Compliance involves integrating the AD’s requirements into the operator’s continuing airworthiness management system. The following steps are practical guidance, assuming the operator is already familiar with CASR Part 42 and Part 145.
1. Identify affected propellers. Obtain a complete list of all aircraft in the operator’s fleet that have Hamilton Standard 14RF‑9, 14RF‑19 or 14RF‑21 propellers. This may require cross‑referencing aircraft type certificates with propeller serial numbers. Note that the AD does not exclude any serial numbers; all units of those models are covered.
2. Acquire and maintain the correct Hamilton Sundstrand MM. The AD references “the applicable Hamilton Sundstrand MM”. The operator must ensure they have the latest revision of that manual for each propeller model. The manual must include the torque procedure, acceptance criteria, FPI method, and lifting fixture instructions. If the manual is updated, the operator must update their compliance procedures accordingly. Keep a copy of the manual revision status in the propeller maintenance records.
3. Schedule initial compliance for new entrants. For any propeller that was not previously subject to AD/PHS/18 (e.g., newly imported, newly manufactured, or previously installed on a non‑Australian aircraft), the operator must:
- Within 30 days of the propeller entering service in Australia (or before flight, whichever comes sooner), perform the initial torque check (Requirement 1.(a)).
- If the torque check passes: loosen and re‑tighten the hub retaining nuts per Requirement 1.(e), then make the one‑time maintenance record entry per Requirement 1.(f).
- If the torque check fails: remove the propeller from service. Concurrently, perform the fluorescent penetrant inspection of the dowel pin holes. If cracks are found, remove the hub. If no cracks, the hub may be reused after the torque issue is rectified (likely by re‑torquing and possibly replacing nuts or washers).
- Record all actions in the propeller maintenance records.
4. Establish repetitive checks.
- 500‑hour torque check: Add this task to the approved maintenance program (AMP). The check should be performed every 500 flight hours from the last initial or repeat check. Ensure the engineer has access to the correct torque values and that the propeller is not loosened unless a failed check requires removal. Note: loosening and re‑tightening is not required at each 500‑hour check; only the torque is verified.
- 70‑hour oil leakage inspection: Add this task to the AMP as well. This is a simple visual inspection, but it must be formally scheduled. The engineer must investigate any leakage and determine the source. If the source is not one of the three exempted items, the propeller must be removed before further flight.
5. Manage propeller installations. When a propeller is installed (whether new, overhauled, or a spare), follow Requirement 3: use the tightening procedure from the MM and record the torque values. This may also trigger the one‑time loosening/re‑tightening if the propeller has never had it done (for example, a propeller that was previously operated without having had the initial action). Keep a log of installation dates and torque values.
6. Maintain records. The propeller maintenance records must contain:
- Evidence of the one‑time initial loosening/re‑tightening (if applicable), including torque values.
- For each 500‑hour torque check, a record of the torque values and an assessment of acceptability.
- For each 70‑hour oil leakage inspection, a record of the inspection and any findings.
- If a propeller is removed for non‑compliance, a record of the removal reason and the outcome of the FPI (if applicable).
These records should be kept for the life of the propeller and transferred with the propeller if it is sold or moved to another aircraft.
7. Train staff. Engineers performing the torque check must be familiar with the Hamilton Sundstrand MM and the specific lifting fixture. FPI must be performed by an NDT technician certified to the appropriate standard. Engineers performing the oil leakage inspection must know how to distinguish acceptable leaks (blade seal, pressure relief valve, actuator) from unacceptable leaks.
8. Monitor for manual revisions. The AD does not freeze the manual revision, so any change to the MM could affect torque values, inspection procedures, or acceptance criteria. The operator should subscribe to Hamilton Sundstrand service bulletins or subscribe to a revision‑tracking service. If the manual changes the tightening procedure, the operator must adopt it immediately to remain compliant.
9. Consider using a Part 145 AMO. Operators without in‑house capability should contract a Part 145‑approved maintenance organisation that holds the necessary scope for propeller work, including NDT. Ensure the contract clearly assigns responsibility for complying with this AD.
10. Document internal procedures. Create a written procedure that cross‑references the AD requirements to specific maintenance tasks in the AMP. This will assist during CASA audits and help avoid missed inspections or erroneous assumptions about one‑time versus repetitive tasks.