This section sets out a step-by-step, source-grounded compliance checklist and operational considerations based solely on the AD text.
Immediate steps (within two weeks of effective date; Compliance 1)
- Suspend aerobatic flight.
- Action: Ensure all operators and pilots cease aerobatic flight for each DH 82/82A subject to the AD, within two weeks of 14 August 2014 as required by Compliance 1.
- Record: Log the suspension and date implemented.
Prioritisation and scheduling (Compliance 2(a)-(b))
- Identify whether the aircraft is used for commercial purposes as prescribed in regulation 206 of CAR 1988.
- Action: Classify the aircraft per reg 206 CAR 1988 to determine which initial completion deadline applies , commercial operators must comply by 30 October 2014; other operators by 31 December 2015.
- Record: Document the basis for classification and the scheduled date for completion.
Technical preparatory steps (Requirement 2(a)-(b))
- Obtain the referenced TNS and any other required approvals.
- Action: Acquire DHSL Technical News Sheet CT (Moth) No. 32, Issue 3, dated 1 December 2008, and ensure the maintenance and engineering team is familiar with Appendix G Figure 3 (installation of inspection rings and drainage provisions) and Appendix B paragraph 6 (inspection content).
- Rationale: The AD requires installations and inspections "in accordance with" these TNS provisions.
- Note: If any clarification or updated TNS content is needed, seek it from DHSL and verify any changes with CASA if necessary.
- Plan for installation of inspection rings and drainage provisions (Requirement 2(a)).
- Action: Schedule and resource installation in conformity with Figure 3 of Appendix G of the TNS. Confirm parts and fitment specifications with DHSL or approved suppliers.
- Considerations: Installation may require specialist fittings or approvals and could be the gating item for inspection access.
- Arrange access to internal wooden structure (Requirement 2(b)).
- Action: Either remove all pop-in panels or prepare to cut fabric from inside inspection rings to permit inspection of the entire internal wooden structure. Decide which access method is appropriate and obtain necessary materials and approval for any fabric cutting or re-covering.
- Record: Retain work orders and maintenance records that record the access method used, locations, and any subsequent restorative work.
Inspection and repair (Requirement 2(c)-(d))
- Perform a detailed inspection of internal wooden structure in accordance with the TNS inspection criteria.
- Action: Conduct the detailed inspection pursuant to Appendix B paragraph 6 of the TNS. Ensure inspectors are briefed on the specific inspection content and use appropriate inspection tools and techniques.
- Record: Produce an inspection report documenting the condition of each inspected element and reference the TNS inspection criteria applied.
- Remove or repair unserviceable wooden structure as required.
- Action: Remove any unserviceable wooden structure from service or effect repairs in accordance with "approved data" as required by Requirement 2(d). Confirm that repair data is formally approved and retain evidence of approval.
- Record: Document repair methodology, parts used, approval references, and test results where applicable.
Reporting (Requirement 3; Compliance 3)
- Report defects to CASA.
- Action: For any defects discovered during inspection, lodge a report to CASA using the Service Difficulty Reporting System in accordance with Part 4B - Defect Reporting of CAR 1988.
- Record: Keep copies of all Service Difficulty Reports and related correspondence.
Recurrent compliance (repetition clause)
- Implement the recurring inspection regime.
- Action: Repeat Requirement 2 inspections at the earlier of every 200 hours, within 36 months of the previous inspection, or after any ground strike, birdstrike or other wing strike of sufficient magnitude to leave witness marks on the fabric covering, or otherwise obvious damage to a wing. When an impact event occurs, inspect both top and bottom wings on the side where the impact occurred.
- Record: Maintain a schedule of next inspections tied to flight-hour counters and calendar intervals. Update records immediately after any qualifying event.
Operational resumption of aerobatics (Compliance 1)
- Re-allow aerobatic flight only when airworthiness has been established following Requirement 2.
- Action: Only permit aerobatic operations after the detailed inspection and any necessary repairs are complete and documented as satisfying the TNS inspection criteria and repair approvals.
Administrative and governance measures
- Centralise documentation and evidence of compliance.
- Action: Keep a compliance folder for each aircraft that includes TNS copies, inspection reports, installation records for inspection rings and drainage provisions, repair approvals and records, Service Difficulty Reports, and a traceable log of inspections and flight hours.
- Rationale: Because the AD ties compliance to external documents and approved data, verifiable documentation is necessary to demonstrate conformity.
- Liaise with CASA and DHSL where necessary.
- Action: If there is uncertainty about what constitutes an “approved” repair or how to apply the TNS, contact CASA or DHSL for guidance and retain written correspondence. For unusual damage scenarios, seek CASA guidance about whether additional actions are required beyond the AD.
- Maintenance planning and budgeting
- Action: Budget for the installation of inspection rings/drainage, potential re-covering of fabric, labour for invasive inspections, parts for repairs or replacement of wooden structure, downtime while inspections and repairs are carried out, and the cost of recurrent inspections at 200-hour or 36-month intervals.
- Rationale: The AD imposes both immediate and ongoing costs; planning reduces risk of non-compliance.
- Ensure pilots and operational staff are briefed
- Action: Circulate AD requirements to pilots, ops managers and event planners, emphasising the aerobatics suspension, the conditional nature of resumption, and the need to report any impact events that could trigger immediate inspections.
Compliance verification
- Internal audits: Schedule internal compliance audits to confirm that inspections are being performed per the TNS, repairs are backed by approved data, and defect reports are lodged correctly under Part 4B.
- External inspections: Be prepared for CASA oversight and to produce the records required to show compliance.
This compliance blueprint flows directly from the AD’s Requirements and Compliance sections and is designed to convert the AD’s prose into actionable operational steps while ensuring documentary evidence exists to demonstrate conformity with the AD and with Part 4B reporting obligations.