) This clause applies to part of Lot 80, DP 1059692, 35 Malpas Street, Guyra, identified as “Item 7” on the Additional Permitted Uses Map.
(2) Development for the purposes of cellar door premises, restaurants or cafes or viticulture is permitted with development consent.
8
Use of certain land in Zone C2
8 Use of certain land in Zone C2
8 Use of certain land in Zone C2
(1) This clause applies to the following land at Guyra in Zone C2, identified as “Item 8” on the Additional Permitted Uses Map—
(a) Lot 5, DP 1254715, 163 Baldersleigh Road,
(b) Lot 311, DP 753659, 350 Lagoon Road,
(c) Lot 359, DP 46361, 46 Chaffeys Lane,
(d) Lot 363, DP 704039, 218 Lagoon Road,
(e) Lot 1, DP 801051, 126 Lagoon Road,
(f) Lot 1, DP 1162151, 316 Lagoon Road,
(g) Lot 21, DP 1050356, 140 Lagoon Road,
(h) Lot 6, DP 1275249, 14 Charlies Lane,
(i) Lot 353, DP 39932, 92 Lagoon Road.
(2) Development for the purposes of extensive agriculture is permitted without development consent.
9
Use of certain land at 242 Rusden Street, Armidale
9 Use of certain land at 242 Rusden Street, Armidale
9 Use of certain land at 242 Rusden Street, Armidale
(1) This clause applies to Lot A, DP 329168, 242 Rusden Street, Armidale, identified as “Item 9” on the Additional Permitted Uses Map.
(2) Development for the purposes of retail premises is permitted with development consent if the gross floor area of the retail premises will not exceed 150m2.
10
Use of certain land at 57 Newton Street, Armidale
10 Use of certain land at 57 Newton Street, Armidale
10 Use of certain land at 57 Newton Street, Armidale
(1) This clause applies to Lot 4, DP 546075, 57 Newton Street, Armidale, identified as “Item 10” on the Additional Permitted Uses Map.
(2) Development for the purposes of light industries is permitted with development consent.
Exempt development may be carried out without the need for development consent under the Act. Such development is not exempt from any approval, licence, permit or authority that is required under any other Act and adjoining owners’ property rights and the common law still apply.
(2) Must be at least 700mm from kerb or roadway edge of a public road.
(3) Must be at least 2.6m above any public footpath.
(4) Must relate to the lawful use of the building (except for temporary signs or tourist information or directional signs).
(5) Must not be detrimental to the character and functioning of the building.
(6) Must not cover mechanical ventilation inlet or outlet vents.
(7) Must not be externally illuminated.
(8) Must not be flashing.
(9) Must not be internally illuminated, unless the sign is on premises in an employment zone or Zone MU1, or on business or industrial premises in Zone RU5 Village.
(10) If fixed to a wall—must be securely fixed by rigid non-corroding metal supports.
sch.2-sec-oc.2
Signage—signs on residential premises
sch.2-sec-oc.2 Signage—signs on residential premises
Signage—signs on residential premises
(1) Must meet the general requirements for signage.
(2) Must be on land in Zone RU1 Primary Production, Zone RU4 Primary Production Small Lots, Zone R1 General Residential, Zone R2 Low Density Residential, Zone R5 Large Lot Residential, Zone RE1 Public Recreation, Zone RE2 Private Recreation, Zone C1 National Parks and Nature Reserves, Zone C3 Environmental Management or Zone C4 Environmental Living.
(3) Maximum 2 signs per premises, including existing signs.
(4) Maximum area—1m2.
(5) Maximum height—3m.
(6) Must not be located on land on which there is a building that is a heritage item unless—
(a) no part of the sign will cover windows or architectural projections or other decorative features of the premises, and
(b) the sign can be removed without altering the fabric of the heritage item, and
(c) the sign is not painted onto the surface of the heritage item, and
(d) display of the sign does not require the removal of a tree.
sch.2-sec-oc.3
Signage—signs in employment or mixed use zones
sch.2-sec-oc.3 Signage—signs in employment or mixed use zones
Signage—signs in employment or mixed use zones
(1) Must be located on land in Zone RU5 or an employment or mixed use zone.
(2) Maximum 3 signs per premises, including existing signs.
(3) Must be one of the following types of signs—
(a) top hamper sign with maximum area—2.5m2, or
(b) under awning sign with maximum area—1.5m2, or
(c) projecting wall sign with maximum area—2.5m2, or
(d) flush wall sign that does not extend above the top of the wall to which it is attached and with maximum area—2.5m2.
(4) Must not be internally illuminated unless—
(a) the sign is not in continuous or intermittent motion, and
(b) the display is not varied at pre-set timing intervals.
(5) Must not be displayed on land on which there is a building that is a heritage item unless—
(a) no part of the sign will cover windows or architectural projections or other decorative features of the premises, and
(b) the sign can be removed without altering the fabric of the heritage item, and
(c) display of the sign does not require the removal of a tree.
(6) Must not be located on land in a heritage conservation area unless—
(a) maximum height—3m, and
(b) no part of the sign will cover windows or architectural projections or other decorative features of the premises.
sch.2-sec-oc.4
Signage—real estate signs
sch.2-sec-oc.4 Signage—real estate signs
Signage—real estate signs
(1) Must meet the general requirements for signage.
(2) Must be located within the boundaries of the premises.
(3) Maximum area for signs on residential premises—2.5m.
(4) Maximum height—6m.
(5) Must be removed within 14 days after the premises or land is sold or let.
(6) Maximum 2 signs per premises.
sch.2-sec-oc.5
Signage—signs behind the glass line of a shop window
sch.2-sec-oc.5 Signage—signs behind the glass line of a shop window
Signage—signs behind the glass line of a shop window
(1) Must meet the general requirements for signage.
(2) Must not be located in a sex services premises or restricted premises.
sch.2-sec-oc.6
Signage—replacement of existing signs
sch.2-sec-oc.6 Signage—replacement of existing signs
Signage—replacement of existing signs
(1) Must replace a sign lawfully displayed.
(2) Must not increase the display area or intensity of illumination.
sch.2-sec-oc.7
Signage—temporary signs (special events or venues for exhibitions or demonstrations)
sch.2-sec-oc.7 Signage—temporary signs (special events or venues for exhibitions or demonstrations)
Signage—temporary signs (special events or venues for exhibitions or demonstrations)
(1) Must meet the general requirements for signage.
(2) Maximum area—5m2.
(3) Maximum height—6m.
(4) Must not be displayed earlier than 28 days before, or later than 14 days after, the event.
(5) Must not obstruct the sight line of vehicular traffic.
