What it does
Airworthiness Directive (AD) DHC-8/148 imposes a three-stage compliance obligation on operators of Bombardier DHC-8-400, 401, and 402 aeroplanes with serial numbers 4135 through 4149. The directive responds to a single reported failure of a tailstock shaft on an elevator power control unit (PCU) part number 390600-1007, where continued actuation of the failed PCU caused secondary damage to surrounding structure. Investigators attributed the failure to a material defect and identified 88 suspect PCUs by serial number.
Stage one requires a one-time identification check of all six installed elevator PCUs within 30 days of the effective date (2 July 2009). The operator must inspect the serial number of each PCU. If every installed PCU bears a suffix “A” after its serial number, or if none of the serial numbers falls within the listed suspect range (see requirement 1.a.), compliance is complete and no further action is required. The suffix “A” indicates the PCU has already passed a magnetic particle inspection and is cleared for continued use.
Stage two applies only if one or more of the installed PCUs has a serial number in the suspect range without the “A” suffix. In that case the operator must perform a daily check for correct operation of all installed elevator PCUs. The AD does not prescribe the exact procedures but notes that the daily check can be achieved by following Appendix A, B or C of Bombardier Q400 All Operator Message No. 217B, dated 26 April 2007. This daily check requirement ceases once stage three is accomplished.
Stage three requires removal of all suspect PCUs (those with serial numbers in the suspect range and without suffix “A”) and replacement with PCUs that either have a serial number outside the suspect list or carry the “A” suffix. Replacement must be completed within 2000 flight hours or 12 months after the effective date, whichever comes first. The AD accepts prior accomplishment of Bombardier Service Bulletin SB 84-27-32, original issue dated 1 May 2007, or Revision A dated 18 January 2008 (or later revisions approved by the Chief, Continuing Airworthiness of Transport Canada) as meeting the removal and replacement requirement.