39 An entity shall disclose:
(a) the amount of contract revenue recognised as revenue in the period;
(b) the methods used to determine the contract revenue recognised in the period; and
(c) the methods used to determine the stage of completion of contracts in progress.
40 An entity shall disclose each of the following for contracts in progress at the end of the reporting period:
(a) the aggregate amount of costs incurred and recognised profits (less recognised losses) to date;
(b) the amount of advances received; and
(c) the amount of retentions.
41 Retentions are amounts of progress billings that are not paid until the satisfaction of conditions specified in the contract for the payment of such amounts or until defects have been rectified. Progress billings are amounts billed for work performed on a contract whether or not they have been paid by the customer. Advances are amounts received by the contractor before the related work is performed.
42 An entity shall present:
(a) the gross amount due from customers for contract work as an asset; and
(b) the gross amount due to customers for contract work as a liability.
43 The gross amount due from customers for contract work is the net amount of:
(a) costs incurred plus recognised profits; less
(b) the sum of recognised losses and progress billings;
for all contracts in progress for which costs incurred plus recognised profits (less recognised losses) exceeds progress billings.
44 The gross amount due to customers for contract work is the net amount of:
(a) costs incurred plus recognised profits; less
(b) the sum of recognised losses and progress billings;
for all contracts in progress for which progress billings exceed costs incurred plus recognised profits (less recognised losses).
45 An entity discloses any contingent liabilities and contingent assets in accordance with AASB 137 Provisions, Contingent Liabilities and Contingent Assets. Contingent liabilities and contingent assets may arise from such items as warranty costs, claims, penalties or possible losses.