(6) Must not be located on land on which there is a building that is a heritage item, unless—
(a) no part of the sign will cover windows or architectural projections or other decorative features of the premises, and
(b) the sign can be removed without altering the fabric of the heritage item, and
(c) the display of the sign does not require the removal of a tree, and
(d) maximum area—2.5m2.
sch.2-sec-oc.8
Signage—sponsorship signs (corporate sponsorship of a community or sporting event)
sch.2-sec-oc.8 Signage—sponsorship signs (corporate sponsorship of a community or sporting event)
Signage—sponsorship signs (corporate sponsorship of a community or sporting event)
(1) Must meet the general requirements for signage.
(2) Maximum height—6m.
(3) Must not include commercial advertising apart from the name or logo of any event sponsors.
(4) Must be located and oriented to be predominantly visible to spectators within the site rather than to the general public externally.
(5) Must not obstruct the sight line of vehicular traffic.
(6) Must not be located on land on which there is a building that is a heritage item, unless—
(a) no part of the sign will cover windows or architectural projections or other decorative features of the premises, and
(b) the sign can be removed without altering the fabric of the heritage item, and
(c) the display of the sign does not require the removal of a tree, and
(d) maximum area—2.5m2.
sch.2-sec-oc.9
Signage—tourist information or directional signs
sch.2-sec-oc.9 Signage—tourist information or directional signs
Signage—tourist information or directional signs
(1) Must indicate to the public tourist attractions and facilities in the locality, comprising—
(a) places of historical, scientific, educational or public interest, or
(b) picnic areas, parks or rest areas, or
(c) public buildings, public utilities or essential services, or
(d) recreational, sporting, charitable or religious facilities, or
(e) tourist and tourist-related facilities and undertakings, including caravan parks, camping grounds, tourist and visitor accommodation, and service stations.
(2) Maximum area—0.3m2.
(3) Maximum height—6m.
(4) Must not be located within a road reserve without the approval of the relevant road authority.
sch.2-sec-oc.10
Signage—A-frame signs on private land
sch.2-sec-oc.10 Signage—A-frame signs on private land
Signage—A-frame signs on private land
(1) Must be on land in an employment or mixed use zone.
(2) Only 1 per property.
(3) Maximum display area on each side—0.5m2.
(4) Must not obstruct access to the land or adjacent land.
(5) Must be secure and stable.
(6) Must not require construction work.
(7) Must not involve live or recorded entertainment, including music, broadcast programs or flashing lights.
(8) Must be removed at the close of business each day.
sch.2-sec-oc.11
Cemeteries and burial grounds
sch.2-sec-oc.11 Cemeteries and burial grounds
Cemeteries and burial grounds
(1) Must only involve—
(a) the creation of a new grave or monument, or
(b) the excavation or disturbance of land for the purpose of carrying out the conservation or repair of a monument or grave marker.
(2) Must be within an existing cemetery or burial ground.
(3) Must not involve development for which development consent is required under clause 5.10.
(4) Must not involve a heritage item.
sch.2-sec-oc.12
Lighting—external
sch.2-sec-oc.12 Lighting—external
Lighting—external
(1) Must not be for lighting a tennis court or sports ground.
(2) Must be constructed—
(a) to contain light spill within the site, and
(b) in accordance with AS/NZS 4282:2019, Control of the obtrusive effects of outdoor lighting.
This Plan is Armidale Regional Local Environmental Plan 2012.
cl 1.1: Am 2022 (716), Sch 1[1].
1 Commencement
1 Commencement
1.1AA Commencement
This Plan commences on the day on which it is published on the NSW legislation website.
1 Aims of Plan
1 Aims of Plan
1.2 Aims of Plan
(1) This Plan aims to make local environmental planning provisions for land in the Armidale Region in accordance with the relevant standard environmental planning instrument under section 3.20 of the Act.
(2) The particular aims of this Plan are as follows—
(aa) to protect and promote the use and development of land for arts and cultural activity, including music and other performance arts,
(a) to encourage the orderly management, development and conservation of resources by protecting, enhancing and conserving—
(i) land of significance for agricultural production, and
(ii) timber, minerals, soils, water and other natural resources, and
(iii) areas of high scenic or recreational value, and
(iv) native plants and animals, including threatened species, populations and ecological communities, and their habitats, and
(v) places and buildings of heritage significance,
(b) to provide a choice of living opportunities and types of settlements,
(c) to facilitate development for a range of business enterprises and employment opportunities,
(d) to ensure that development is sensitive to both the economic and social needs of the community, including the provision of community facilities and land for public purposes,
(e) to ensure that development has regard to the principles of ecologically sustainable development and to areas subject to environmental hazards and development constraints,
The Plan frequently cross-refers to State instruments and other Acts, for example State environmental planning policies, the Heritage Act 1977, the Rural Fires Act 1997 and fisheries and crown land laws. Many clauses state explicit objectives that the consent authority must have regard to when deciding applications, and other clauses set mandatory pre-conditions to consent being granted, for example availability of essential services (cl 6.6) and flood planning tests (cl 5.21).
Main concepts
The Plan organises land use and development in the Armidale Region around a small set of core legal concepts that carry operational consequences for applicants and the consent authority.
Zoning and the Land Use Table. Zones are defined in cl 2.1 and mapped in cl 2.2. The Land Use Table (cl 2.3 and the Land Use Table at Part 2) specifies for each zone the objectives and whether a use is permitted without consent, permitted with consent, or prohibited. The consent authority must have regard to zone objectives when determining applications (cl 2.3(2)).
Development consent threshold. Many activities require development consent including subdivision (cl 2.6), demolition (cl 2.7), erection of dwellings in specified rural and conservation zones (cl 4.2A), and certain conversions such as fire alarm system changes (cl 5.8). The Act is the primary statutory framework under which consent is given, and the Plan operates subject to it (cl 1.6, cl 1.9(1)).
Exempt and complying development. The Plan identifies exempt development (Schedule 2) and complying development (Schedule 3), but with important exclusions: exempt and complying development must not occur in designated environmentally sensitive areas (cl 3.3). Exempt development must meet Building Code standards and other criteria (cl 3.1). Complying development must be permissible with consent in the zone and meet relevant deemed-to-satisfy Building Code provisions (cl 3.2).
Principal development standards and flexibility. The Plan prescribes minimum lot sizes for subdivisions via the Lot Size Map and detailed clauses (cl 4.1 and cl 4.1AA-4.1E). It also includes an exceptions mechanism under cl 4.6 that permits the consent authority to grant consent for development that contravenes a development standard provided the applicant demonstrates compliance with the criteria in cl 4.6(3). That mechanism is bounded by express prohibitions, for example it cannot be used to breach certain complying development standards or BASIX commitments (cl 4.6(8)).
Heritage and archaeological controls. Schedule 5 lists heritage items, conservation areas and archaeological sites. Cl 5.10 makes many heritage-related works subject to consent and empowers the consent authority to require heritage management documents or conservation management plans and to consult the Heritage Council or local Aboriginal communities where archaeological sites or Aboriginal places of heritage significance are affected (cl 5.10(5)-(9)).
