This section gives a practical, stepwise compliance checklist grounded in the AD’s text. It does not substitute for engineering or regulatory advice but translates the AD’s requirements into action items that operators, CAMOs and maintenance organisations should follow.
Step 0 , Read and map applicability
- Consult the AD’s Applicability and Table 1. Confirm whether any aeroplane in your fleet has a Rockwell Collins TDR-94 or TDR-94D transponder with the listed current P/Ns (622-9352-007, -008, -108; 622-9210-007, -008, -108) and is equipped with a Honeywell AZ800 or AZ810 ADC that provides Selected Altitude to the transponder via the data bus interface. If the ADC is not supplying Selected Altitude, review Notes 3 and 4 to determine whether an exemption applies (honour the caveat that modifications enabling a digital link revoke the exemption).
Step 1 , Prioritise affected aircraft and create a compliance plan (timebox)
- The AD requires compliance for Requirement 1 within 60 days of commencement (commencement 10 September 2021). For each affected aircraft, create a slotting plan that identifies:
- whether you will pursue modification per Rockwell Collins SBs (Requirement 1.a) or replacement under an approved aeroplane modification (Requirement 1.b),
- parts procurement lead times for the chosen P/N,
- maintenance facility capacity and available dates,
- necessary approvals for aeroplane modifications (if replacement chosen),
- the need to address ADS-B function concurrently (Requirement 2 / Note 2).
Step 2 , Choose remediation route and document rationale
-
Option A , Modify per Rockwell Collins Service Bulletin (Requirement 1.a)
- Obtain the Rockwell Collins Service Bulletins referenced in Tables 2 and 3 that correspond to your current P/N. The tables identify SB references (e.g., TDR-94/94D-34-505, -506, -507) and map current to new P/N options. Remember the AD requires the SB “as in force from time to time” , obtain and record the current revision.
- Schedule the SB work with an approved maintenance organisation and document SB revision, maintenance release, and logbook entries.
-
Option B , Replace with listed new P/N under approved aeroplane modification (Requirement 1.b)
- Confirm available approved aeroplane modifications that authorise installation of P/N 622-9352-309/-409 or 622-9210-309/-409. If none exists, engage your design approval holder/CAMO to develop an approved modification.
- If choosing 409 variants, prepare to address Note 2: ADS-B must be disabled on P/N 409 units unless you can demonstrate compliance with EASA AMC 20-24 or CS-ACNS or FAA 14 CFR 91.225 and 91.227. If you need ADS-B enabled, document and assemble the required demonstration evidence (testing, manufacturer attestations, certification evidence).
- Schedule procurement and installation, and ensure maintenance release and approved modification paperwork are completed and retained.
Step 3 , Address ADS-B concurrently
- Requirement 2 requires action on ADS-B concurrent with the modification.
- If you are installing P/N 622-9352-409 or 622-9210-409 and do not have the necessary demonstration, ensure the ADS-B function is disabled at the time of the modification.
- If you intend to keep ADS-B enabled, gather the necessary evidence that demonstrates compliance with the listed EASA or FAA standards; document the method of demonstration and retain records for inspection. Confirm with CASA that your demonstration approach is acceptable if necessary.
Step 4 , Implement installation prohibition controls for spares (Requirement 3)
- After commencement, unmodified units identified in the Applicability must not be installed in affected ADC installations. Put inventory controls in place:
- Tag/segregate unmodified transponders that must not be installed in the specified ADC configuration.
- Update maintenance procedures and provide staff training and job cards to ensure unmodified spares are not mistakenly fitted.
- Record the modification status of each transponder serial number and P/N in the maintenance records.
Step 5 , Verify exemptions where claimed (Notes 3 and 4)
- If you seek to rely on the ATR or DHC-8 exemptions:
- Maintain documentation proving the original architecture does not supply Selected Altitude via the ADC (design drawings, type design notes, modification histories).
- If the aircraft has later modifications that enable a digital link between ADC and transponder, do not claim the exemption; comply with the AD.
Step 6 , Record evidence and update continuing airworthiness documentation
- For every action undertaken, retain:
- SB revision used and maintenance release documents,
- logbook entries recording the work and P/N changes,
- approved aeroplane modification paperwork if replacement route used,
- evidence of ADS-B compliance demonstration where relevant,
- records showing the date of compliance relative to the AD’s commencement and the 60-day window.
- Update CAMO records and continuing airworthiness documentation to reflect the change.
Step 7 , Operational planning for ADS-B impact
- If ADS-B is disabled on affected aircraft or transponders, coordinate with operations and route/airspace planning teams to confirm whether that affects access to routes or airspace that require ADS-B surveillance. If necessary, coordinate with ANSPs and CASA to identify mitigations (alternative surveillance or procedural measures).
Step 8 , Engage CASA proactively if you cannot meet the deadline
- The AD does not set out an extension mechanism. If you foresee inability to comply within 60 days due to parts shortage, maintenance capacity or other constraints, proactively contact CASA to request guidance, relief or to document mitigating steps. Maintain written evidence of your communications and remediation plan.
Step 9 , Post-compliance surveillance and maintenance
- Monitor the behaviour of modified or replacement transponders in service, and maintain records for potential follow-up (e.g., if a newer SB revision supersedes the current one). Because the AD ties SB and standards to “as in force from time to time”, operators should track further SB revisions and relevant EASA/FAA updates that could affect continued compliance or ADS-B enablement status.
Step 10 , Audit readiness
- Prepare for CASA oversight by assembling a compliance dossier per aircraft showing:
- identification of affected units,
- the remediation route selected and why,
- SB and modification documentation,
- maintenance release and logbook references,
- ADS-B compliance evidence or proof of disablement,
- inventory controls preventing reinstallation of unmodified units.
Concise checklist for a single aircraft
- Verify whether ADC provides Selected Altitude to the transponder. If not, verify exemption documented.
- If affected, decide: modify per SB (1.a) or replace under approved modification (1.b).
- If replacing with 409 P/N, determine whether you can demonstrate compliance with EASA/FAA ADS-B criteria; if not, plan to disable ADS-B.
- Schedule maintenance within 60 days; obtain current SBs; perform work and record SB revision.
- Update logbooks, CAMO records and parts inventory; ensure unmodified units cannot be reinstalled.
- Retain evidence for CASA audit.
Following these steps aligns an operator’s processes with the AD’s textual requirements and helps demonstrate compliance in a way CASA is likely to expect.