What it does
This Airworthiness Directive (AD/CESSNA 550/26) issued by the Civil Aviation Safety Authority (CASA) on 4 April 2006, effective 20 April 2006, mandates a sequence of mandatory actions on certain Cessna Model S550, 550 and 551 aeroplanes to address a reported risk of fuel vapour ignition in the wing fuel tanks. The mechanical effect is to impose two short-term, time-limited compliance actions and one longer-term investigative and corrective action, with a terminating action that removes the initial restrictions.
First, within 25 hours of time in service (TIS) after the effective date, operators must revise the Limitations Section of the applicable Cessna aircraft flight manual (AFM) to prohibit use of the wing fuel boost pumps for defueling under certain conditions. The revision is done by inserting a specific temporary change identified in Cessna Service Bulletin SB550-28-14 dated 2 December 2003, or by using a corresponding temporary change listed in a table within the AD that covers different AFM variants for Models 550 Citation Bravo and S550 Citation S/II (e.g. 55BFM TC-R10-07 through 55BFM TC-R10-09 for the Citation Bravo). Simultaneously, within the same 25-hour TIS window, operators must install a placard close to the fuel quantity gauge with lettering at least 6mm (one quarter inch) tall, using the accomplishment instructions of SB550-28-08 (7 May 2004), SB550-28-14 (2 December 2003), or SB550-28-15 (20 January 2004) as applicable.
Second, within 300 hours TIS after the effective date, operators must perform a detailed inspection for chafed wiring of the wing fuel boost pumps and modify those pumps. A detailed inspection is defined in Note 1 of the AD as an intensive examination of the specific item, installation or assembly, using supplementary lighting and inspection aids as necessary, with possible surface cleaning. If discrepancies are found during that inspection, operators must accomplish all applicable corrective and other specified actions in accordance with the relevant service bulletin before further flight. Finally, once the inspection and modification have been completed, operators must remove the AFM temporary change inserted under Requirement 1 and the placard installed under Requirement 2, and this removal must occur before further flight.