Special local controls. Part 6 contains focused, site-specific or issue-specific controls, for example earthworks (cl 6.1), airspace/airport operations and consultation requirements (cl 6.3), development in aircraft noise contours with acoustic standards to be met (cl 6.4), and remediation controls over a specified former gasworks site where penetration of capping or containment works is regulated (cl 6.8). These clauses typically set matters the consent authority must consider or pre‑conditions to consent.
Interaction and precedence. The Plan acknowledges State environmental planning policies that prevail where the SEPP so provides (cl 1.9(1)), and repeatedly cross-references other legislation such as the Heritage Act 1977, the Rural Fires Act 1997, the Fisheries Management Act and various State SEPPs. Several notes in the Plan flag that State policies may specify additional exempt or complying development or other technical requirements, signalling multi-layered regulatory oversight.
Together these concepts create a layered decision framework: zoning and maps define what is normally permitted; schedule and clause-based technical standards limit how those uses are implemented; procedural and evidentiary rules (heritage documents, BASIX, flood and airport tests) impose gating conditions; and exception mechanisms allow discretion subject to statutory criteria. Each layer imposes compliance tasks on applicants and discretionary assessments by the Council as consent authority.
Who it affects
Stakeholders affected by the Plan are varied and can be identified by legal role, economic interest and practical activity.
Landowners and developers. Owners of land within the Plan area are directly affected because the Plan defines permissible uses, minimum lot sizes for subdivision, and specific development constraints. Constraints on subdivision and dwelling erection in rural and conservation zones (cl 4.1, cl 4.2A, cl 4.1AA-4.1E) restrict the ability to fragment holdings, with direct implications for land value, development feasibility and potential redevelopment strategies. Owners of parcels listed in Schedule 1 receive specific additional permitted uses that benefit those parcels, for example educational establishment permission at 201 Canambe Street (Schedule 1, Item 1).
Council and consent authority. The Plan designates the Council as the consent authority (cl 1.6). The Council makes discretionary decisions under the Plan, must keep records of certain assessments (cl 4.6(4)), and has statutory responsibilities such as classifying public land under Schedule 4 (cl 5.2). Practical burdens on the Council include processing heritage management documents, coordinating Commonwealth consultation on airspace penetrations (cl 6.3), and applying special site clauses such as remediation controls at the former gasworks site (cl 6.8).
Existing and potential occupants. Residents in zones with noise or hazard exposure are affected through planning controls. For example, development within mapped aircraft noise contours must meet indoor design sound levels in AS 2021,2000 and the consent authority must consider siting tests (cl 6.4(3)). Flood-prone land falls within the flood planning area and the consent authority must ensure development will not increase flood affectation and will provide evacuation safety (cl 5.21).
Heritage stakeholders. Owners of heritage-listed properties and groups representing Aboriginal objects or places are affected by the heritage clauses that require consent for alteration, demolition, excavation and new buildings on or near listed sites (cl 5.10(2)-(3), (7)-(9)). The Plan mandates consultation with the Heritage Council and local Aboriginal communities where relevant (cl 5.10(7), (8)).
Businesses and traders. The Land Use Table and cl 5.4 set limits on retail and industrial uses in certain zones and additional permitted uses in Schedule 1 allow particular commercial activities at specified sites. Exempt and complying development rules, signage standards in Schedule 2, and retail floor area caps for neighbourhood shops, industrial retail outlets and farm gate premises (cl 5.4) shape business opportunities and constraints.
State and Commonwealth bodies. The Plan reserves certain acquisition and reservation arrangements and identifies relevant State authorities for acquisition under the Land Acquisition (Just Terms Compensation) Act 1991 (cl 5.1). The Plan also requires consultation with a relevant Commonwealth body on development that would penetrate mapped airport operational surfaces, giving the Commonwealth an explicit decision-making or clearance role in those cases (cl 6.3).
Utilities and service providers. Clause 6.6 makes essential services a pre-condition to consent, meaning water, electricity, sewage and road access providers are implicitly involved in assessing development readiness and timing.
Public authorities with land or enforcement roles. The Plan preserves the Crown’s rights in relation to use of existing Crown buildings and infrastructure permitted under State SEPPs (cl 5.12), and specifies exceptions where private covenants are suspended only to the extent necessary subject to listed exclusions including Crown instruments and planning agreements (cl 1.9A).
In short, the Plan shifts decision power to the local consent authority, alters the development rights of landowners both generally and by parcel through Schedule 1, creates procedural and technical obligations for applicants and Council, and embeds multi-level engagement requirements where State or Commonwealth interests are implicated.
Key duties and rights
The Plan sets duties for applicants and the consent authority, and recognises certain rights.
Duties and evidentiary obligations on applicants
Demonstrate compliance with standards for exempt and complying development. Exempt development must meet the Building Code of Australia and other Schedule 2 conditions (cl 3.1(2)-(5)). Complying development must be permissible in the zone and meet deemed-to-satisfy Building Code provisions and relevant Council approvals for on-site effluent where needed (cl 3.2(3)).
Provide material to justify any contravention of development standards. Under cl 4.6(3) a development application that proposes to contravene a development standard must be accompanied by grounds demonstrating that compliance is unreasonable or unnecessary and must set out sufficient environmental planning grounds to justify the contravention. The Environmental Planning and Assessment Regulation 2021 requires that an application seeking to contravene a standard include the document setting out the grounds.
Heritage and archaeological documentation. Where development affects a heritage item or conservation area the consent authority may require a heritage management document or conservation management plan before granting consent (cl 5.10(5)-(6)). If development is proposed on an archaeological site, notification to the Heritage Council and waiting 28 days for a response is required in most cases (cl 5.10(7)).
Flood and hazard assessments. For land within the flood planning area, applicants must demonstrate compatibility with flood function, that the development will not increase flood affectation, will allow safe evacuation and incorporate appropriate risk management measures (cl 5.21(2)-(3)).
Essential services availability. Applicants must satisfy the consent authority that essential services will be available when required, including water, electricity, sewage disposal and road access (cl 6.6).
Duties and decision-making duties on the consent authority (Council)
Have regard to zone objectives. The consent authority must have regard to the objectives for development in the relevant zone when determining applications (cl 2.3(2)).
Consider specified matters. Many clauses impose mandatory consideration duties. Examples include cl 4.6(3) for contraventions of development standards, cl 5.18 for intensive livestock agriculture where the consent authority must assess odour, water impacts and codes of practice, cl 6.3 requiring consultation with a Commonwealth body if a proposal penetrates mapped airspace surfaces, and cl 5.10 requiring consideration of heritage significance before granting consent.
Keep records. The consent authority must keep a record of its assessment when considering a contravention under cl 4.6(4).
