Contract Costs
16 Contract costs shall comprise:
(a) costs that relate directly to the specific contract;
(b) costs that are attributable to contract activity in general and can be allocated to the contract; and
(c) such other costs as are specifically chargeable to the customer under the terms of the contract.
17 Costs that relate directly to a specific contract include:
(a) site labour costs, including site supervision;
(b) costs of materials used in construction;
(c) depreciation of plant and equipment used on the contract;
(d) costs of moving plant, equipment and materials to and from the contract site;
(e) costs of hiring plant and equipment;
(f) costs of design and technical assistance that is directly related to the contract;
(g) the estimated costs of rectification and guarantee work, including expected warranty costs; and
(h) claims from third parties.
These costs may be reduced by any incidental income that is not included in contract revenue, for example, income from the sale of surplus materials and the disposal of plant and equipment at the end of the contract.
18 Costs that may be attributable to contract activity in general and can be allocated to specific contracts include:
(a) insurance;
(b) costs of design and technical assistance that are not directly related to a specific contract; and
(c) construction overheads.
Such costs are allocated using methods that are systematic and rational and are applied consistently to all costs having similar characteristics. The allocation is based on the normal level of construction activity. Construction overheads include costs such as the preparation and processing of construction personnel payroll. Costs that may be attributable to contract activity in general and can be allocated to specific contracts also include borrowing costs.
Aus18.1 In respect of not-for-profit public sector entities, costs that may be attributable to contract activity in general and can be allocated to specific contracts also include borrowing costs only when the contractor capitalises borrowing costs in accordance with AASB 123 Borrowing Costs.
19 Costs that are specifically chargeable to the customer under the terms of the contract may include some general administration costs and development costs for which reimbursement is specified in the terms of the contract.
20 Costs that cannot be attributed to contract activity or cannot be allocated to a contract are excluded from the costs of a construction contract. Such costs include: