Compliance with AD/A320/180 Amdt 2 requires a structured plan that integrates into the operator’s continued airworthiness management system. The steps below assume the aircraft is on the applicability list and does not already have SB A320‑28‑1149. If the aircraft does have that SB, the AD does not apply; record that fact in the compliance status.
Step 1: Confirm applicability and effective date. Check the aircraft MSN against the 179 listed numbers. If the MSN is listed, the AD applies as of 30 April 2007. If the aircraft also has SB A320‑28‑1149 incorporated, it is excluded. Verify incorporation status and record why the AD is not applicable if appropriate.
Step 2: Insert MMEL TR within 10 days (by 10 May 2007). Locate the MMEL for the aircraft type. Insert Temporary Revision No 01‑28/01Z issue 01 (the one referenced by the AD). The TR prohibits flight with one pump inoperative. Ensure the flight crew is briefed and the MEL is updated. Record the insertion in the aircraft logbook or equivalent. This step should be completed immediately if the AD was not actioned earlier.
Step 3: Schedule pump and canister inspection within 600 flight hours. Arrange for a licensed maintenance organisation (LAME) to perform Requirement 3 inspection per Airbus SB A320‑28‑1102 Revision 2 (or later DGAC‑approved revision). The inspection covers all four wing pumps and their canisters. If the aircraft already incorporates Revision 1 of that SB, Requirement 3 is considered compliant; record that and move to Step 4. If not, the inspection must be done within 600 FH of 30 April 2007. Plan for possible part replacement or rectification per the SB. Document findings.
Step 4: Establish repetitive fuel tank inspection program. Determine the applicable interval based on SB A320‑57‑1117 incorporation status:
- If the aircraft has not incorporated any revision of SB A320‑57‑1117, the initial inspection (Requirement 5) must be done by 30 July 2011 (or earlier if flight hours accumulate quickly), and then repeat every 600 FH until terminating action.
- If the aircraft has incorporated Revision 1 or 2 (or later DGAC‑approved revision), the repetitive interval is 3,000 FH. The initial inspection deadline remains the same.
Step 5: Plan for terminating action (Requirement 6). Procure the new fuel strainers per Airbus SB A320‑28‑1149 original issue or later DGAC‑approved revision. Install them by 30 July 2011 (or 162 months from first entry into service for the three specified MSNs). This modification ends the repetitive inspection requirement. Confirm installation in the aircraft logbook and stamp the AD as having terminating action accomplished.
Step 6: Update the AD compliance schedule. After Requirement 6 is accomplished, the AD is fully complied with. However, the operator should ensure that the MMEL TR is still in effect (it may be superseded by a general MMEL revision). Check with the MEL provider.
Step 7: Handle pump failures reactively. If a fuel pump fails at any time after effective date, before further flight comply with Requirement 2: inspect the failed pump, the companion pump, and both canisters per SB A320‑28‑1102 Rev 2, and rectify per instructions. This applies even after terminating action, because the AD does not remove Requirement 2; only Requirement 4 stops. However, after terminating action, a pump failure may not generate label‑related debris, but the AD still requires the inspection. The likely interpretation is that the inspection is to check for label ingestion; if the labels are removed by the strainer, the risk is lower, but the AD text does not exempt Requirement 2 after terminating action. Therefore, operators should still comply.
Step 8: Maintain records. For each compliance action, record the date, flight hours (where applicable), service bulletin revision used, findings, rectifications, and person certifying. Keep these records accessible for CASA audit.
Cost considerations: The major cost items are: labour for pump inspection (approx 4‑8 hours), labour for tank inspection (10‑20 hours, includes tank entry), strainer parts (moderate cost), potential pump or canister replacements if damage found, and aircraft downtime. The terminating action may require a dedicated maintenance input. The repetitive inspection regime favours early incorporation of SB A320‑57‑1117 to get the 3,000‑hour interval, and early installation of strainers to end inspections altogether. The operator should perform a cost‑benefit analysis: if the aircraft is near the 30 July 2011 deadline, performing the strainer installation early may reduce ongoing inspection costs. If the aircraft has many MSNs, a fleet‑wide approach may be more efficient.
Compliance verification: Use an AD compliance matrix tracking each requirement, completion date, and next due date (for repetitive items). After terminating action, mark the AD as closed. Any future maintenance actions related to pump failure should still reference this AD.
Finally, note that this AD is now over 17 years old. Many aircraft subject to it will already have the strainer installed. The primary risk now is for aircraft that have not yet accomplished terminating action and are still subject to repetitive inspections. For those, immediate scheduling of Requirement 6 is prudent.