Apply mandatory prohibitions. The consent authority must not grant consents in some circumstances, for example it must not grant consent for subdivision of land with a secondary dwelling that would separate principal and secondary dwellings onto different lots unless minimum lot sizes are met (cl 2.6(2)), and the Plan prohibits canal estate development (cl 2.9(1)-(2)). Cl 4.6(6) disallows using the exceptions mechanism to create multiple undersized lots in certain rural, residential and conservation zones.
Rights and entitlements
Right to existing development applications being determined under former rules. If an application was lodged before the Plan commenced and was not finally determined, it must be determined as if the Plan had not commenced (cl 1.8A). This is a transitional protection for applicants.
Parcel-specific rights. Schedule 1 confers additional permitted uses on particular parcels, creating site-specific rights that differ from the standard Land Use Table. For example, Schedule 1 Item 1 permits an educational establishment at 201 Canambe Street.
Ability to seek variation. Applicants may seek consent despite contravening a development standard under cl 4.6, by submitting the required justification material. This creates a procedural right to request flexibility, subject to the consent authority’s statutory assessment and limits in cl 4.6(8).
Exempt development rights. Where development qualifies as exempt under Schedule 2, the applicant may carry out the works without development consent, subject to other approvals, codes and exclusion zones like the environmentally sensitive areas list in cl 3.3.
Rights retained by public authorities and third parties
The Plan preserves rights of public authorities under registered instruments (cl 1.9A(3)). Covenants imposed by the Council are excluded from the suspension-of-covenants clause (cl 1.9A(2)(a)), and specific Crown instruments and conservation agreements are excluded (cl 1.9A(2)(b)-(f)). These provisions affirm that the Plan cannot be used to nullify particular statutory instruments or Council-imposed restrictions.
Taken together, the duty structure allocates the onus of technical compliance to applicants while giving the Council a structured discretion bounded by mandatory considerations and express prohibitions. Several clauses explicitly require consultation with or notification to other statutory bodies, creating inter-agency duty pathways.
Penalties and enforcement
The Plan sets legal requirements about where development consent is required, what must be considered and what uses are prohibited, but it does not itself set out new penalty levels in the text provided. Enforcement of compliance with development consent, exemptions and prohibitions derives from the Act and its regulations, which the Plan repeatedly invokes. The Plan therefore relies on the statutory enforcement regime under the Environmental Planning and Assessment Act 1979 and associated regulations for remedies where development proceeds without required consent or in breach of consent conditions.
Observable enforcement mechanisms and triggers in the Plan
Consent requirement triggers enforcement jurisdiction. Many clauses make development consent a pre-condition, for example subdivision (cl 2.6), demolition (cl 2.7), heritage-affecting works (cl 5.10(2)), and specific remediation works over the former gasworks capping layer (cl 6.8(3)). Proceeding without the necessary consent puts an applicant into the enforcement scope of the Act.
Record keeping and transparency as control. The Plan requires the consent authority to keep records of assessments under cl 4.6(4). That requirement facilitates internal accountability and provides documentary evidence in post-decision review or compliance processes.
Notifications to other statutory authorities. Clauses such as cl 5.10(7)-(9) create procedural notification obligations to the Heritage Council and to local Aboriginal communities. Those notification steps can lead to third‑party engagement, conserving cultural heritage and supplying material for enforcement or refusal decisions.
Prohibitions. The Plan contains express prohibitions which are legal limits on development, for example canal estate development is prohibited (cl 2.9(1)). The Plan also prohibits development that would penetrate certain remediation containment cells on specified lots (cl 6.8(5)). Breach of a prohibition gives rise to an enforcement concern under the Act.
What the Plan does not do
It does not, in the text provided, specify fines, time-limited injunction regimes or specific penalty provisions. The mechanism for penalties therefore rests with the Act. The Plan instead defines regulated activities and pre-conditions for consent, leaving enforcement measures to the broader statutory framework.
Practical enforcement implications
Non-compliance may lead to the Council taking action under the Act, which typically includes orders to remedy or remove unauthorised works, fines under the Act and potentially prosecution depending on the nature of the breach. The Plan’s detailed mapping and schedule references also mean that precise identification of zoning, lot size minima, height maps and heritage listings will be central in any compliance assessment.
Procedural lapses, such as failing to notify required parties when development affects heritage or archaeological sites, can create grounds for administrative review or third-party challenge. The Plan builds in those procedural safeguards which can be invoked during enforcement or merits reviews.
Readers planning projects should therefore treat the Plan’s consent triggers and mandatory consideration lists as enforcement touchpoints under the Act, and should consult the Act and its regulations for the specific enforcement powers and penalty levels that will apply in the event of non-compliance.
How it interacts with other laws
The Plan is expressly framed as operating within a multi-layered legal environment. It continually cross-references the Environmental Planning and Assessment Act 1979 (the Act) and a range of State and Commonwealth instruments and other statutes. The text defines a hierarchy and interaction points that determine which rules prevail and which agencies must be consulted.
Key statutory and policy interactions
Precedence of State Environmental Planning Policies. Clause 1.9(1) states the Plan is subject to any State environmental planning policy (SEPP) that prevails over it under section 3.28 of the Act. The Land Use Table notes list a range of SEPPs of likely relevance, for example SEPP (Housing) 2021, SEPP (Transport and Infrastructure) 2021 and SEPP (Resilience and Hazards) 2021. This means State policies can override local provisions where the SEPP so provides.
The Plan and the Act. The Plan repeatedly invokes the Act for procedural context, for example in cl 1.6 which makes the Council the consent authority "subject to the Act", and in cl 1.8A where Division 3.5 of the Act is referenced for applications involving amendments to environmental planning instruments. The Plan depends on the Act for its enforcement machinery, rights of appeal and other procedural mechanisms.
Heritage Act 1977. Cl 5.10 refers to the State Heritage Register and interim heritage orders under the Heritage Act. The Plan requires consent for works affecting items listed under the Heritage Act and sets out notification duties to the Heritage Council where works affect archaeological sites or nominated State heritage items (cl 5.10(7) and (9)). Consequently heritage approvals and procedures under the Heritage Act intersect with Plan requirements.
Crown and crown land laws. The Plan excludes certain Crown instruments from the suspension-of-covenants clause (cl 1.9A(2)(b)), and cl 5.12 affirms that the Plan does not restrict development by or on behalf of public authorities where SEPP (Transport and Infrastructure) 2021 applies. The Community Land and Crown land regimes referenced in various clauses mean Crown tenure matters remain governed by their primary Acts.
Land Acquisition Act 1991. Clause 5.1 identifies the relevant authorities for owner-initiated acquisitions under the Land Acquisition (Just Terms Compensation) Act 1991 and links the Plan’s Land Reservation Acquisition Map to acquisition processes under that Act. Where land parcels are shown with public reservations, the owner-initiated acquisition provisions of the Land Acquisition Act are engaged.
