Step 1 , Plan and prioritise: Treat the AD as mandatory law effective from 18 April 2002 with a 120-day compliance window for Requirements 1-4. Operators should prioritise an immediate audit of fleet maintenance records to identify any installed cartridges that match the OAS part numbers and lot numbers in the AD’s chart. Because the AD’s applicability turns on part and lot numbers and on distribution during 1 April 1996 to 15 September 1997, the records audit must capture part numbers, lot numbers, purchase/supply dates and chain-of-custody information to establish provenance in line with the AD’s Note.
Step 2 , Maintenance records check (Requirement 1): Conduct a systematic review of aircraft maintenance logs, component histories and parts procurement records. Where records lack explicit lot numbers or distribution dates, seek supplier invoices, packing slips, previous maintenance organisation records, and any serviceable-tag documentation. If records are incomplete, adopt a conservative approach that errs on the side of identification and physical verification, since the AD requires removal of listed cartridges found installed.
Step 3 , Physical verification and tagging: For aircraft where records indicate possible presence of a listed cartridge, physically verify the cartridge part number and lot number on the component. Tag identified suspect cartridges and remove them from service per Requirement 2 within the 120-day period. Maintain a traceable chain-of-custody for removed parts (quarantine, tagging, storage or return to supplier) and log removal in maintenance records.
Step 4 , Inspections after prior discharge (Requirement 3): Where records show that a listed cartridge was previously installed and has been discharged in service, arrange inspection of the fire extinguisher discharge tube(s) for debris. The AD does not specify inspection techniques; consult Overland Aviation Services Service Bulletin 22-09-97 and FAA AD 2001-22-14 for technical guidance on inspection methods, and engage appropriately qualified maintenance engineers. Document inspection findings and any corrective actions taken.
Step 5 , Replacement sourcing (Requirement 4): Replace removed cartridges with cartridges that are not OAS part numbers referenced in the chart that were distributed during 1 April 1996 to 15 September 1997. Verify replacement parts by supplier certification, part numbers, lot numbers and distribution date records. If in doubt about a replacement’s provenance, obtain evidence in writing from the supplier that the part is not an OAS cartridge covered by the AD. Where manufacturers or WKA provide acceptable alternative part numbers or upgraded cartridges, obtain written confirmation of airworthiness and compatibility (including any necessary installation instructions) before fitting.
Step 6 , Prohibition on installation (Requirement 5): Implement operational controls to prevent installation of any OAS cartridge listed in the AD and distributed in the specified period from the effective date onward. Update parts procurement controls, maintenance work orders and parts stores inventory management to prevent accidental re-installation. Communicate the prohibition to all maintenance personnel, subcontractors and parts suppliers.
Step 7 , Record and evidence compliance: Although the AD does not prescribe a specific compliance-reporting format, maintain contemporaneous records demonstrating the steps taken: the maintenance records checks, evidence of removed part numbers and lot numbers, inspection reports for discharge tubes, replacement parts receipts and certifications, and date stamps showing completion within the 120-day window. These records will be the primary evidence of compliance in the event of CASA audit or inquiry.
Step 8 , Consult referenced guidance: Obtain and review FAA AD 2001-22-14 and Overland Aviation Services SB 22-09-97 to align inspection methodology and technical detail. Use the service bulletin and FAA AD to inform the inspection scope, debris removal procedures and any engineering recommendations for replacement cartridges or modifications. Coordinate with WKA (Firex) where necessary to confirm bottle assembly compatibility with replacement cartridges.
Step 9 , Manage operational impact: Plan maintenance windows that allow timely removals and replacements without creating undue disruption. For fleets with multiple affected aircraft, coordinate with maintenance providers early to secure parts and inspection capacity, given the 120-day deadline. Prioritise aircraft with records showing prior discharge, as they have an additional inspection duty.
Step 10 , Seek regulatory clarification if necessary: If an operator faces ambiguity (for example uncertain distribution provenance, replacement part acceptability, or technical inspection criteria), seek clarification from CASA or from the manufacturer (OAS/WKA) and retain written guidance. Because the AD does not prescribe penalties or exemptions in its text, documented regulatory or manufacturer guidance will help manage compliance risk.
Practical cautions: Do not assume that non-listed aircraft types are outside scope if a listed cartridge part/lot is fitted. Verify both part number and lot number. Keep removed cartridges segregated and documented. Ensure that procurement processes require supplier attestations regarding distribution dates and part origins when sourcing replacements.