The AD defines a specific compliance pathway and schedules. The following is a stepwise compliance checklist based strictly on the AD’s text and timing language. Operators and maintenance providers must follow the Beechcraft SI No. 0448-211 at any FAA approved revision status to perform the technical work.
Step 1, confirm applicability
- Verify the aeroplane’s model and serial number against the AD’s Applicability table. The AD lists the exact serial-number ranges for Group 1 and Group 2. Only aircraft within those enumerated serial-number blocks are subject to the AD’s requirements.
Step 2, obtain the SI
- Obtain Beechcraft Service Instructions No. 0448-211 at an FAA approved revision status. The AD requires the SI at any FAA approved revision status as the method of compliance.
Step 3, perform the mandatory determination (Requirement 1)
- Using the SI, physically inspect each up-lock roller and determine whether it is the greasible type (inner race drilled and grooved) or non-greasible (solid inner race). Record the determination in maintenance records.
Step 4, react to the determination (Requirements 2 and “Before further flight” clause)
- If any up-lock roller is non-greasible, replace it with the greasible type as required by Requirement 2.
- The AD specifies that after the determination required by Requirement 1, any necessary replacement is to be completed “Before further flight.” Practically, if non-greasible rollers are found, the aircraft must not be flown further until replacements are installed.
Step 5, install hollow zerk-ended mounting bolts (Requirement 3)
- Install hollow zerk-ended mounting bolts on the up-lock rollers as required. Use the SI’s procedures to ensure proper removal, installation torque, and any compatibility checks.
Step 6, lubricate the up-lock mechanism (Requirement 4)
- Perform lubrication of the up-lock mechanism following the SI’s guidance. The AD sets initial and recurring intervals, which differ by applicability group:
- Group 1: initial compliance steps (determination, replacement where necessary, installation of zerk-ended bolts, and lubrication) are required “unless already accomplished, within 100 hours TIS after the effective date of this AD.” Additionally, lubrication is required “initially within 100 plus/minus 10 hours TIS, and repetitively thereafter, at intervals not to exceed 100 plus/minus 10 hours TIS.”
- Group 2: initial compliance steps are required “unless already accomplished, within 300 hours TIS after the effective date of this AD.” Lubrication is required “initially within 300 hours TIS, and repetitively thereafter, at intervals not to exceed 100 plus/minus 10 hours TIS.”
Step 7, scheduling and record-keeping
- Because the AD uses TIS windows and a “Before further flight” clause, schedule the inspections and parts procurement to meet the group-specific initial timing. Maintain records showing the date, TIS at the time of action, details of the SI revision used, part numbers of replacements, and the technician who completed the work. While the AD text does not specify record formats, demonstrable maintenance records will be essential to establish credit for “Unless already accomplished” and to show ongoing compliance with the recurrent lubrication intervals.
Step 8, parts, tools and technical personnel
- Ensure availability of greasible up-lock rollers and hollow zerk-ended mounting bolts that conform to the SI’s specifications. Ensure that maintenance personnel authorised to perform the work are familiar with SI No. 0448-211 and the AD’s timing requirements.
Step 9, contingency planning
- Because the AD’s “Before further flight” clause can ground an aircraft pending replacement, operators should identify supply chains for parts and maintenance slots to avoid operational disruption. If an operator believes an alternative method of compliance would be appropriate, the AD text provided does not set out an alternative compliance route; any pursuit of an alternative will require engagement with the regulator outside the AD’s text.
Step 10, monitor for updates
- The AD permits the use of SI No. 0448-211 at any FAA-approved revision status. Monitor FAA and Beechcraft releases to ensure the SI revision used remains FAA-approved. Also monitor the regulator’s AD register for any amendments, supersessions or related directives.
Timing examples derived from the AD’s effective date wording
- Effective date is 7 June 2007. For a Group 1 aeroplane, unless already accomplished, the initial determination and required actions would need to be completed within 100 hours TIS from that date. For a Group 2 aeroplane, initial completion is within 300 hours TIS from the effective date. Thereafter, lubrication must occur on the 100 ±10 hours TIS cadence specified.
In short, compliance requires (1) determining roller type using the SI, (2) replacing non-greasible rollers with greasible ones, (3) installing hollow zerk-ended bolts, (4) performing and scheduling recurring lubrication at the specified TIS intervals, and (5) maintaining maintenance records showing the SI revision used and what was accomplished. All actions must be performed in accordance with Beechcraft SI No. 0448-211 at an FAA-approved revision status and within the TIS windows and “before further flight” constraints set out in the AD.