Fisheries, Marine Estate and Aquaculture law. Clauses relating to pond-based, tank-based and oyster aquaculture (cl 5.19 and Schedule 6) cross-reference the Fisheries Management Act 1994, the Marine Estate Management Act 2014 and relevant aquaculture industry development plans. The Plan imposes local site and operational requirements that operate alongside, and do not displace, licensing or approvals required under fisheries legislation.
Rural Fires Act 1997. The Plan defers to the Rural Fires Act in allowing bush fire hazard reduction work on any land without development consent (cl 5.11). However, the Plan also requires consideration of bush fire prone land in certain development controls, indicating an overlap between bush fire safety obligations and planning control.
Building Code, BASIX and other technical standards. Exempt and complying development clauses require adherence to deemed-to-satisfy Building Code of Australia provisions (cl 3.1(3)(a), cl 3.2(3)(b)). Clause 4.6(8)(b) prevents using the exceptions mechanism to contravene BASIX commitments. The Plan therefore integrates building and sustainability rules from other regimes.
Operational consequences of the interactions
Layered approval pathway. An applicant must navigate local zoning and Plan clauses, State SEPPs, separate heritage, fisheries or crown approvals where applicable, and building and sustainability codes when exempt or complying development is proposed. Compliance with one instrument does not replace approvals required under another Act; the Plan repeatedly notes that exempt development is not exempt from approvals required under other Acts (Schedule 2 Note 2).
Consultation and notification duties that cross jurisdictions. The Plan directs the consent authority to consult or notify Commonwealth bodies for airspace penetrations (cl 6.3), the Heritage Council for archaeological matters (cl 5.10(7)), and local Aboriginal communities for Aboriginal heritage (cl 5.10(8)). These duties create inter-governmental engagement points in decision-making.
Supremacy and practical conflicts. Where a SEPP or another higher-order statutory instrument prevails, the local Plan will be displaced to the extent of inconsistency (cl 1.9(1)). Applicants and consent authorities must therefore check State instruments before relying on local allowances or constraints in the Plan.
In summary, the Plan is not a standalone rulebook. It positions local controls within a web of State and Commonwealth statutes and policies, creating multiple checkpoints for approvals, overlapping technical standards to be complied with, and specific inter-agency consultation duties that become operational gates for consent.
Amendment history
The Plan’s text includes numerous amendment notations that indicate iterative updates since its original making. The instrument itself records many clause-level and schedule-level amendments with source notation. The notations in the Plan show amendments in particular years and sometimes indicate the amending instrument. The following summarises the amendment pattern visible in the source text, using the Plan’s own clause footnotes and schedule notes.
Early amendments and consolidations. Several clauses bear amendment footnotes referencing 2013, 2014 and 2016 actions. For example, cl 1.3 was amended in 2014 (Am 2014 (341), Sch 1[1]) and cl 1.8 records an amendment in 2014 (Am 2014 (341), Sch 1[2]). Schedule 5 also records amendments in 2013 and 2014 (sch 5: Am 2013 (503), Sch 1[1]-[11]; 2014 (341), Sch 1[4]).
Mid‑period amendments. The Land Use Table and other parts reflect amendments and insertions in 2016, 2017 and 2018, with notations such as Am 2016 (168), Sch 1 [2] [5]; 2017 (493), Sch 1.1 [1] [2]; 2018 (488), Sch 1.1 [1]. These changes often concern updating the Land Use Table and adding or adjusting permitted uses and zone listings.
2019 and 2020 updates. The Plan was amended in 2019 for provisions including the suspension of covenants clause and savings provisions, with explicit notations: cl 1.8A Am 2019 (621), Sch 5[1]; cl 1.9A Am 2019 (621), Sch 5[2]-[4]. Schedule 4 records an amendment in 2020 (sch 4: Am 2014 (420), cl 4 (1)-(4); 2020 (380), cl 4), indicating adjustments to the classification/reclassification listings.
Significant cluster of 2022 amendments. A substantial number of clauses cite amendments in 2022, identified by the same amending instrument codes for that year, for example cl 1.1 Am 2022 (716), Sch 1[1]; cl 1.2 Am 2022 (716), Sch 1[2]; cl 2.1 Am 2022 (716), Sch 1[3]; many of the Part 4 clauses and local provisions also show 2022 amendments (cl 4.1, cl 4.6, cl 5.10, cl 6.8 and others). Schedule notes (eg sch 1 and the Land Use Table) also indicate multiple 2022 amendment entries. The frequency and breadth of the 2022 notations suggest a comprehensive review and update was made that year affecting zoning, lot size rules and local provisions.
Later updates 2023-2026. The Plan shows amendment notations for 2019, 2021, 2022, 2023, 2024 and 2026 in various places. For instance, Schedule 1 notes amendments up to 2023 and 2022 (sch 1: Am 2014 (341); 2018 (488); 2021 (45); 2022 (716) Sch 1[44]-[47]; 2023 (28), cl 5; 2023 (534), Sch 1). Clauses such as cl 4.2A show being amended in 2026 (cl 4.2A: Am 2022 (716) … ; 2026 (66), Sch 1).
Repeals and insertions. The Plan records repeals of specific subclauses and inserts, such as cl 1.3(1A) repealed, cl 1.7(1AA) repealed, cl 6.2 repealed (Rep 2021 (225), Sch 1) and various insertion notes. Some schedules were substantiated or re-substantiated, for example Schedule 5 being "Subst 2022 (716), Sch 1[54]" and further amended 2024 (sch 5 note).
What the amendment history shows for practitioners
The Plan has been actively maintained, with multiple amendments across years and especially a significant set in 2022. Practitioners should not rely solely on older consolidations; they must consult the current consolidated online Plan and amendment instruments.
Clause-level footnotes are the primary source for tracing what was amended and when. Many substantive local rules, including lot sizes, zone listings, heritage and site-specific clauses, have recorded amendments, indicating a live local planning environment with periodic policy updates.
For precise drafting or litigation work, refer to the official NSW legislation or planning portal entries for each amending instrument referenced in the footnotes to obtain the exact textual change, commencement date and any transitional provisions.
The Plan’s own amendment annotations are the authoritative trail within the instrument. Users should cross-check those annotations against the amending instruments and the consolidated Plan on the NSW Planning Portal for up-to-date text and effective dates.
Litigation history
The Plan’s text as provided contains no citations of judicial decisions and does not include a litigation history. It does not refer to any cases or judicial determinations. Where the Plan references the Act and other statutes or the Heritage Council, those references imply potential pathways for dispute resolution and merits review under the Act and related legislation, but the Plan itself does not record litigation outcomes or established judicial interpretations.
Practical implications and litigation risk points for practitioners
Administrative review and merits appeal pathways. Because the Plan creates discretionary decision points for the consent authority (for example under cl 4.6 exceptions to development standards and many cl 5.x clauses), decisions made under the Plan are likely subject to the standard review and appeal processes under the Act and the Land and Environment Court jurisdiction. The Plan’s repeated use of "must be satisfied" and "must consider" language frames administrative standards that can be challenged in judicial review or merits appeal contexts.
Records and documentary obligations. The consent authority is required to keep records of assessments under certain clauses (cl 4.6(4)), and applicants must supply justifications for contravening standards (cl 4.6(3)). Those documentary requirements will feature in any subsequent review or challenge, making contemporaneous record keeping and the sufficiency of reasoning a litigation-relevant issue.
Heritage and Aboriginal heritage processes. Clauses that require notification to the Heritage Council or local Aboriginal communities (cl 5.10(7)-(9)) create procedural steps that, if not followed, may give rise to procedural challenge or affect the validity of a consent. Practitioners should note the Plan’s explicit procedural duties commonly relied upon in judicial review claims.
Interplay with State policies and other Acts. Because the Plan is subject to SEPPs and cross-references other Acts, litigation may raise questions about which instrument prevails and whether the consent authority correctly applied the relevant higher-order requirement. Challenges may therefore implicate interpretation of SEPPs, the Heritage Act or procedural requirements under the Act.
No reported cases in the instrument. The absence of case references in the Plan means any case law that affects interpretation will be found in the courts and not in the Plan text. Practitioners should therefore conduct case-law research under the Act and related statutes rather than searching the Plan for judicial interpretation.
In short, although the Plan itself records no litigation, it establishes numerous discretionary decisions and mandatory procedural steps that are typical sources of administrative law and merits review disputes. Those are standard litigation touchpoints for planning instruments in New South Wales.
Gotchas
The Plan contains several provisions and interactions that commonly trip up practitioners and developers. Below are specific "watch-outs" drawn directly from the Plan text with the operative mechanism identified.
Savings for pending applications, with an important caveat. Clause 1.8A provides that a development application lodged and not finally determined before the Plan’s commencement must be determined as if the Plan had not commenced. That protects applicants from sudden changes. However Division 3.5 of the Act, which cl 1.8A references, also allows the consent authority to consider an application that requires an environmental planning instrument amendment, provided public notice is given of both the application and the draft instrument as closely together as practicable. Practitioners should not assume automatic transfer of rights without checking whether the application requires an instrument amendment and whether the consent authority has acted under Division 3.5.
Suspension of private covenants is limited and requires Governor approval history. Clause 1.9A makes agreements, covenants or instruments that restrict development ineffective to the extent necessary to enable development consistent with the Plan, but it lists several important exceptions including covenants imposed by the Council and specified Crown instruments (cl 1.9A(2)). The clause also records that the Governor approved the clause under section 3.16 of the Act (cl 1.9A(4)), which is a procedural point that affects enforceability. Practitioners should examine whether a covenant is within the excluded categories and whether the rights of public authorities under registered instruments are preserved (cl 1.9A(3)).
Exempt and complying development excluded from many environmentally sensitive areas. Clause 3.3 prohibits exempt or complying development in a long list of environmentally sensitive areas including coastal waters, Ramsar wetlands, land within 100 metres of such areas, and places identified as high Aboriginal cultural or biodiversity significance. Developers seeking to rely on exempt or complying pathways must check that the site is not within the listed areas.
Exceptions to development standards are bounded. Clause 4.6 allows consent to be granted where a development contravenes a development standard if the applicant demonstrates compliance with cl 4.6(3). However cl 4.6(6) prevents using this mechanism to permit subdivisions that create multiple undersized lots in specified rural and conservation zones, and cl 4.6(8) excludes certain development standards from being varied by this clause, including complying development standards and BASIX commitments. Applications seeking variation must address these limits and the consent authority must keep a record of the assessment (cl 4.6(4)). The EP&A Regulation requires a supporting document.
Heritage procedural traps. Cl 5.10 makes many heritage works subject to consent and allows the consent authority to require heritage management documents or conservation plans. For archaeological sites, the consent authority must notify the Heritage Council and consider any response within 28 days (cl 5.10(7)). For Aboriginal places, local Aboriginal communities must be notified and responses considered within 28 days (cl 5.10(8)). Failure to observe these steps can open procedural challenges.
Parcel-specific rights and constraints. Schedule 1 and clauses 6.9-6.10 give parcel-specific permissions and caps on floor areas. Practitioners must check the Additional Permitted Uses Map and Clause Application Map carefully, because those site-based permissions modify the general Land Use Table.
Canal estate prohibition. Clause 2.9 prohibits canal estate development. Developers proposing works that involve excavation to create waterways or filling to create dwellings in flood planning areas must note the prohibition and the narrow exceptions for drainage or water supply works carried out by authorised bodies.
Height and FSR differences. The Plan adopts a Height of Buildings Map as the instrument for height limits (cl 4.3) but records that floor space ratio clauses have not been adopted (cl 4.4 and 4.5 are "Not adopted"). This creates a situation where height is a mapped limit but FSR is not used, which affects built-form analyses and may require alternative approaches to bulk and scale assessments.
Music and noise refusal protections. Clause 5.20(1) prevents the consent authority refusing licensed premises development on grounds related to music genre, live or amplified performance, instruments, dancing or presence of a dance floor, and cl 5.20(2) restricts refusal on noise grounds where noise may be managed to an acceptable level. Applicants and surrounding residents must analyse acoustic management early to avoid conflicts, because grounds for refusal are narrower than might be expected.
Airspace and Commonwealth consultation. Under cl 6.3 the consent authority must consult the relevant Commonwealth body if a development will penetrate the Limitation or Operations Surface for Armidale Regional Airport. Moreover the consent authority must not grant consent if that body advises the development should not be constructed. Practitioners must factor potential Commonwealth objections into project risk.
Intensive livestock and aquaculture locational tests. Clause 5.18 sets exclusion zones and distance requirements for intensive livestock that can be carried out without consent. Schedule 6 sets operational and species requirements for aquaculture. Applicants must check both locational criteria and operational thresholds, otherwise an application may be required or refused.
Essential services gate. Clause 6.6 makes availability of essential services a condition precedent to consent. Applicants proposing remote or unserviced development should plan for service provision or demonstrate adequate arrangements.
Each of these points is embedded in the Plan text and represents an operational constraint or procedural requirement that can materially affect project timing, costs and approvals strategy.
How to comply
Compliance with the Plan is a layered exercise requiring attention to zone mapping, schedules, technical standards and procedural steps. The following practical checklist is grounded in the Plan’s clauses and is aimed at applicants, advisers and consent authorities.
Confirm zoning and applicable maps
Check the Land Zoning Map, Lot Size Map, Height of Buildings Map, Clause Application Map, Airport Buffer Map, Sewage Treatment Plant Buffer Map and Heritage Map as referenced in cl 2.2, cl 4.1(3), cl 4.3, cl 6.5 and cl 5.10. These maps determine permissibility, minimum lot sizes, height limits and site-specific clauses such as the former gasworks site (cl 6.8).
Determine permissibility under the Land Use Table
Identify the zone and then consult the Land Use Table to see if the proposal is permitted without consent, permitted with consent, or prohibited (cl 2.3(1)-(3)). If the use is not listed, treat it as prohibited unless Schedule 1 provides a parcel-specific additional permitted use (cl 2.5, Schedule 1).
Check for exempt or complying pathways
For minor works, consult Schedule 2 for exempt development and Schedule 3 for additional complying development types and conditions (cl 3.1, cl 3.2). Ensure the site is not within an environmentally sensitive area where exempt/complying development is excluded (cl 3.3).
Assess subdivision and lot size rules early
For subdivision proposals, confirm the minimum lot size on the Lot Size Map and the application of cl 4.1 and related clauses such as cl 4.1AA, 4.1A-4.1E. If the proposal would create lots smaller than mapped minima, evaluate whether any exception clauses apply and whether cl 4.6 prevents variations for multiple undersized lots in specified zones.
Prepare heritage and cultural heritage material if relevant
If the site is listed in Schedule 5, or is within a heritage conservation area, include heritage impact assessments and be prepared to provide heritage management documents or conservation plans if requested by the consent authority (cl 5.10(4)-(6)). For archaeological sites or Aboriginal places, allow time for statutory notifications and the 28-day consideration periods (cl 5.10(7)-(9)).
Satisfy technical pre-conditions
For flood-prone land, prepare flood risk assessments referencing the Considering Flooding in Land Use Planning Guideline and the Flood Risk Management Manual as required by cl 5.21. For aircraft noise or airport buffer areas, include acoustic reports conforming to AS 2021,2000 and consult the relevant Commonwealth body if airspace penetration is an issue (cl 6.3, cl 6.4).
Demonstrate essential services
Under cl 6.6, ensure that water, electricity, sewage disposal, stormwater drainage and road access either exist or that adequate arrangements are in place for their provision at the time of occupation or as required for the development.
If seeking variation to development standards, follow cl 4.6 and EP&A Regulation requirements
Prepare the document required by the EP&A Regulation to justify a contravention under cl 4.6(3), demonstrating why compliance is unreasonable or unnecessary and the environmental planning grounds that justify the contravention. Be aware of prohibitions under cl 4.6(6) and cl 4.6(8), and that the consent authority must record its assessment (cl 4.6(4)).
Consider parcel-specific and local clauses
Review Schedule 1 for additional permitted uses on particular parcels, and relevant Part 6 clauses such as cl 6.8 remediation rules for the former gasworks site, cl 6.9-6.10 gross floor area caps for certain shops, and cl 5.24-5.25 controls on farm stay and farm gate premises.
Manage procedural notifications and consultative duties
Factor in statutory notifications: Heritage Council notifications, local Aboriginal community notifications, and Commonwealth consultation for airport surface penetrations (cl 5.10(7)-(9), cl 6.3). These processes have statutory timelines and can affect decision-making.
Address signage, retail floor area and other quantums
If the proposal includes signage, check Schedule 2 (sch.2-sec) for sign size, height and illumination limits. For retail or industrial proposals review cl 5.4 which caps retail floor area for industrial retail outlets, neighbourhood shops and neighbourhood supermarkets, and other quantums such as bed numbers for bed and breakfast and farm stay accommodation.
Engage early with the consent authority and relevant agencies
Given the degree of discretionary assessment and inter-agency consultation signalled by the Plan, engage the Council early to identify expected heritage, flood and service requirements. Pre-lodgement meetings will help identify which studies, heritage documents and notifications will be necessary.
Keep records and prepare to justify decision-making
The consent authority must keep assessment records in certain cases (cl 4.6(4)). Applicants should provide clear material and maintain records of communications, expert reports and mitigation measures to support decision-making and to respond to any review or compliance enquiries.
Check related Acts and SEPPs
Confirm whether any State environmental planning policy applies and prevails, and check whether other Acts such as the Heritage Act, Fisheries Management Act or Crown land laws impose separate licensing, approvals or exemptions that the development must satisfy (cl 1.9, cl 5.12, cl 5.19).
Following this checklist will not guarantee approval but will align applications with the Plan’s structure and its many specific technical and procedural gates. Where uncertainty exists, legal and planning advice should be sought early, particularly for heritage, flood, aviation and remediation-sensitive sites.
(f) to provide for flexibility in applying certain development standards, where compliance with such standards may be unreasonable or unnecessary in the circumstances of a particular development, and there is sufficient justification for varying the standards on environmental planning grounds.
The Dictionary at the end of this Plan defines words and expressions for the purposes of this Plan.
1 Notes
1 Notes
1.5 Notes
Notes in this Plan are provided for guidance and do not form part of this Plan.
1 Consent authority
1 Consent authority
1.6 Consent authority
The consent authority for the purposes of this Plan is (subject to the Act) the Council.
1 Maps
1 Maps
1.7 Maps
(1) A reference in this Plan to a named map adopted by this Plan is a reference to a map by that name—
(a) approved by the local plan-making authority when the map is adopted, and
(b) as amended or replaced from time to time by maps declared by environmental planning instruments to amend or replace that map, and approved by the local plan-making authority when the instruments are made.
(1AA) (Repealed)
(2) Any 2 or more named maps may be combined into a single map. In that case, a reference in this Plan to any such named map is a reference to the relevant part or aspect of the single map.
(3) Any such maps are to be kept and made available for public access in accordance with arrangements approved by the Minister.
(4) For the purposes of this Plan, a map may be in, and may be kept and made available in, electronic or paper form, or both.
Note.
The maps adopted by this Plan are to be made available on the NSW Planning Portal. Requirements relating to the maps are set out in the documents entitled Standard technical requirements for LEP maps and Standard requirements for LEP GIS data which are available on the website of the Department of Planning and Environment.
1 Repeal of planning instruments applying to land
1 Repeal of planning instruments applying to land
1.8 Repeal of planning instruments applying to land
(1) All local environmental plans and deemed environmental planning instruments applying only to the land to which this Plan applies are repealed.
(2) All local environmental plans and deemed environmental planning instruments applying to the land to which this Plan applies and to other land cease to apply to the land to which this Plan applies.
Note.
The following local environmental plan is repealed under this provision—
Armidale Dumaresq Local Environmental Plan 2008
cl 1.8: Am 2014 (341), Sch 1 [2].
1 Savings provision relating to development applications
1 Savings provision relating to development applications
1.8A Savings provision relating to development applications
If a development application has been made before the commencement of this Plan in relation to land to which this Plan applies and the application has not been finally determined before that commencement, the application must be determined as if this Plan had not commenced.
Note.
However, under Division 3.5 of the Act, a development application may be made for consent to carry out development that may only be carried out if the environmental planning instrument applying to the relevant development is appropriately amended or if a new instrument, including an appropriate principal environmental planning instrument, is made, and the consent authority may consider the application. The Division requires public notice of the development application and the draft environmental planning instrument allowing the development at the same time, or as closely together as is practicable.
cl 1.8A: Am 2019 (621), Sch 5[1].
1 Application of SEPPs
1 Application of SEPPs
1.9 Application of SEPPs
(1) This Plan is subject to the provisions of any State environmental planning policy that prevails over this Plan as provided by section 3.28 of the Act.
(2) The following State environmental planning policies (or provisions) do not apply to the land to which this Plan applies—
1 Suspension of covenants, agreements and instruments
1 Suspension of covenants, agreements and instruments
1.9A Suspension of covenants, agreements and instruments
(1) For the purpose of enabling development on land in any zone to be carried out in accordance with this Plan or with a consent granted under the Act, any agreement, covenant or other similar instrument that restricts the carrying out of that development does not apply to the extent necessary to serve that purpose.
(2) This clause does not apply—
(a) to a covenant imposed by the Council or that the Council requires to be imposed, or
(b) to any relevant instrument within the meaning of section 13.4 of the Crown Land Management Act 2016, or
(c) to any conservation agreement within the meaning of the National Parks and Wildlife Act 1974, or
(d) to any Trust agreement within the meaning of the Nature Conservation Trust Act 2001, or
(e) to any property vegetation plan within the meaning of the Native Vegetation Act 2003, or
(f) to any biobanking agreement within the meaning of Part 7A of the Threatened Species Conservation Act 1995, or
(g) to any planning agreement within the meaning of Subdivision 2 of Division 7.1 of the Act.
(3) This clause does not affect the rights or interests of any public authority under any registered instrument.
(4) Under section 3.16 of the Act, the Governor, before the making of this clause, approved of subclauses (1)–(3).
cl 1.9A: Am 2019 (621), Sch 5[2]–[4].
Part 2 Permitted or prohibited development
Part 2 Permitted or prohibited development
Part 2 Permitted or prohibited development
2 Land use zones
2 Land use zones
2.1 Land use zones
The land use zones under this Plan are as follows—
For the purposes of this Plan, land is within the zones shown on the Land Zoning Map.
2 Zone objectives and Land Use Table
2 Zone objectives and Land Use Table
2.3 Zone objectives and Land Use Table
(1) The Land Use Table at the end of this Part specifies for each zone—
(a) the objectives for development, and
(b) development that may be carried out without development consent, and
(c) development that may be carried out only with development consent, and
(d) development that is prohibited.
(2) The consent authority must have regard to the objectives for development in a zone when determining a development application in respect of land within the zone.
(3) In the Land Use Table at the end of this Part—
(a) a reference to a type of building or other thing is a reference to development for the purposes of that type of building or other thing, and
(b) a reference to a type of building or other thing does not include (despite any definition in this Plan) a reference to a type of building or other thing referred to separately in the Land Use Table in relation to the same zone.
(4) This clause is subject to the other provisions of this Plan.
Notes.
2
1
Schedule 1 sets out additional permitted uses for particular land.
2
2
Schedule 2 sets out exempt development (which is generally exempt from both Parts 4 and 5 of the Act). Development in the land use table that may be carried out without consent is nevertheless subject to the environmental assessment and approval requirements of Part 5 of the Act.
2
3
Schedule 3 sets out complying development (for which a complying development certificate may be issued as an alternative to obtaining development consent).
2
4
Clause 2.6 requires consent for subdivision of land.
2
5
Part 5 contains other provisions which require consent for particular development.
2 Unzoned land
2 Unzoned land
2.4 Unzoned land
(1) Development may be carried out on unzoned land only with development consent.
(2) In deciding whether to grant development consent, the consent authority—
(a) must consider whether the development will impact on adjoining zoned land and, if so, consider the objectives for development in the zones of the adjoining land, and
(b) must be satisfied that the development is appropriate and is compatible with permissible land uses in any such adjoining land.
2 Additional permitted uses for particular land
2 Additional permitted uses for particular land
2.5 Additional permitted uses for particular land
(1) Development on particular land that is described or referred to in Schedule 1 may be carried out—
(a) with development consent, or
(b) if the Schedule so provides—without development consent,
in accordance with the conditions (if any) specified in that Schedule in relation to that development.
(2) This clause has effect despite anything to the contrary in the Land Use Table or other provision of this Plan.
2 Subdivision—consent requirements
2 Subdivision—consent requirements
2.6 Subdivision—consent requirements
(1) Land to which this Plan applies may be subdivided, but only with development consent.
Notes.
(2) Development consent must not be granted for the subdivision of land on which a secondary dwelling is situated if the subdivision would result in the principal dwelling and the secondary dwelling being situated on separate lots, unless the resulting lots are not less than the minimum size shown on the Lot Size Map in relation to that land.
Note.
The definition of secondary dwelling in the Dictionary requires the dwelling to be on the same lot of land as the principal dwelling.
2
1
If a subdivision is specified as exempt development in an applicable environmental planning instrument, such as this Plan or State Environmental Planning Policy (Exempt and Complying Development Codes) 2008, the Act enables it to be carried out without development consent.
2
2
Part 6 of State Environmental Planning Policy (Exempt and Complying Development Codes) 2008 provides that the strata subdivision of a building in certain circumstances is complying development.
2 Demolition requires development consent
2 Demolition requires development consent
2.7 Demolition requires development consent
The demolition of a building or work may be carried out only with development consent.
Note.
If the demolition of a building or work is identified in an applicable environmental planning instrument, such as this Plan or State Environmental Planning Policy (Exempt and Complying Development Codes) 2008, as exempt development, the Act enables it to be carried out without development consent.
2 Temporary use of land
2 Temporary use of land
2.8 Temporary use of land
(1) The objective of this clause is to provide for the temporary use of land if the use does not compromise future development of the land, or have detrimental economic, social, amenity or environmental effects on the land.
(2) Despite any other provision of this Plan, development consent may be granted for development on land in any zone for a temporary use for a maximum period of 52 days (whether or not consecutive days) in any period of 12 months.
(3) Development consent must not be granted unless the consent authority is satisfied that—
(a) the temporary use will not prejudice the subsequent carrying out of development on the land in accordance with this Plan and any other applicable environmental planning instrument, and
(b) the temporary use
This is an opening excerpt, not the complete document.